# Davis-Bacon back wages withheld from your contract payment: what happens next

This page covers payment holds on federal and federally assisted construction contracts under the Davis-Bacon labor standards clauses. It rests on the Department of Labor's rules at [29 CFR 5.9](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9), [5.5](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5) and [5.11](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.11), read on the eCFR, and on [DOL's August 23, 2023 final rule](https://www.govinfo.gov/content/pkg/FR-2023-08-23/html/2023-17221.htm).

Last reviewed November 6, 2026 against the sources it cites

The short answer

On contracts entered after October 23, 2023 (earlier ones keep the older clause), 29 CFR 5.9 lets the agency suspend payment on its own, and requires it when the Department of Labor asks in writing, until enough is withheld to cover back wages. The hold can reach your other federal jobs. A timely response makes findings inoperative if facts are disputed; on a no-facts ruling, petition the Board.

- On contracts entered after October 23, 2023, [29 CFR 5.9(a)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9) says the agency may suspend payment on its own action and must on the written request of an authorized Department of Labor representative, until the violations are discontinued and/or enough is withheld to cover wages, monetary relief, liquidated damages and interest.
- Under [29 CFR 5.9(b)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9), money can also be withheld from any other federal or federally assisted contract subject to Davis-Bacon or CWHSSA that the same prime contractor holds, whichever agency awarded it.
- On contracts entered after October 23, 2023, [section 5.9(c)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9) says cross-withholding from a different legal entity's contract is not appropriate unless that contract carries the withholding provisions in full or by reference.
- On contracts entered after October 23, 2023, the Department has priority to withheld funds over your surety, the agency's reprocurement costs, a bankruptcy trustee, your assignees, your successors and Prompt Payment Act claims ([29 CFR 5.5(a)(2)(ii)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5)).
- A timely hearing request, a factual response that the Administrator refers to an ALJ, or an ARB petition makes the findings inoperative until an ALJ or the Administrative Review Board upholds them, and a ruling that no facts are disputed needs a petition within 30 days ([29 CFR 5.11](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.11)).
- DOL's rule says its provisions are applicable only to contracts entered into after October 23, 2023 ([Federal Register, August 23, 2023](https://www.govinfo.gov/content/pkg/FR-2023-08-23/html/2023-17221.htm)).

## Who can hold your payment

Under [29 CFR 5.9(a)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9), the federal agency "(and any other agency)" "may, upon its own action, or must, upon written request of an authorized representative of the Department of Labor," act to suspend "the payment, advance, or guarantee of funds." The suspension runs until the violations are discontinued "and/or" until enough is withheld to cover wages, monetary relief, liquidated damages, and interest. WHD, the Department's Wage and Hour Division, is the enforcement agency ([DOL's 2023 preamble](https://www.govinfo.gov/content/pkg/FR-2023-08-23/html/2023-17221.htm)).

The hold is sized to the liability, not the contract. The clause in [29 CFR 5.5(a)(2)(i)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5) reaches "so much of the accrued payments or advances as may be considered necessary" to cover the liabilities of the prime contractor "or any subcontractor."

| What the letter says | Provision | Who acts |
| --- | --- | --- |
| Payment suspended until violations stop or enough is withheld | 5.9(a) | The agency on its own action; it must on DOL's written request |
| Accrued payments withheld for wages, interest, overtime liquidated damages | 5.5(a)(2)(i), (b)(3)(i) | Same |
| Further payment suspended for missing records or refused worker interviews | 5.5(a)(2)(i), (a)(3)(iv)(B) | The agency, after written notice |

If you are a subcontractor, the agency withholds from the contractor it pays, to cover the liabilities of the prime or any subcontractor. [Section 5.5(a)(6)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5) makes the prime and any responsible subcontractor "liable for any unpaid wages and monetary relief, including interest" owed to lower-tier workers. The contract clause is filled in with the agency or the recipient of Federal assistance, so read your contract to see who is named. See our [housing authority](https://wellstanding.com/guides/housing-authority-certified-payroll/) and State Revolving Fund guides.

## What the held money covers

Wages come with interest: [5.5(a)(1)(vi)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5) says the contractor "will be required to pay interest on any underpayment of wages." Liquidated damages come from the overtime clause. On a contract over $100,000 subject to the [Contract Work Hours and Safety Standards Act](https://wellstanding.com/guides/cwhssa-overtime-liquidated-damages/) (CWHSSA), 5.5(b)(2) sets them for each worker and each calendar day of unpaid overtime past 40 hours in a workweek. The eCFR figure is $33. It was $31 until [January 2024](https://www.federalregister.gov/citation/89-FR-1815), then $32 until [January 2025](https://www.federalregister.gov/citation/90-FR-1859), in DOL's annual inflation adjustments.

