# Davis-Bacon restitution: the corrected payroll, proof of payment and who gets the money

This page covers the federal rule on restitution and the correction procedure in HUD-assisted and Navy work. The sources are [29 CFR 5.10](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.10), [5.9](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9) and [5.5](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5), and HUD's [Handbook 1344.1, chapter 5](https://www.hud.gov/sites/dfiles/OCHCO/documents/13441C5SECH.pdf).

Last reviewed November 6, 2026 against the sources it cites

The short answer

Restitution is the difference between the rate required on the wage determination and the rate you paid, times the hours affected, plus interest on contracts entered into after October 23, 2023. HUD's handbook and the Navy's guide have you report restitution on a corrected payroll with a signed Statement of Compliance. What proof of payment the agency wants depends on the agency, so read its written instructions.

- [29 CFR 5.10(a)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.10) says interest runs from the date of the underpayment, uses the rate for underpaid taxes under 26 U.S.C. 6621, and is compounded daily, in text added by the August 2023 rule, which the [final rule](https://www.federalregister.gov/citation/88-FR-57526) applies only to new contracts entered into after October 23, 2023.
- The [HUD Handbook 1344.1 (January 2023)](https://www.hud.gov/sites/dfiles/OCHCO/documents/13441C5SECH.pdf) computes restitution as hours worked times the adjustment rate, or total wages earned minus total wages paid.
- The same [HUD handbook](https://www.hud.gov/sites/dfiles/OCHCO/documents/13441C5SECH.pdf) says an employer need only submit a correction payroll to evidence restitution paid, with no copies of checks or employee receipts required during basic enforcement.
- A 2007 [NAVFAC contractor guide](https://agc.org/system/files/resources/dba_contractor_guide_Aug_07.pdf) (copy hosted by AGC) required a signed employee receipt or a copy of the cancelled check as evidence of receipt, so guidance differs by agency and year.
- [29 CFR 5.9(b)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9) lets back wages be withheld under any other federal contract with the same prime contractor, or any other federally assisted Davis-Bacon contract it holds, in text the [2023 final rule](https://www.federalregister.gov/citation/88-FR-57526) applies only to new contracts entered into after October 23, 2023.

## What restitution is and who it goes to

When violations of the labor standards clauses in 5.5 underpay workers, or cause monetary damages under 5.5(a)(11) or (b)(5), [29 CFR 5.10(a)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.10) says the federal agency or an authorized Department of Labor representative "will request that restitution be made to such workers or on their behalf to plans, funds, or programs for any type of bona fide fringe benefits." So the money goes to the workers, and unpaid fringe benefits go to the fringe benefit plan, fund or program.

For contracts entered into after October 23, 2023, the restitution includes interest from the date of the underpayment. Section 5.10(a) sets the rate as the one used for underpayment of taxes under 26 U.S.C. 6621, compounded daily. Under 5.10(b), willful violations of a criminal statute can be forwarded to the Attorney General.

The eCFR showed these sections as up to date as of November 3, 2026 (5.9), November 5, 2026 (5.5) and November 10, 2026 (5.10). Both 5.9 and 5.10 carry the August 23, 2023 amendment citations (88 FR 57740 and 57741), including the cross-withholding in 5.9(b) and the daily-compounded interest in 5.10(a) as they read now. The [final rule](https://www.federalregister.gov/citation/88-FR-57526) says that, with the exception of § 1.6(c)(2)(iii), the remaining provisions of parts 1, 3 and 5 apply only to new contracts entered into after October 23, 2023. For contracts entered into before that date, the terms of those contracts and the regulations in effect when they were entered into continue to govern. So the daily-compounded interest in 5.10(a) and the cross-withholding in 5.9(b) and (c) as they read now apply to contracts entered into after October 23, 2023. Read your own contract's interest and withholding wording. Our guide on [responding to a findings letter](https://wellstanding.com/guides/davis-bacon-findings-letter-response-alj-hearing/) covers disputes.

## Step 1: Work out the back wages for each worker

The regulation gives no formula, but HUD's handbook gives two equivalent methods:

1. Total hours worked times the adjustment rate, which is the Davis-Bacon rate minus the rate paid.
2. Total wages earned minus total wages paid.

Wages earned means the rate for the classification actually performed times covered hours, which matches [5.5(a)(1)(i)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5), which requires the full basic hourly wage and bona fide fringe benefits for the classification actually performed.

