# Indiana certified payroll on INDOT jobs: CPMS, held estimates, and which rules apply

This page covers contracts let by the Indiana Department of Transportation (INDOT). The sources are INDOT's [2026 Standard Specifications, Division 100](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf), [Construction Memorandum 19-07](https://www.in.gov/dot/div/contracts/conmemo/19-07.pdf) of July 24, 2019, and the 2026 Indiana Code, [Title 5](https://iga.in.gov/ic/2026/Title_5.html) and [Title 8](https://iga.in.gov/ic/2026/Title_8.html).

Last reviewed November 6, 2026 against the sources it cites

The short answer

INDOT requires the prime contractor to submit certified payroll every week for its own crew and its subcontractors. Since July 24, 2019 that happens in the Contractor Payroll Management System inside ITAP. If a payroll is late or not properly submitted, INDOT may hold progress estimate payments, and its own memo tells project staff to check first whether the cause is lateness or confusion with CPMS.

- Section 103.07(b) of INDOT's [2026 Standard Specifications](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf) makes the contractor on each INDOT contract responsible for submitting certified payroll electronically each week for its own employees and any subcontractors, and says a late payroll may lead to withheld progress estimates until it is properly submitted.
- [Construction Memorandum 19-07](https://www.in.gov/dot/div/contracts/conmemo/19-07.pdf), dated July 24, 2019, put CPMS into use at once in place of emailed payrolls and tells the project engineer to decide whether a deficiency comes from lateness or from a lack of understanding of CPMS before withholding.
- [IC 5-16-7.2-1(b)](https://iga.in.gov/ic/2026/Title_5.html) says the chapter that bars public agencies from requiring a wage scale does not apply to contracts awarded by INDOT when IC 8-23-9 applies.
- On federal-aid contracts, [INDOT's provision 100-C-151A](https://www.in.gov/dot/div/contracts/standards/rsp/sep25/100/100-C-151A%20260701.pdf), revised June 25, 2026, says the prime is responsible for submitting all subcontractor payrolls and that the agency may withhold accrued payments on its own action and must on a written Department of Labor request.
- Specification 103.07(c) sets a $20.00 hourly minimum on state-funded contracts and cites [IC 8-23-9-22](https://iga.in.gov/ic/2026/Title_8.html), but that section states no dollar figure, and the sources do not resolve the difference.
- Under [IC 8-23-9-28](https://iga.in.gov/ic/2026/Title_8.html), INDOT keeps the amount of a labor or material claim out of what it owes the contractor, and specification 109.07 applies that through the contract liens pay item.

## Why INDOT is holding your progress estimate

Section 103.07(b) of the [2026 Standard Specifications](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf) makes the contractor on each INDOT contract responsible for submitting certified payroll electronically every week, for its own employees and any subcontractors. If it is late, INDOT may withhold progress estimate payments until the payroll is properly submitted. The section covers all contracts let by the Department.

The hold is discretionary and lasts until the certified payroll is properly submitted. It reaches subcontractors' payrolls, so a sub's gap can hold the prime's estimate. The specification does not say how much is held.

INDOT's memo to its staff says to find the cause first. Under [Construction Memorandum 19-07](https://www.in.gov/dot/div/contracts/conmemo/19-07.pdf), the project engineer or supervisor (PE/S) must decide before withholding whether the problem is lateness or a lack of understanding of CPMS. The memo cites the authority as 103.06(b); the 2026 book has it at 103.07(b). INDOT says the [2026 book](https://www.in.gov/dot/div/contracts/standards/book/sep25/sep.htm) is effective for lettings from September 1, 2025 through August 31, 2027, so check which book your contract was let under.

### What INDOT's CPMS manual tells its staff to check

| What the [manual](https://www.in.gov/dot/div/contracts/conmemo/19-07.pdf) says | What to check |
| --- | --- |
| CPMS lists each approved contractor and the weeks it had people on site, from daily work reports. Staff can mark a firm's week as needing a payroll, such as DBE and trucking firms not recorded on site. | If a week shows due when nobody worked, ask the PE/S to switch it off. |
| Weeks run across the top by Friday, and the payroll uploaded for a week should contain that Friday. | Pick the week by its Friday. |
| A payroll for the wrong week or firm should not be denied. Staff are told to tell the prime so it can fix it. | Check week and firm on every upload. |
| A payroll is marked late after a 3-week upload window. Once late, it stays late, and INDOT still requires it. | The specification says weekly and the sources do not reconcile the two, so submit weekly. |
| A non-compliant payroll needs a written comment. The contractor can upload more files to that week for context. | Ask for the comment, then add what it asks for. |

That manual, for CPMS version 1.00, is dated July 2019. INDOT's [manuals page](https://erms12c.indot.in.gov/sitemanagermanuals/?startkeywords=CPMS) lists a CPMS 3.0 manual revised October 22, 2024, which could not be opened, so details may have changed.

