Baltimore County prevailing wage payroll: the 14 day clock, the $10 a day charge, and the closeout
This page covers Baltimore County's own prevailing wage and local hiring law for county construction. The sources are the county's Requirements and Compliance page, its Complaints and Violations page, Bill 102-20, which added Code sections 10-2-506 and 10-2-507 (subdivision numbers on this page are the bill as enacted on 11/09/2020 and may differ in the current code), the contract terms (item 14 names the Office of Administrative Hearings), and the annual reports for fiscal year 2026 and fiscal year 2024.
Last reviewed against the sources it cites
The short answer
On a Baltimore County construction contract over $300,000, every contractor and subcontractor enters certified payroll in the county's LCP Tracker portal within 14 days after each payroll period. Under your contract terms, late payroll costs $10 per calendar day, unless state or federal prevailing wage law applies instead. A written decision that you violated the law can be appealed within ten working days of receipt.
- The law covers County-financed construction contracts over $300,000 and County-subsidized capital projects receiving assistance over $5,000,000, under Baltimore County Code sections 10-2-506 and 10-2-507.
- Certified payroll goes through the web-based LCP Tracker system within 14 days after the end of each payroll period, from every contractor and subcontractor.
- The monthly local hire report is due by the last day of each month, and the county assesses $50 per calendar month while it remains unreported.
- A contractor may appeal a written decision of the Director to the Office of Administrative Hearings within ten working days after receiving it, or the decision becomes final and not appealable.
- The county's fiscal year 2026 report describes a 45 day closeout with a final 30 day compliance report, then 15 more days to correct before the vendor issues the Final Project Completion Report to the county, and separately a Director's Final Report with a ten working day appeal period.
- The county assesses $20 per day for each day a misclassified worker is not paid the proper prevailing wage for the work classification.
Late payroll or a closeout report: the clocks
Payroll is late when it is not in the county's system within 14 days after the end of the payroll period. The county assesses liquidated damages of $10 per calendar day that the records are late. The March 2024 training slides say the $10 applies to a payroll submitted more than 14 days after the close of the payroll period, and that the payroll period means the week-ending date shown in LCP Tracker. The same slides put the underpayment charge at $20 per worker per day. The handbook says charges are assessed "per violation, per month, as noted in the contract terms", and the contract terms control. They set the late-payroll charge at $10 per calendar day.
A closeout report is the larger clock. The county's fiscal year 2026 report says the Director issues the Final Report to the contractor with a ten working day appeal period. The ordinance sends the appeal to the Office of Administrative Hearings within ten working days after you receive the decision, and an unappealed decision becomes final (section 10-2-506(J)(3)). Write down the day it arrives, because the clock runs from receipt.
Which contracts the county law covers
The law covers County-financed construction contracts over $300,000 and County-subsidized capital projects receiving assistance over $5,000,000. The county landing page says the county law is effective for contracts signed on or after July 1, 2021. It is separate from Maryland's law, covered on our Maryland page.
| Your contract | What applies |
|---|---|
| County capital improvement contract over $300,000 | Prevailing wage (10-2-506) and local hiring (10-2-507). |
| County-subsidized capital project, assistance over $5,000,000 | Both. The bill changed the prevailing wage figure from $500,000 to $5,000,000, and the county states $5,000,000. |
| Contract of $300,000 or below that an approved modification pushes over | The county's contract terms make the modification that takes the sum past $300,000 subject. The handbook says it covers the work the change order covers. |
| Federal or state prevailing wage law applies | The ordinance's prevailing wage section does not apply, but the county says local hiring may still apply alongside it. The federal weekly form is on our WH-347 page. |
| Other exclusions in 10-2-506(B)(2) | Contracts awarded without competition, with a governmental entity, by the Baltimore County Revenue Authority, entered under 10-2-310(E), joint or cooperative purchases, emergency purchases, and contracts where federal or state law, a contract or a grant expressly precludes compliance. These exclusions are in the prevailing wage section only. The bill's local hiring section, 10-2-507, lists thresholds but no exclusions, and the contract terms (introduction) define Capital Improvement Project with the same exclusions. |
The county's code library blocked automated access, so this page reads the ordinance as passed in Bill 102-20. The county's 2026 pages state the same thresholds and 14 day rule. Wage rates come from the State of Maryland determination for Baltimore County, and the contract terms (revised November 11, 2023) fix the rates in effect on the solicitation date for the whole contract (item 1). Their introduction says time of award instead, and the handbook agrees with the solicitation date, so confirm with your solicitation.
Who submits what, when, and where
| What | When | Where |
|---|---|---|
| Affidavit from each contractor and bidder, signed by an officer or agent who supervises payment of employees (form revised 10/1/2023) | On the county's demand, as a requirement of the contract | To the county. The form also promises a subcontractor list after award. |
| Employment analysis: jobs needed and new hires needed | Before the county disburses any funds | To the Prevailing Wage and Local Hire unit |
| Certified payroll from every contractor and subcontractor | Within 14 days after the end of each payroll period | LCP Tracker Compliance Reporting Portal |
| Monthly local hire report from contractors and subcontractors | By the last day of each month | The form (revised November 2023) says upload it to the LCP Tracker portal. The handbook says eDocs. Confirm the destination with the division at the preconstruction conference. |
| Payroll records kept for inspection | At least five years after the work is completed | With you, open to the Director on reasonable notice |
The county says payroll is entered online rather than on paper forms. The contract terms say to submit a certified copy of payroll records electronically through the county's designated certified payroll and compliance system. The prime contractor gives each subcontractor its login (handbook), and each contractor is jointly and severally liable for a subcontractor's noncompliance (10-2-506(J)(6)).