### Three cases with their own arithmetic

| Situation | How HUD's handbook computes it |
| --- | --- |
| Apprentices over the allowed ratio, or not registered | Use the wage rate on the wage decision for the work actually done. Of five apprentices where the plan allows three, the first three are in the quota and the last two are owed restitution. If you cannot tell who started first, the handbook accepts any equitable formula, such as rotating three of the five. |
| Overtime under the [Contract Work Hours and Safety Standards Act](https://wellstanding.com/guides/cwhssa-overtime-liquidated-damages/) | One and one-half times the basic rate, plus the straight-time rate of any required fringe benefits, times the overtime hours. The half-time premium is not applied to fringe benefits. |
| Liquidated damages for unpaid overtime | Owed to the United States, not to the worker. [5.5(b)(2)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5) sets $33 per employee for each calendar day over the 40-hour week without the overtime pay, in the current eCFR clause text. HUD's handbook says DOL adjusts the amount annually and its example uses $27 at 2021 rates, so check the clause in your own contract. |

If the cause is a lost apprenticeship registration, see our guide on [apprenticeship registration lapses](https://wellstanding.com/guides/davis-bacon-apprentice-registration-lapse/).

## Step 2: Pay the workers and report it on a corrected payroll

HUD's handbook says restitution is made promptly, in full, less permissible and authorized deductions, and documented on a correction payroll. In the handbook's process, an employer who agrees to pay is told to compute and pay the back wages and submit the corrected payroll within 30 days.

The correction payroll shows the earlier payrolls or period covered, for example payrolls 1 through 6, or a start and end date. For each worker it lists:

- the work classification;
- the total hours involved;
- the adjustment rate, which is the required rate minus the rate paid;
- the gross restitution due, the deductions and the net amount paid.

A properly executed Statement of Compliance must go with it. Under [5.5(a)(3)(ii)(C)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5) that statement certifies that each worker has been paid the full weekly wages earned and not less than the required rates and fringe benefits. Paragraph (E) requires an original handwritten or a legally valid electronic signature, and paragraph (F) says falsifying the certification can bring prosecution under 18 U.S.C. 1001 and 31 U.S.C. 3729. Our guide on the [HUD statement of compliance signature](https://wellstanding.com/guides/hud-statement-of-compliance-signature/) covers who may sign.

California corrections follow a different process, see our California guide, [amending a certified payroll in California](https://wellstanding.com/guides/correct-certified-payroll-report/).

## What proof of payment the agency wants

Federal sources differ here, and the difference follows the agency.

| Source | Proof it asks for |
| --- | --- |
| HUD Handbook 1344.1, January 2023, section 5-11 | The correction payroll alone. Copies of checks, cancelled checks, signed receipts and employee signatures on the payroll are not required during basic enforcement. |
| HUD Labor Relations Desk Guide LR01.DG, [January 2012, as posted by NYC HPD](https://www.nyc.gov/assets/hpd/downloads/pdfs/services/contractors-guide-davis-bacon.pdf), section 2-8 | The same: no employee signatures, check copies or signed receipts, except in the most extraordinary cases. |
| [NAVFAC contractor guide (August 2007), copy hosted by AGC](https://agc.org/system/files/resources/dba_contractor_guide_Aug_07.pdf), section 2-10 | A restitution receipt signed by the employee, or a copy of both sides of the cancelled check. |

The Department of Labor's own restitution guidance was not readable for this page. To resolve the difference, ask the contracting officer or contract administrator which proof they require and get it in writing. Keep copies of checks and receipts anyway. Under [5.5(a)(3)(i)(A)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5) payroll records must be preserved for at least 3 years after all work on the prime contract is complete.

## After you submit: review, shortfalls and 30 days

HUD's handbook says the agency computes what is due itself and compares it with your correction payroll. If you underpaid, it notifies you and you must make additional payments, shown on another correction payroll, within 30 days. It also says that if violations are not corrected within 30 days of notice to the prime contractor, the agency may withhold from payments due the contractor the amount needed to ensure full restitution. If you disagree with the findings, see [responding to a findings letter](https://wellstanding.com/guides/davis-bacon-findings-letter-response-alj-hearing/).

## Who pays: the prime contractor is on the hook

For contracts entered into after October 23, 2023, [5.9(a)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9) lets the agency, and on written request from the Department of Labor requires it to, suspend payment until enough is withheld to cover wages, monetary relief, liquidated damages and interest. For contracts entered into after October 23, 2023, section 5.9(b) allows the necessary funds to be withheld under "any other Federal contract with the same prime contractor, or any other federally assisted contract that is subject to Davis-Bacon labor standards and/or the Contract Work Hours and Safety Standards Act and is held by the same prime contractor." For those contracts, under [5.9(c)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9), cross-withholding from a different legal entity requires that entity's contract to contain the withholding provisions. Also, 5.5(a)(2)(ii) gives the Department priority over claims by sureties, bankruptcy trustees and others. HUD's 2012 guide says the prime contractor is held liable for restitution owed to workers of its subcontractors and lower-tier subcontractors. HUD's handbook tells the agency to send its determination to the prime contractor with notice of its responsibility to ensure correction.

