Davis-Bacon payroll review: the contracting agency or Wage and Hour?
This page maps who can do what. Its sources are 29 CFR 5.6 and 5.7, HUD Handbook 1344.1 and Form FHWA-1273. eCFR showed title 29 as current through November 5, 2026 for 5.6 and November 10, 2026 for 5.7.
Last reviewed against the sources it cites
The short answer
Check the sender. Under 29 CFR 5.6(a) the Federal agency investigates: it examines payrolls and interviews workers, and HUD lets local contracting agencies perform delegated functions on CDBG and HOME work. The Wage and Hour Administrator issues findings under 5.6(b) and 5.11, and the agency may not reduce them. An agency sends DOL an enforcement report within 60 days when underpayments are $1,000 or more or, for contracts entered into after October 23, 2023, the contractor disregarded its obligations (5.7(a)(2)).
- The agency's duty to investigate is in 29 CFR 5.6(a)(3): interviews with workers taken in confidence, plus examination of certified payrolls, regular payrolls and other basic records.
- Under 5.6(b)(3), findings from a Department of Labor investigation, including amounts found due, may not be altered or reduced without DOL approval.
- An agency may withhold payments on its own action but must do so on written request of DOL, under 29 CFR 5.9(a).
- Where underpayments total $1,000 or more, or, for contracts entered into after October 23, 2023, the contractor has disregarded its obligations, the agency sends DOL a detailed enforcement report within 60 days after its investigation ends (29 CFR 5.7(a)(2)).
- HUD's Handbook 1344.1 chapter 5 tells agency staff to ask for a corrected payroll within 30 days when the employer agrees to pay, and says staff have no authority to negotiate a smaller restitution figure.
Two reviewers, two sets of powers
A Davis-Bacon job can be checked by the agency that awarded or funds it, or by the Department of Labor's Wage and Hour Division (WHD). The regulation treats them separately. Section 5.6(a) sets the duties of the "Federal agency," which 29 CFR 5.2 defines as an agency or instrumentality of the United States or the District of Columbia that enters into the contract or provides assistance to the project. Section 5.6(b) sets DOL's. Section 5.6(a) names only the Federal agency. HUD staff and local agencies act on its behalf under HUD Handbook 1344.1 chapter 5 (5-1) for programs such as CDBG and HOME, and Form FHWA-1273 (Section III, paragraph 2) says the contracting agency may withhold.
| Question | Federal agency (5.6(a)) | Wage and Hour (5.6(b)) |
|---|---|---|
| Examine payrolls and interview workers | Yes. Investigations must include interviews with workers taken in confidence and examination of certified payrolls, regular payrolls and basic records (5.6(a)(3)). | Yes. Contractors and agencies must cooperate in record inspection and worker interviews (5.6(b)(2)). |
| Hold contract payments | May on its own action, must on DOL's written request (5.9(a)). | Can require the agency to do it by written request (5.9(a)). |
| Change an amount found due | Cannot alter or reduce a DOL investigation's findings (5.6(b)(3)). | Findings stand unless DOL approves a change (5.6(b)(3)). |
| Decide a formal dispute | Not under 5.11. DOL decides formal 5.11 disputes, which can start on the Administrator's own motion, on agency referral under 5.5(a)(9), or on the contractor's or subcontractor's request (5.11(a)). In HUD's process, an employer's 30 day appeal goes up HUD's levels, and underpayment cases that are not agreed are referred to a DOL Regional Administrator for a hearing (Handbook 7-9(B)(4)). | Yes. DOL decides through a hearing before an administrative law judge, or a ruling and Board review, under 5.11(b) and (c). |
| Report to the other | Sends DOL enforcement reports (5.7). | Sends the agency an enforcement report or a summary (5.6(b)(4)). |
How to tell who is writing to you
- Read the letterhead and the signer's agency. A letter from the contracting agency or a HUD office is an agency-level review. A Wage and Hour office is DOL.
- Look for the 5.11 language. The Administrator notifies you of investigation findings by registered or certified mail or similar means, and you have 30 days from the date of that notification (5.11(b)(2) and (c)(2)). Our guide to the findings letter covers that clock.
- Check for a withholding notice. Before an agency suspends payment for unpaid wages or missing records, 5.5(a)(2)(i) says it acts after written notice to you. See payments held back.
What the agency reviews and can do
Before and during the work
After construction begins, the agency may not approve payment unless a contractor certification of compliance, or of a substantial dispute, is on file ((a)(1)(i)). It must keep the certified payrolls for 3 years after all work on the prime contract and give them to DOL on request, whether or not DOL has opened an investigation ((a)(2)(i)).
On the payroll itself
Section 5.6(a)(3) tells the agency to check the correctness of classifications and whether there is a disproportionate amount of work by laborers and by apprentices registered in approved programs. It also tells the agency to look at fringe benefit evidence and to give priority to complaints.