## How to clear a hold

1. **Get specifics.** Ask the PE/S which weeks and firms CPMS shows as missing, late or non-compliant, and why.
2. **Count everyone.** Include subcontractors, and leased equipment operators and truck drivers, whose payrolls [section 108.01](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf) requires when certified payrolls are required.
3. **Match and submit.** Tie each payroll to the right firm and the Friday it contains, then upload missing or corrected payrolls in CPMS.
4. **Ask when it releases.** The specification ties release to proper submission and names no other date.

## CPMS: where Indiana payrolls go

Memo 19-07 says CPMS took effect immediately on July 24, 2019, replaced emailing payrolls, and covered active contracts not yet substantially complete. CPMS is an application inside ITAP, the INDOT Technical Application Pathway.

The manual's ITAP enrollment steps are written for consultants working as INDOT staff, not contractors, and involve a company enrollment and approval by the company's ITAP Administrator. INDOT's [ITAP Applications page](https://www.in.gov/indot/doing-business-with-indot/Business-Opportunity-Initiative-Division/itap-applications) lists the applications contractors enroll in (On-the-Job Training, SPT/DBE-3 and DBE), and does not list CPMS. Ask the PE/S how your company gets CPMS access. CPMS is also separate from the Subcontractor Payment Tracking System ([section 108.01](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf)), where the prime records payments to subcontractors and they verify them.

## What goes in the payroll

For state-funded work, the specification names no form. It asks for a format acceptable to the Department, so ask the PE/S what INDOT accepts. On federal-aid contracts, INDOT's [provision 100-C-151A](https://www.in.gov/dot/div/contracts/standards/rsp/sep25/100/100-C-151A%20260701.pdf) (revised June 25, 2026, for lettings on or after [July 1, 2026](https://www.in.gov/dot/div/contracts/standards/rsp/sep25/sec100.htm)) reproduces the federal clauses: weekly payrolls to the contracting agency, on Form WH-347 or any other format, with a Statement of Compliance signed by the contractor, the subcontractor, or the agent who pays or supervises payment. The federal mechanics are in our [WH-347 guide](https://wellstanding.com/guides/wh-347/), [version guide](https://wellstanding.com/guides/which-wh-347-version-to-use/) and [FHWA-1273 guide](https://wellstanding.com/guides/fhwa-1273-changes-2026/).

## Does Indiana have a prevailing wage law?

Not a general one. The common construction wage statute, IC 5-16-7, was [repealed by P.L.252-2015](https://iga.in.gov/ic/2026/Title_5.html), and IC 5-16-7.1-2 keeps it for public works contracts awarded before July 1, 2015. For contracts awarded after June 30, 2015, IC 5-16-7.2-5 says that unless federal or state law provides otherwise, a public agency may not establish, mandate or require a wage scale.

The repeal does not remove INDOT's payroll duty. [IC 5-16-7.2-1(b)](https://iga.in.gov/ic/2026/Title_5.html) says that chapter does not apply to contracts awarded by INDOT when IC 8-23-9 applies, and the duty comes from the contract specification. On federal-aid work, [section 103.07(c)](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf) points to the Davis-Bacon General Decision, but 103.07(c)1 applies only where the General Decision is in the Contract Information book, so check your contract book, and section III of provision 100-C-151A covers federal-aid construction projects over $2,000 on federal-aid highways (not local roads or rural minor collectors) and projects that applicable law treats as federal-aid highway projects.

## The $20 an hour floor on state-funded contracts

| Source | What it says |
| --- | --- |
| [Specification 103.07(c)](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf), 2026 book | No one on a state-funded contract may be paid less than $20.00 an hour, citing IC 8-23-9-22, or the General Decision rate, whichever is greater. |
| [IC 8-23-9-22](https://iga.in.gov/ic/2026/Title_8.html) | A state highway bid must state an hourly rate for laborers, not lower than the rate INDOT pays for common labor, which becomes part of the contract. No dollar figure appears, and the history line shows P.L.18-1990 and no amendment. |

The statute speaks of a bid's laborer rate, the specification of anyone on a state-funded contract. The sources do not say what INDOT pays for common labor, where $20 comes from, or which text controls, and this page does not pick one. Ask the PE/S in writing which floor INDOT applies to your contract.

## Labor and material claims that cut into an estimate

[IC 8-23-9-26](https://iga.in.gov/ic/2026/Title_8.html) lets anyone owed money for labor, material or services on state highway system work, or on a building or structure for INDOT, whether for you or a subcontractor, submit a verified itemized statement to INDOT within 60 days after the last labor, material or service and within 30 days after final acceptance.

