The skilled and trained workforce requirement in California public works

A skilled and trained workforce requirement is a hiring rule written into a specific California public works statute, defined in Public Contract Code section 2600. It does not apply to every public job. It applies when the law authorizing your project, such as local agency design-build, a school district lease-leaseback, or a CEQA-streamlined housing development, says a skilled and trained workforce is required, and the contract documents must give you notice of that.

What "skilled and trained workforce" actually means

Public Contract Code section 2601 defines it. Every worker performing an apprenticeable occupation in the building and construction trades on the job must be either a skilled journeyperson, meaning a graduate of an approved apprenticeship program or someone with equivalent on the job hours, or an apprentice registered in an approved program. On top of that, a rising share of the journeypersons on the job must themselves be apprenticeship graduates:

Work performed on or afterMinimum share of journeypersons who are apprenticeship graduates
January 1, 201730 percent
January 1, 201840 percent
January 1, 201950 percent
January 1, 2020 and after60 percent

A set of trades stays frozen at the 30 percent floor instead of climbing with the rest. Section 2601 names them: acoustical installer, bricklayer, carpenter, cement mason, drywall installer or lather, marble mason, finisher, or setter, modular furniture or systems installer, operating engineer, pile driver, plasterer, roofer or waterproofer, stone mason, surveyor, teamster, terrazzo worker or finisher, and tile layer, setter, or finisher. If your trade is on that list, you owe 30 percent regardless of the year. If it is not, you owe whatever the current year's line says.

Two built-in exceptions

Section 2601 carves out two situations where the graduation percentage requirement does not apply. A contractor or subcontractor whose skilled journeypersons perform fewer than 10 hours of work on the contract or project in a given calendar month does not have to meet the graduation percentage requirement for that month at all. That is a monthly threshold for the contractor or subcontractor's total hours on the job, not a rule that drops any one worker's hours from the count. And a subcontractor that is not a listed subcontractor on the bid, whose subcontract does not exceed one half of one percent of the prime contract price, is exempt from the requirement entirely for that subcontract. Neither exception touches the separate apprentice ratio you already track for DAS 140 and DAS 142 filings. Those two systems ask different questions and you can owe both on the same job.

Which projects this actually applies to

Unlike prevailing wage or certified payroll, this is not a blanket rule for public works. Section 2600 says the chapter applies only when a statute requires the commitment, or the public entity requires it on its own. A handful of statutes carry the actual mandate:

  • Local agency design-build. Public Contract Code section 22164 bars a design-build entity from being prequalified or shortlisted unless it commits that it and its subcontractors at every tier will use one.
  • School district lease-leaseback. Education Code section 17407.5 puts the same commitment on a lease-leaseback entity before a school district can sign.
  • CEQA-streamlined leadership projects. Under the Jobs and Economic Improvement Through Environmental Leadership Act, a project is deemed to create jobs that pay prevailing wages and promote apprenticeship training if the applicant demonstrates to the Governor's satisfaction that the project will comply with Public Resources Code section 21183.5, per section 21183, subdivision (b). That demonstration is part of what lets the Governor certify the project, and a certified project gets the Act's 270 day expedited judicial review timeline under section 21185.
  • Streamlined housing over 85 feet. Government Code section 65913.4, the SB 35 ministerial approval statute, requires it above that height, exempting a project that is 100 percent lower income units.

Several of these statutes let a qualifying multicraft project labor agreement stand in for the requirement, so check the specific statute your project is built under. And if your bid documents never mentioned this requirement, it almost certainly does not apply: the public entity must disclose it up front, under section 2600, subdivision (c).

The commitment, and what it does to your subcontract

Public Contract Code section 2602 is where the paperwork lives. Whoever signs the enforceable commitment promises two things: to comply with the chapter itself, and to make its contractors and subcontractors at every tier comply too. That second promise is a flow down clause, the same mechanism covered in our guide to subcontractor flow down clauses, and it reaches your subcontract even if you never signed anything with the owner directly.

The signing contractor also owes a monthly compliance report naming the apprenticeship program, location, and graduation date for each worker counted toward the percentage. The same journeyperson and apprentice status feeds your certified payroll worker classification, though this report goes to the awarding body, not the DIR eCPR system.