Payment holds
Under 5.9, the agency may suspend payments until violations stop or enough is withheld to cover back wages, liquidated damages and interest.
Example: HUD staff and local agencies
HUD's Handbook 1344.1 (REV-3, January 2023) shows how one agency splits the work. Chapter 5 covers HUD labor standards specialists and local contracting agencies acting under delegated functions on programs such as CDBG and HOME (5-1). Their duties include spot-checking certified payrolls and notifying the employer and prime contractor of deficiencies (5-2(A)).
Paragraph 5-12 sets the order:
- Staff notify the employer of an apparent underpayment and ask for an explanation or correction.
- If the employer agrees to pay, staff instruct it to compute and pay the back wages and submit a corrected certified payroll within 30 days, then test the computations and payments.
- If the employer refuses, staff compute the back wages and send a written determination by receipted mail with a notice of the right to dispute within 30 days. The prime contractor gets a copy.
The handbook adds that staff have no authority to negotiate restitution, such as paying 50 cents on the dollar (5-12(C)). Our guide to restitution and corrected payrolls covers the payroll itself, and the HUD-11 guide covers the interview form.
Example: highway work under FHWA-1273
On Federal-aid highway contracts, Form FHWA-1273 says the contracting agency may withhold on its own action and must on DOL's written request, and that records must be open for inspection and worker interviews by the contracting agency, the State DOT, FHWA or DOL (Section III, paragraphs 2 and 3). Since June 10, 2026, attaching the form is optional (form notice). See FHWA-1273 changes.
When the agency must hand the case to DOL
If underpayments are under $1,000, there is no reason to believe you disregarded your obligations, and restitution is made with future compliance assured, the agency need not send DOL its findings unless DOL asked for the investigation. At $1,000 or more, or on reason to believe you disregarded your obligations, it sends a detailed enforcement report within 60 days after finishing (5.7(a)(1) and (2)). It also sends DOL semi-annual reports by April 30 and October 31 (5.7(b)).
HUD's chapter 10-2 applies its own version of those tests, with the older "aggravated or willful" wording, and routes reports from the local agency through the labor standards specialist and Deputy Director to DOL. Its chapter 7 says DOL has sole authority to suspend or debar for aggravated or willful violations, and that payroll falsification cases may be referred to DOL at the outset (7-16(B) and (C)). For the contractor's side of debarment, see Davis-Bacon debarment.
Disputes follow a different path. In HUD's process, the appeal goes from the labor standards specialist to the Deputy Director to HUD headquarters (HQLS). If no agreement is reached, HUD refers underpayment cases to the DOL Regional Administrator for a hearing, but appeals of maintenance wage rates or monitoring findings end at HQLS (Handbook 7-9(B)(4)). For other programs, the contract clause and the agency's own letter set the route. The clause at 5.5(a)(9) takes labor standards disputes out of the general disputes clause and says they are resolved under DOL procedures in parts 5, 6 and 7, including disputes between you and the contracting agency. Formal 5.11 proceedings can start on the Administrator's own motion, on agency referral under 5.5(a)(9), or on your request as contractor or subcontractor (5.11(a)).
Contracts entered before October 23, 2023
The 2023 final rule applies to contracts entered into after October 23, 2023. The text in effect on January 1, 2023 differed in these ways:
| Point | Current text | January 1, 2023 text |
|---|---|---|
| Agency's examination (5.6(a)(3)) | Certified payrolls, regular payrolls, other basic records | Payroll data and apprenticeship registration evidence |
| Report to DOL (5.7(a)) | Contractor disregarded its obligations | Violations "aggravated or willful", or for Davis-Bacon, disregard of obligations |
If your contract predates the 2023 rule, read your contract's own clause. State rules vary; see the state requirements table.
What to do this week
- Identify the sender and the legal basis it cites.
- Calendar every deadline in the letter, and the 30 days under 5.11 if DOL sent it.
- Answer the agency's request in writing. If you disagree with a finding, say so in the response.
- If a worker complained, read what happens after a complaint.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Does an agency letter mean I owe back wages now?
Can the agency lower an amount Wage and Hour found due?
Can the agency stop paying me while it reviews?
Does the agency tell DOL about small problems?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- 29 CFR 5.6 ecfr.gov
- 5.7 ecfr.gov
- HUD Handbook 1344.1 hud.gov
- Form FHWA-1273 fhwa.dot.gov
- 29 CFR 5.9(a) ecfr.gov
- Handbook 1344.1 chapter 5 hud.gov
- 29 CFR 5.2 ecfr.gov
- 5.11(a) ecfr.gov
- Handbook 7-9(B)(4) hud.gov
- 5.5(a)(2)(i) ecfr.gov
- chapter 10-2 hud.gov
- 2023 final rule federalregister.gov
- January 1, 2023 ecfr.gov
- 5.7(a) ecfr.gov