1. INDOT mails you a copy and retains the claim amount from what it owes you ([IC 8-23-9-27 and 8-23-9-28](https://iga.in.gov/ic/2026/Title_8.html)), through the contract liens pay item in [specification 109.07](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf).
2. You have 20 days after receiving the copy to allow or reject it in writing ([IC 8-23-9-29](https://iga.in.gov/ic/2026/Title_8.html)).
3. If you reject it, the claimant has 90 days after notice to sue. If the claimant sues and sends INDOT the clerk's certificate in that time, INDOT holds the amount until the case is decided ([IC 8-23-9-30 and 8-23-9-31](https://iga.in.gov/ic/2026/Title_8.html)). If not, INDOT pays the amount to you if you are otherwise entitled ([IC 8-23-9-32](https://iga.in.gov/ic/2026/Title_8.html)).

Final payment is not made until allowed under [IC 8-23-9-26 through 8-23-9-39](https://iga.in.gov/ic/2026/Title_8.html) ([section 109.08](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf)).

## Federal-aid jobs: a Department of Labor hold

Provision 100-C-151A says the contracting agency may withhold accrued payments on its own action, and must on a written request from the Department of Labor, to cover unpaid wages and other monetary relief, including interest. After written notice, the federal agency may suspend payments if you fail to submit required records or refuse worker interviews, and either can be grounds for debarment. See [what happens when back wages are withheld](https://wellstanding.com/guides/davis-bacon-withholding-of-contract-payments/), [the debarment rule](https://wellstanding.com/guides/davis-bacon-debarment/) and the [state-by-state table](https://wellstanding.com/guides/certified-payroll-requirements-by-state/).

We prepare certified payroll for public works contractors. Tell us about your project.

## Questions

**Who submits certified payroll on an INDOT job?**

The prime. [Section 103.07(b)](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf) puts the duty on the contractor for its own employees and any subcontractors, and [provision 100-C-151A](https://www.in.gov/dot/div/contracts/standards/rsp/sep25/100/100-C-151A%20260701.pdf) makes the prime responsible for subcontractor payrolls.

**Does INDOT always hold the estimate when a payroll is late?**

No. The specification says INDOT may withhold, and Memo 19-07 tells the PE/S to find the cause first.

**Which payroll form does INDOT want?**

The specification names none for state-funded work and asks for a format acceptable to the Department. [Provision 100-C-151A](https://www.in.gov/dot/div/contracts/standards/rsp/sep25/100/100-C-151A%20260701.pdf) allows Form WH-347 or any other format on federal-aid contracts.

**How long do I keep payroll records on INDOT work?**

Three years after the project work is complete, and open to INDOT inspection ([section 103.07(b)](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf)). On federal-aid work, [provision 100-C-151A](https://www.in.gov/dot/div/contracts/standards/rsp/sep25/100/100-C-151A%20260701.pdf) says three years after all work on the prime contract is completed.

## Sources

Every figure on this page links to its source where it first appears. The full list, in order:

1. [2026 Standard Specifications, Division 100](https://www.in.gov/dot/div/contracts/standards/book/sep25/100-2026.pdf) in.gov
2. [Construction Memorandum 19-07](https://www.in.gov/dot/div/contracts/conmemo/19-07.pdf) in.gov
3. [Title 5](https://iga.in.gov/ic/2026/Title_5.html) iga.in.gov
4. [Title 8](https://iga.in.gov/ic/2026/Title_8.html) iga.in.gov
5. [INDOT's provision 100-C-151A](https://www.in.gov/dot/div/contracts/standards/rsp/sep25/100/100-C-151A%20260701.pdf) in.gov
6. [2026 book](https://www.in.gov/dot/div/contracts/standards/book/sep25/sep.htm) in.gov
7. [manuals page](https://erms12c.indot.in.gov/sitemanagermanuals/?startkeywords=CPMS) erms12c.indot.in.gov
8. [ITAP Applications page](https://www.in.gov/indot/doing-business-with-indot/Business-Opportunity-Initiative-Division/itap-applications) in.gov
9. [July 1, 2026](https://www.in.gov/dot/div/contracts/standards/rsp/sep25/sec100.htm) in.gov

## Related

- [Certified payroll requirements by state](https://wellstanding.com/guides/certified-payroll-requirements-by-state/)
- [How to fill out Form WH-347](https://wellstanding.com/guides/wh-347/)
- [FHWA-1273 changes in 2026](https://wellstanding.com/guides/fhwa-1273-changes-2026/)
- [Davis-Bacon back wages withheld from payments](https://wellstanding.com/guides/davis-bacon-withholding-of-contract-payments/)
- [Which WH-347 version to use](https://wellstanding.com/guides/which-wh-347-version-to-use/)