CWHSSA overtime on federal construction: the 40 hour rule and liquidated damages

This page reads 29 CFR 5.5(b), 29 CFR 5.8, 40 U.S.C. 3702 and DOL's Employment Law Guide. The eCFR copy of section 5.5 was up to date as of November 3, 2026, and section 5.8 as of November 5, 2026.

Last reviewed against the sources it cites

The short answer

On a covered federal or federally assisted construction contract, laborers and mechanics must be paid at least one and one-half times the basic rate for hours over 40 in a workweek. If not, you owe the unpaid wages and liquidated damages of $33 per worker for each calendar day. Interest and mandatory withholding on DOL's written request come with the current clause (contracts entered into after October 23, 2023); earlier and FAR clause contracts differ.

  • 29 CFR 5.5(b)(1) bars a contractor or subcontractor from requiring or permitting a laborer or mechanic to work more than forty hours in a workweek unless the extra hours are paid at not less than one and one-half times the basic rate.
  • The liquidated damages figure in 29 CFR 5.8(a) is $33 for each calendar day per laborer or mechanic, raised from $32 by DOL's January 10, 2025 inflation adjustment.
  • The statute, 40 U.S.C. 3702(c), reads $10 a day in the 2023 edition, so a $10 figure in older guidance is out of date.
  • Under the current 29 CFR 5.5(b)(3), for contracts entered into after October 23, 2023, the agency may withhold, and must when DOL asks in writing, from this contract or any other federal or federally assisted CWHSSA contract held by the same prime contractor, whichever agency awarded it; earlier and FAR clause contracts word this differently.
  • An agency head can reduce or release liquidated damages of $500 or less without DOL under 29 CFR 5.8(d), while larger amounts go to DOL as a recommendation under 5.8(b).
  • DOL's 2023 Davis-Bacon rule says its provisions apply only to contracts entered into after October 23, 2023 (with one exception, for a part 1 wage determination provision), so older contracts keep the terms and regulations in effect when they were signed.

The rule: time and a half over 40 hours in a workweek

The Contract Work Hours and Safety Standards Act (CWHSSA) sets a standard workweek of 40 hours. Section 3702(a) makes wages include pay "at a rate not less than one and one-half times the basic rate of pay, for all hours worked in excess of 40 hours in the workweek." The contract clause in 29 CFR 5.5(b)(1) says the same for any laborer or mechanic, including watchpersons and guards. Who counts as one is covered in our working foremen guide.

The trigger is the week, not the day. DOL's guide says state overtime requirements may apply too; California's daily rule is in our California overtime guide.

Liquidated damages: the amount and how days are counted

Missed overtime brings the unpaid wages (with interest on later contracts) plus liquidated damages owed to the United States. Under 5.5(b)(2) they are $33 "for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours," for each laborer or mechanic. Section 5.8(a) uses the same $33.

The statute, 40 U.S.C. 3702(c) (2023 edition), reads $10. DOL raises the figure by inflation adjustment, no later than January 15 each year. DOL's January 10, 2025 notice changed $32 to $33 for penalties assessed after January 15, 2025. The eCFR showed no later change as of November 5, 2026; check it before you price an exposure.

Section 5.8(a) charges damages for "each calendar day in the workweek on which such individual was required or permitted to work in excess of forty hours": days, not hours. For example, a worker who put in six 11 hour days with no premium worked over forty hours on three calendar days, so $99 at $33.

Withholding, priority and the prime's exposure

This section quotes the current clause; the table further down shows how earlier contracts differ. Under 5.5(b)(3)(i) the agency or the recipient of the assistance "may, upon its own action, or must, upon written request" of DOL, withhold what is necessary for unpaid wages, interest and liquidated damages. The money can come from this contract, any other federal contract with the same prime contractor, or any other federally assisted CWHSSA contract that prime holds, "regardless of whether the other contract was awarded or assisted by the same agency."

Section 5.9(c) says cross-withholding from a different legal entity is not appropriate unless the withholding provisions were incorporated in that entity's contract, and, absent exceptional circumstances, "is not permitted" where the Davis-Bacon labor standards were incorporated only by operation of law. DOL has priority over sureties, reprocurement costs, bankruptcy trustees, assignees, successors and Prompt Payment Act claims (5.5(b)(3)(ii)). See our withholding guide.

Paragraph (b)(4) makes the prime responsible for lower tiers. The prime and any responsible subcontractor are liable for lower-tier workers' unpaid wages, interest and associated liquidated damages, and "may be subject to debarment" (debarment guide).

Reducing or waiving the damages

40 U.S.C. 3703(d) gives 60 days after an amount is withheld to appeal to the agency head, then 60 days after a final order to file a claim in the Court of Federal Claims. The grounds are that the amount is incorrect or the violation was inadvertent despite due care.