## Workers you cannot find

Section 5.10 does not say what happens to restitution for a worker who cannot be located. The agency guidance does, and it varies:

- **HUD, January 2023:** the amount due to any worker who is entitled to restitution and is not paid for any reason goes into a deposit or labor standards escrow account as a condition for final closing.
- **HUD, January 2012:** after paying everyone you could find, you submit a list of unfound workers with names, Social Security numbers, last known addresses and gross amounts due. The prime contractor places that total in a deposit or escrow account at the end of the project, the contract administrator keeps looking for 3 years, and any remainder is then credited or forwarded to HUD.
- **Navy, 2007:** you provide evidence the worker could not be located, such as a returned envelope, and the amount is deducted from money owed to you and forwarded to the General Accountability Office for direct payment to the worker or retention by the government.

The HUD handbook (January 2023) also lets the agency allow closing on condition of a deposit to the U.S. Treasury of funds sufficient to meet any wage restitution that has been or may be found due, in its final closing clearance section. Document your search for each worker, ask the agency which procedure applies, and see the [closeout guide](https://wellstanding.com/guides/davis-bacon-final-certified-payroll-closeout/).

We prepare certified payroll for public works contractors. Tell us about your project.

## Questions

**Is there interest on Davis-Bacon back wages?**

Yes, for contracts entered into after October 23, 2023. [29 CFR 5.10(a)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.10) says restitution includes interest from the date of the underpayment, calculated at the 26 U.S.C. 6621 rate and compounded daily. For earlier contracts, the contract terms and the regulations in effect when it was entered into govern, per the [final rule](https://www.federalregister.gov/citation/88-FR-57526).

**Do I have to send the agency copies of the checks?**

It depends on the agency. HUD's 2023 handbook says the correction payroll is enough during basic enforcement. A 2007 Navy guide required a signed receipt or cancelled check. Ask for the requirement in writing.

**Does the corrected payroll need a signed Statement of Compliance?**

Yes, according to HUD's handbook, which says a properly executed statement must accompany the correction payroll. The signer is the contractor or its agent who pays or supervises payment, under [5.5(a)(3)(ii)(C)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5).

**What if a worker cannot be found?**

The agency guidance sends the unpaid amount to a deposit or escrow account, or in the Navy's 2007 guide to the General Accountability Office. Section 5.10 itself is silent on it. Keep proof of your search.

**Can the agency take restitution from another job of mine?**

Often, yes, on contracts entered into after October 23, 2023. [29 CFR 5.9(b)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9) allows withholding under "any other Federal contract with the same prime contractor, or any other federally assisted contract that is subject to Davis-Bacon labor standards" held by the same prime contractor. Your own contract's withholding clause controls.

**Is the California correction process the same?**

No. California corrections are covered in our [California amendment guide](https://wellstanding.com/guides/correct-certified-payroll-report/). The steps here come from federal rules and agency guidance.

## Sources

Every figure on this page links to its source where it first appears. The full list, in order:

1. [29 CFR 5.10](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.10) ecfr.gov
2. [5.9](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9) ecfr.gov
3. [5.5](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5) ecfr.gov
4. [Handbook 1344.1, chapter 5](https://www.hud.gov/sites/dfiles/OCHCO/documents/13441C5SECH.pdf) hud.gov
5. [final rule](https://www.federalregister.gov/citation/88-FR-57526) federalregister.gov
6. [NAVFAC contractor guide](https://agc.org/system/files/resources/dba_contractor_guide_Aug_07.pdf) agc.org
7. [January 2012, as posted by NYC HPD](https://www.nyc.gov/assets/hpd/downloads/pdfs/services/contractors-guide-davis-bacon.pdf) nyc.gov

## Related

- [Davis-Bacon apprenticeship registration lapse](https://wellstanding.com/guides/davis-bacon-apprentice-registration-lapse/)
- [Davis-Bacon final certified payroll closeout](https://wellstanding.com/guides/davis-bacon-final-certified-payroll-closeout/)
- [Davis-Bacon findings letter response](https://wellstanding.com/guides/davis-bacon-findings-letter-response-alj-hearing/)
- [HUD statement of compliance signature](https://wellstanding.com/guides/hud-statement-of-compliance-signature/)
- [Amending a certified payroll in California](https://wellstanding.com/guides/correct-certified-payroll-report/)