## Missing certified payrolls can stop payment too

A hold does not need a wage finding. Clause 5.5(a)(2)(i) lets the agency, "on its own initiative and after written notice," suspend further payment "upon the contractor's failure to submit the required records." Paragraph (a)(3)(iv)(B) adds refusing worker interviews on the job. The required records are those in (a)(3)(i) through (iii), which include the weekly certified payrolls with their signed Statement of Compliance. The suspension lasts "until such violations have ceased."

Failing to produce records on request "may be grounds for debarment action," and records not produced within the time WHD sets cannot later be introduced as evidence in a part 6 hearing. WHD considers a reasonable request for more time, judged on factors such as the location and volume of the records. The prime must submit every subcontractor's payrolls ([5.5(a)(3)(ii)(A)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5)). Certified payrolls are due weekly for each week of covered work, and the clause sets no grace period. See our guides to [WHD investigations](https://wellstanding.com/guides/davis-bacon-wage-and-hour-investigation/), [debarment](https://wellstanding.com/guides/davis-bacon-debarment/), and the [WH-347](https://wellstanding.com/guides/wh-347/).

## Cross-withholding: your other federal jobs

[Section 5.9(b)](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9) lets funds be withheld under "any other Federal contract with the same prime contractor," or any other federally assisted contract subject to Davis-Bacon or CWHSSA that the same prime holds, "regardless of whether the other contract was awarded or assisted by the same agency."

"Same prime contractor" is wider than one company. [29 CFR 5.2](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.2) counts controlling shareholders or members, joint venturers or partners, and a contractor delegated "all or substantially all" of the construction, and for sections 5.5 and 5.9 "related entities holding different prime contracts are considered to be the same prime contractor." For contracts entered after October 23, 2023, section 5.9(c) then limits reach into a different legal entity's contract: it is "not appropriate unless the withholding provisions were incorporated in full or by reference," and, absent exceptional circumstances, not permitted where Davis-Bacon applies only by operation of law.

## Who is paid, and who ranks behind the workers

[40 U.S.C. 3144(a)(1)](https://www.law.cornell.edu/uscode/text/40/3144) says the Secretary of Labor "shall pay directly to laborers and mechanics from any accrued payments withheld" the wages found due. The preamble says WHD pays out after any challenge is resolved and sends unclaimed funds to the Treasury after 3 years. On contracts entered after October 23, 2023, others rank behind the Department: 5.5(a)(2)(ii) gives it priority over claims to the funds by your sureties, the agency for reprocurement costs, a bankruptcy trustee or estate, your assignees, your successors, and Prompt Payment Act claims.

## Your 30 days under 29 CFR 5.11

[Section 5.11](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.11) covers disputes over wage rates, overtime, classification, and relief for retaliation. Your contract's general disputes clause does not: 5.5(a)(9) sends labor standards disputes to DOL's procedures.

| If WHD's notification says | What you must do | By when |
| --- | --- | --- |
| Facts are at issue (5.11(b)) | Ask for a hearing in writing, naming each disputed finding, your reasons, and any affirmative defenses. An administrative law judge hears it. | Sent within 30 days of the notification date |
| No facts at issue, with a ruling on law (5.11(c)) | If you dispute the facts, say which, in detail, with documents. To contest a ruling, petition the Administrative Review Board, with a copy to WHD. | 30 days from the notification; petition within 30 days of the ruling |

No timely response or petition makes the findings final (5.11(d)), and on debarment the Administrator advises the Comptroller General. A timely hearing request or factual response makes them "inoperative unless and until the decision is upheld" by the judge or the Board. If the Administrator finds no relevant issue of fact and rules, you must petition the Board within 30 days of the ruling. Count from the date on the letter: the rule says "sent within 30 days of the date of the Administrator's notification."

Disputing contractors get a hearing and appeal "before any withheld funds are disbursed to workers," the preamble says, so withheld funds are not paid to workers until that process ends. If you win, WHD asks the agency to release the funds.

## Which version applies to your contract

DOL's 2023 rule took effect October 23, 2023. Its provisions are "applicable only to contracts entered into after October 23, 2023," with limited wage determination exceptions, and the preamble says it does not otherwise affect earlier contracts. An earlier contract is left to its own terms, so read the clause in yours. The [preamble](https://www.federalregister.gov/documents/2023/08/23/2023-17221/updating-the-davis-bacon-and-related-acts-regulations) treats option exercises and new out-of-scope work as new contracts, so check the contract and any modification for which clause text it carries. The eCFR shows 5.9 current to November 3, 2026, and 5.5 and 5.11 current to November 5, 2026, with no change to 5.9 or 5.11 since 2023 and only the inflation adjustments above to 5.5. As of January 1, 2023, [section 5.9](https://www.ecfr.gov/on/2023-01-01/title-29/subtitle-A/part-5/subpart-A/section-5.9) said the agency "shall" act and had no paragraph (c). [Section 5.11](https://www.ecfr.gov/on/2023-01-01/title-29/subtitle-A/part-5/subpart-A/section-5.11) required a letter "postmarked" within 30 days. The [older clause](https://www.ecfr.gov/on/2023-01-01/title-29/subtitle-A/part-5/subpart-A/section-5.5) had no priority list, but it already reached other federal and federally assisted contracts held by the same prime and already allowed suspension for unsubmitted records.