What happens if the numbers do not add up

Two enforcement tracks run under sections 2602 and 2603, and which one applies depends on what is wrong with the monthly report. A report that is missing or incomplete falls under section 2602, subdivision (b): the public entity withholds further payments until a complete report is provided. If the incompleteness was caused by a subcontractor's own late submission to the contractor, that withholding is capped at 150 percent of that subcontractor's monthly billing. A missing or incomplete report is not forwarded to the Labor Commissioner. A report that is submitted but does not demonstrate compliance is different, under section 2602, subdivision (c): the public entity withholds 150 percent of that entity's monthly billing and forwards the report to the Labor Commissioner for issuance of a civil wage and penalty assessment under section 2603. Separately, if a contractor or subcontractor actually fails to use a skilled and trained workforce, section 2603 sets a civil penalty of up to $5,000 per month of work in violation for a first offense, rising to up to $10,000 per month within three years of a repeat. The Labor Commissioner can reduce or waive a penalty that is disproportionate to the violation, weighing intent, prior history, and voluntary correction.

A contractor who violates the chapter with intent to defraud can be debarred from public works for not less than one year and not more than three years, under subdivision (h). A contractor found to have committed two or more separate willful violations within a three year period can be debarred for up to three years under subdivision (i), which sets no one year floor.

Prime contractor liability has a limit built in. A prime is only on the hook for a subcontractor's violation if it knew about it, or skipped its own required steps: putting the chapter's language into every subcontract signed after January 1, 2019, monitoring subcontractor compliance, correcting a problem once notified, and getting a signed compliance declaration before final payment. See our guide to general contractor liability for subcontractor violations for how this liability standard works more broadly.

How this is different from prevailing wage and certified payroll

Prevailing wage sets what you pay. Certified payroll proves you paid it. The skilled and trained workforce requirement is neither of those; it sets who you can put on the job, by apprenticeship status, and it only shows up when a specific statute or your contract says so. You can owe full prevailing wage and certified payroll compliance on a job with no skilled and trained workforce requirement at all, and you can owe all three together on a design-build or lease-leaseback job. For the broader distinction, see prevailing wage vs certified payroll.

Questions

Does the skilled and trained workforce requirement apply to every California public works job?
No. It applies only when a statute authorizing the project requires it, or when the public entity chooses to require it on its own, under Public Contract Code section 2600. Your bid documents and contract are required to disclose it if it applies.
What percentage of workers has to be apprenticeship program graduates?
The floor rises over time under Public Contract Code section 2601: 30 percent for work performed starting January 1, 2017, 40 percent starting 2018, 50 percent starting 2019, and 60 percent from 2020 forward. A set of trades, including carpenter, operating engineer, and roofer among others, stays at the 30 percent floor.
Does a project labor agreement satisfy the requirement instead?
Often yes. Several of the statutes that impose this requirement, including the local agency design-build statute and the SB 35 streamlined housing statute, exempt a project already covered by a qualifying multicraft project labor agreement. Check the specific statute your project falls under.
Is my small subcontract exempt?
It can be. A subcontract that is not a listed subcontractor on the bid and does not exceed one half of one percent of the prime contract price is exempt under Public Contract Code section 2601. Separately, a contractor or subcontractor whose skilled journeypersons work fewer than 10 hours on the contract or project in a given calendar month does not have to meet the graduation percentage requirement for that month at all.
Can a general contractor be penalized for a subcontractor's violation?
Only in limited circumstances. Under Public Contract Code section 2603, the prime is liable for a subcontractor's failure only if the prime knew about it, or did not put the chapter's language into the subcontract, monitor compliance, act on notice of a problem, or obtain a signed compliance declaration before final payment.
Is the skilled and trained workforce requirement the same thing as certified payroll?
No. Certified payroll proves you paid the correct prevailing wage rate. The skilled and trained workforce requirement controls the apprentice to journeyperson mix on the crew and is reported separately to the awarding body, though the underlying worker classifications overlap.
Who do I send the monthly compliance report to?
The signing contractor sends it to the public entity or awarding body under the enforceable commitment required by Public Contract Code section 2602. A report that does not demonstrate compliance is forwarded to the Labor Commissioner for a wage and penalty assessment. A report that is merely missing or incomplete is not forwarded; instead, further payments are withheld until a complete report is provided. Monthly reports are public records under section 2602, subdivision (d).

Also filing certified payroll on this job? First filing free

Send the payroll export you already run. We turn it into the WH-347 and the DIR eCPR filing, checked by software and verified by a person. Your first weekly filing is free, before you pay us anything. $995 one time setup, then $249 per month flat.

Got it. We reply the same business day. Next: we confirm your payroll system and the project, you send one export, and your first filing comes back for your review before anything is submitted.

First filing free