Each payroll lists the job and contractor details and, for each employee, the name, current address (unless previously reported, per 10-2-506(I)(3)), specific classification, daily straight and overtime hours, rate of pay, fringe benefits by type and amount, and gross wages. The contractor or subcontractor signs a statement that the records are correct, the wages are not less than required, and each rate and classification reflects the work done (10-2-506(I)(2)). The contract terms (item 9) also ask for the contractor's email address and any deductions taken from pay, and the handbook asks for each employee's Social Security number and check number.
What happens when payroll is late, wrong or missing
The dollar amounts below are the county's published schedule in its contract terms (revised 11/11/2023, item 17), which say contracts may specify liquidated damages. The handbook adds that solicitation documents can set rates in addition to those in the law. Section 10-2-506(E)(3) is the ordinance's ceiling on contract-specified liquidated damages for noncompliance: not more than three times the wages owed to the employee. The county's published schedule is the contract terms (item 17), and the sources do not say how the ceiling applies to the $10 late charge.
| Problem | What the county does |
|---|---|
| Payroll late | $10 per calendar day. Invoices may be deemed deficient and payment postponed until the records arrive (10-2-506(J)(7)). |
| Underpayment or misclassification | The worker is paid in full, and the county assesses $20 per day for each day the worker lacks the proper rate. The county's March 2024 training slides say damages stand even after payroll is corrected and restitution paid. |
| Wage rates not posted at the site | The contract terms say $50 per violation, and the slides say $50 per day. The handbook says rates are set in the solicitation documents, so read your contract. |
| Local hire report late or missing | $50 per calendar month while it remains unreported. |
| Violation found | A written decision with sanctions. Pending a final decision, the county may withhold from payment due enough to pay each employee in full and cover liquidated damages (10-2-506(J)(2)). The handbook describes a written cure notice first. |
| Intentional violation | After notice and a hearing, the bill bars new county contract awards to the contractor, its principals or firms in which it has an interest for one year, and says contracts already awarded are not impacted (10-2-506(J)(4)). The county's contract terms (item 14, revised 11/11/2023) go further: an intentional violator may not be awarded a County contract or work on any County project for one year from the date of the OAH determination. Read your own contract to see which applies to you. |
The closeout and the appeal
Both annual reports describe a 45 day closeout (fiscal year 2024 and fiscal year 2026). The 2026 report separately describes the Director's Final Report with its ten working day appeal period. It does not state the order or timing between the vendor's Final Project Completion Report and the Director's Final Report, so the list below is the two descriptions side by side, not a county timeline.
- Notice. The county's compliance vendor is told the project is complete.
- 30 days. The vendor issues a final labor compliance report on outstanding items.
- 15 more days. Unresolved items get 15 days to correct.
- Final Project Completion Report. The vendor sends it to the county. Closeout documents include exhibits for violations.
- Director's Final Report. The Program Manager sends a draft to the Director, who issues it to you with a ten working day appeal period.
- Appeal. The ten working days run from your receipt of a written decision of the Director that you violated the law (10-2-506(J)(3)). A timely appeal gets a hearing at the Office of Administrative Hearings, and without one the decision is final.
The fiscal year 2024 report says the county meets with its compliance vendor every other Thursday to review project updates and waivers for liquidated damages. The sources give no waiver standard or procedure, so ask the division and read your contract. The landing page also publishes a debarment list.
Since July 2025 the county sends compliance reports to contractors once every six months, plus a random report on 10% of active projects each month, where they were monthly before.
| County figure | FY24 (July 2023 to June 2024) | FY26 |
|---|---|---|
| Contracts active at year end / closed | 32 / 3 | 62 / 28 |
| Compliance reviews / onsite visits | 470 / 103 | 2,000 / 406 |
| Wages recovered for workers | $1,088.96 from contractors, plus $168,066.87 withheld from retention | $180,413 |
| Liquidated damages assessed on projects closed | $38,460 | $326,370 |
Local hire and the monthly report
Under 10-2-507, at least 51% of the new jobs needed for the contract must be filled by Baltimore County residents. All new jobs are posted through the department for seven days before public advertising. The department may waive or lower the 51% on four listed findings, one of which is a good faith effort. The affidavit promises best efforts to reach 51%, where the ordinance says the jobs must be filled. The handbook says the statute controls in a conflict.
The monthly form (revised November 2023) asks for employees needed, current employees transferred, new openings, openings listed with the department, Baltimore County residents hired, and the efforts made to fill openings locally. If no work was done, it says to write NO WORK PERFORMED. The ordinance and the contract terms also list per-hire details: name, last four digits of the Social Security number, job title, hire date, address and referral source. The form has no per-hire columns, so ask the unit where those go.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Does the county law apply to a contract of $300,000 or below?
What if there was no work in a week?
Are my payroll records public?
Can a worker sue over underpayment?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Requirements and Compliance page baltimorecountymd.gov
- Complaints and Violations page baltimorecountymd.gov
- Bill 102-20 mgaleg.maryland.gov
- contract terms baltimorecountymd.gov
- fiscal year 2026 baltimorecountymd.gov
- fiscal year 2024 baltimorecountymd.gov
- County-financed construction contracts over $300,000 and County-subsidized capital projects receiving assistance over $5,000,000 baltimorecountymd.gov
- March 2024 training slides bcg-prod.baltimorecountymd.gov
- handbook resources.baltimorecountymd.gov
- Wage rates come from the State of Maryland determination baltimorecountymd.gov
- form revised 10/1/2023 baltimorecountymd.gov
- form baltimorecountymd.gov