Liquidated damages computedWho can reduce or release
$500 or lessThe agency head, without reporting to DOL (5.8(d); FAR 22.302(c)(1) and (2))
More than $500The agency head can issue a final order affirming the determination, or recommend relief to the Secretary of Labor. DOL decides only a recommendation, and the Administrator's order is final unless the Administrative Review Board takes review (5.8(b) and (c); 40 U.S.C. 3703(d)(2); FAR 22.302(c)(3))

Which contracts carry the clause

Section 3701(b)(1) reaches contracts that may require laborers or mechanics on a federal public work, other contracts to which the Government is a party or that are made for or on behalf of it, and contracts for work financed at least in part by loans or grants from, or loans insured or guaranteed by, the Government under a federal law providing wage standards. Under 3701(b)(3)(A) the chapter does not apply to contracts for transportation by land, air or water, transmission of intelligence, or purchase of supplies or materials or articles ordinarily available in the open market, to work under 41 U.S.C. chapter 65 (Walsh-Healey), or to a contract of $100,000 or less. Under 3701(b)(3)(B), section 3702 (the overtime rule) does not apply where the assistance is only a loan guarantee or insurance. The dollar lines differ:

SourceDollar line
40 U.S.C. 3701(b)(3)(A)(iii), 2023 editionDoes not apply to a contract not greater than $100,000
29 CFR 5.5(b)Clauses go in "any contract in an amount in excess of $100,000"
DOL Employment Law Guide, May 2024Over $150,000 for federal construction under the FAR, $100,000 for federal construction outside it, over $100,000 for federally assisted construction
FAR 22.305, FAC 2026-01 (March 13, 2026)Do not include clause 52.222-4 in contracts valued at or below $200,000

The Employment Law Guide figure is dated May 2024, and FAR 22.305 is the current clause-insertion rule in the FAR. The statute's $100,000 line is unchanged in the 2023 edition. These do not match, so read the overtime clause in your subcontract and the prime contract and ask the contracting officer which applies. For contracts entered into after October 23, 2023, 5.5(e) makes the clauses part of any prime contract the statute requires them in, even if left out, unless the Administrator grants a variance, tolerance, or exemption. Section 5.15(b) also lists classes of contracts exempt from CWHSSA.

Contracts entered before and after October 23, 2023

DOL's 2023 rule (88 FR 57526) says: "Except with regard to ยง 1.6(c)(2)(iii), the provisions of this final rule are applicable only to contracts entered into after October 23, 2023." For earlier contracts, "the terms of those contracts and the regulations that were effective at the time those contracts were entered into" continue to govern, such as the clause text in effect October 22, 2023.

ItemEarlier contractsLater contracts
Back wages"the unpaid wages"Unpaid wages "and interest from the date of the underpayment"
WithholdingAgency "shall" withhold on its own action or DOL's request"May" on its own action, "must" on DOL's written request, plus a priority list

A FAR contract carries the clause by reference. The preamble to the 2023 rule says that for a FAR contract entered into after the effective date but before the FAR is amended, the mandatory FAR clauses "in effect at the time the FAR contract was entered into" govern. FAR 52.222-4 is still the May 2018 text, so the 5.5(b)(3) priority list and the 5.5(b)(5) anti-retaliation paragraph are not in it. Its paragraph (c) says the Contracting Officer "will withhold from payments due under the contract" and reaches other contracts only "If amounts withheld under the contract are insufficient." Check which clause your contract cites.

How it shows on the certified payroll

CWHSSA has no weekly submission of its own. On a Davis-Bacon job, 5.5(a)(3)(ii) requires weekly certified payrolls with daily and weekly hours and hourly rates, on the WH-347 or "any other format." A contract subject only to CWHSSA needs records kept under paragraph (c), not weekly submission. See our WH-347 example.

The contractor, subcontractor or their agent who pays or supervises pay signs the Statement of Compliance (5.5(a)(3)(ii)(C)), which certifies each worker "has been paid the full weekly wages earned." Investigators examine payrolls and interview workers (5.6(a)(3); see WHD investigations).

Payroll preparation

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

Does CWHSSA require daily overtime?
No. The statute and the clause use a 40 hour workweek, though state law may add its own rules.
How much are the liquidated damages?
$33 for each calendar day for each laborer or mechanic, in 29 CFR 5.5(b)(2) and 5.8(a) as of November 5, 2026.
Can the agency take the money from another job?
Yes, on contracts with the current clause: under 5.5(b)(3)(i) it can withhold from other covered contracts the same prime contractor holds. A FAR clause contract reaches other contracts only if this contract's funds fall short, and a different legal entity's contract is reached only under 29 CFR 5.9(c).
Can liquidated damages be reduced or waived?
Yes, if the amount is incorrect or the violation was inadvertent despite due care. The agency head can act alone at $500 or less. Above that, the agency head can affirm the determination or recommend relief to DOL, and DOL decides on the recommendation.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. 29 CFR 5.5(b) ecfr.gov
  2. 29 CFR 5.8 ecfr.gov
  3. 40 U.S.C. 3702 govinfo.gov
  4. Employment Law Guide webapps.dol.gov
  5. January 10, 2025 inflation adjustment federalregister.gov
  6. 2023 Davis-Bacon rule federalregister.gov
  7. no later than January 15 each year acquisition.gov
  8. Section 5.9(c) ecfr.gov
  9. 40 U.S.C. 3703(d) govinfo.gov
  10. Section 3701(b)(1) govinfo.gov
  11. FAR 22.305 acquisition.gov
  12. Section 5.15(b) ecfr.gov
  13. in effect October 22, 2023 ecfr.gov
  14. FAR 52.222-4 acquisition.gov
  15. 5.6(a)(3) ecfr.gov

Questions about overtime on your project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us