## If your job runs under California law

California withholding runs under the Labor Code, with its own notice and clocks, and none of the deadlines above apply. Use our guide to the [California Notice of Withholding of Contract Payments](https://wellstanding.com/guides/notice-of-withholding-contract-payments/).

## What to do in the first week

1. **Find the sender and the provision:** agency or recipient alone, DOL's written request, or a records suspension.
2. **Date the clock.** If WHD issued findings, mark 30 days from the date on its notification.
3. **Send what is missing.** For a records suspension, submit the missing payrolls with the signed Statement of Compliance, and answer WHD records requests on time.
4. **List your other federal jobs,** including jobs held by related entities, since 5.9(b) and (c) can reach them.

We prepare certified payroll for public works contractors. Tell us about your project.

## Questions

**Can the agency hold my payment before any hearing?**

Section 5.9(a) lets the agency suspend payment until enough is withheld, and the clause does not make that depend on a hearing. Your 30 days under 5.11 run separately.

**Can the agency take money from a different federal job of mine?**

Yes, if the same prime contractor holds that contract, whichever agency awarded or assisted it (5.9(b)). Related entities can count as the same prime under 5.2.

**I am a subcontractor. Why is the prime's payment held for my workers' wages?**

The clause covers the liabilities of the prime or any subcontractor, and 5.5(a)(6) makes the prime liable for wages owed to lower-tier workers.

**Does a late certified payroll let the agency stop payment?**

The clause names a failure to submit the required records, after written notice. Payrolls are due weekly, and the clause sets no grace period.

**Does responding within 30 days release the money?**

No. If the Administrator finds a factual dispute, it makes the findings inoperative until a judge or the Board decides, and on a no-facts ruling you need a timely Board petition. Per the preamble, withheld funds are not paid to workers until the hearing and appeal process ends, and WHD asks the agency to release the funds if you prevail.

## Sources

Every figure on this page links to its source where it first appears. The full list, in order:

1. [29 CFR 5.9](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.9) ecfr.gov
2. [5.5](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.5) ecfr.gov
3. [5.11](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.11) ecfr.gov
4. [DOL's August 23, 2023 final rule](https://www.govinfo.gov/content/pkg/FR-2023-08-23/html/2023-17221.htm) govinfo.gov
5. [January 2024](https://www.federalregister.gov/citation/89-FR-1815) federalregister.gov
6. [January 2025](https://www.federalregister.gov/citation/90-FR-1859) federalregister.gov
7. [29 CFR 5.2](https://www.ecfr.gov/current/title-29/subtitle-A/part-5/subpart-A/section-5.2) ecfr.gov
8. [40 U.S.C. 3144(a)(1)](https://www.law.cornell.edu/uscode/text/40/3144) law.cornell.edu
9. [preamble](https://www.federalregister.gov/documents/2023/08/23/2023-17221/updating-the-davis-bacon-and-related-acts-regulations) federalregister.gov
10. [section 5.9](https://www.ecfr.gov/on/2023-01-01/title-29/subtitle-A/part-5/subpart-A/section-5.9) ecfr.gov
11. [Section 5.11](https://www.ecfr.gov/on/2023-01-01/title-29/subtitle-A/part-5/subpart-A/section-5.11) ecfr.gov
12. [older clause](https://www.ecfr.gov/on/2023-01-01/title-29/subtitle-A/part-5/subpart-A/section-5.5) ecfr.gov

## Related

- [What a Wage and Hour investigation asks for](https://wellstanding.com/guides/davis-bacon-wage-and-hour-investigation/)
- [Davis-Bacon debarment](https://wellstanding.com/guides/davis-bacon-debarment/)
- [California Notice of Withholding of Contract Payments](https://wellstanding.com/guides/notice-of-withholding-contract-payments/)
- [HUD-4010 federal labor standards provisions](https://wellstanding.com/guides/hud-4010-federal-labor-standards-provisions/)
- [How to fill out the WH-347](https://wellstanding.com/guides/wh-347/)
- [CWHSSA overtime and liquidated damages](https://wellstanding.com/guides/cwhssa-overtime-liquidated-damages/)
- [Responding to a findings letter and the ALJ hearing](https://wellstanding.com/guides/davis-bacon-findings-letter-response-alj-hearing/)
- [Restitution and corrected payrolls under Davis-Bacon](https://wellstanding.com/guides/davis-bacon-restitution-corrected-payroll/)