How to find the apprenticeship committee for your DAS 140 and DAS 142

DIR runs a lookup that lists apprenticeship programs by county and craft. This page shows how to use it and what to send each committee, following the Division of Apprenticeship Standards public works page, 8 CCR 230 and 8 CCR 230.1.

Last reviewed against the sources it cites

The short answer

Open DIR's public works apprenticeship program search, pick the county of the jobsite and the craft, and it lists the registered program sponsors. If you are not approved to train, send your DAS 140 to every applicable committee whose area covers the jobsite, for each apprenticeable craft. Send it to the committees, not to DAS.

  • DIR's public works program search lets you select a county and an occupation group, and the page states its data is current as of 11/04/2026 (read November 4, 2026).
  • A contractor not already approved to train must give contract award information to all applicable apprenticeship committees whose geographic area includes the project (8 CCR 230(a)).
  • The lookup lists registered program sponsors and, in DIR's words, does not signify they will dispatch apprentices.
  • The DAS 142 form is headed "DO NOT SEND THIS FORM TO DAS"; it goes to the committee.
  • If a committee does not dispatch, 8 CCR 230.1(a) has you request dispatch from each other committee in the craft and area.

The short version

DIR publishes the lookup itself. It is the "Find available apprenticeship committees" link on the DAS public works page, and it opens the public works program search. You choose a county and a craft. It returns the registered program sponsors for that pair.

Then you send the notice. The forms themselves are covered on other pages: the DAS 140 field by field, the DAS 142 and its 72 hour rule, and both side by side in DAS 140 and DAS 142, explained. This page covers the step between them: who is on the address line.

Use the DIR lookup, step by step

  1. Write down the county of the jobsite. The lookup works by the county where the work happens, not the county of your office. The county list runs from Alameda to Yuba.
  2. Pick the craft for each kind of apprenticeable work you will do. The occupation list includes Carpentry, Cement Masons, Electrical & Electronic, Heating, Ventilation & Air Conditioning, Laborers, Operating Engineer, Plumbing & Pipefitting, Roofer, Sheet Metal and others. Use the craft on your prevailing wage determination as your guide. Run one search per craft.
  3. Read the results as a list of candidates. DIR's disclaimer on the page says the listing is of registered program sponsors in the construction industry and "does not signify they will dispatch apprentices." Each sponsor decides for itself when to dispatch.
  4. If your craft is missing, look one level up. DIR says an occupation you cannot find may be a sub-craft of a main occupation. Its examples: Brick Tender and Plaster Tender sit under the Northern California Laborer listing, and Landscape and Irrigation Fitter and Plaster Tender sit under the Southern California Laborer listing.
  5. Still stuck? Contact the DAS office for the county. The search page says to contact the respective DAS office for the county of the project, and links the DAS Offices page. The DAS public works FAQ gives the same advice, and the DAS contact page lists regional offices in Fresno, Los Angeles, Sacramento, San Diego and the Bay Area.
  6. Save what you found. Print each result with its date, so you can show which committees you identified when you sent your notice.

Which committees get your DAS 140

It depends on whether a committee has already approved you to train apprentices. The rule is in 8 CCR 230(a), and the DAS public works page says the same thing in plainer words.

Your statusSend the DAS 140 to
Approved to train apprentices by a committeeThe committee for each applicable craft in the project area that has approved you
Not approved to trainAll applicable apprenticeship committees whose geographic area of operation includes the project, for each apprenticeable craft

The second row applies to any contractor not already approved to train. A non-union contractor is not excused: the DAS FAQ says you must request dispatch from all approved programs in the geographic area of the project.

The notice is due within 10 days of the date you executed the contract, and no later than the first day you have workers on the public work. The same regulation says that failing to provide it is a continuing violation for the duration of the contract for purposes of penalties under Labor Code 1777.7. That is why a missed committee matters. A committee you left off the list is a committee you did not notify.

The ratio rule has exemptions under Labor Code 1777.5, as 8 CCR 230.1(a) notes. The DAS public works FAQ says a contractor with an individual contractor exemption under 1777.5(j) or (k), or a program committee exemption, must still send the DAS 140. For a contractor exempt from 1777.5 altogether, such as one whose craft is not apprenticeable or a general contractor under $30,000, the same FAQ says you do not have to submit the DAS 140, though you may want to send it so the committee knows of the exemption.

What to send each committee

The DAS 140: send it to each applicable committee

Send the DAS 140 to each applicable committee, and keep a dated copy of what went to each. The form has a line for the name and address of the apprenticeship program. The regulation lists what the notice must carry and bars a committee from requiring more: contractor name, address, telephone and license number; the awarding body; the exact site; the award date; the expected start; estimated journeyman hours; the number of apprentices; and the approximate dates they would be employed.

The DAS 142: first request, then the rest

The written notice is required, and the DAS forms are optional ways to give it: 8 CCR 230(a) says the contract award information "may be" a DAS 140, and 8 CCR 230.1(a) calls the DAS 142 an optional form for the dispatch request. Under 8 CCR 230.1(a), if you do not already employ enough registered apprentices to meet the one-to-five ratio, you request dispatch from the committees that train in the craft and whose area covers the site. If a committee does not dispatch as requested, you request dispatch from the next committee, and then from each committee in the area, one after another or all at once.

The DAS 142 takes one occupation per form. Requests go in writing by first class mail, fax or email, and the form says proof of submission may be required. Both forms go to committees, not to DAS. The DAS requirements page adds that the full round of requests to other committees only needs to be done once during the life of the project.

If a committee says no, or says nothing

You are not required to sign extra paperwork to get apprentices. The DAS FAQ says you do not have to sign a DAS 7 (Agreement to Train Apprentices) or agree to other conditions set by a program. It also says that if a program will not dispatch unconditionally and you have contacted all the appropriate programs in the area, you have met your obligation.

8 CCR 230.1(a) adds that a contractor who has agreed to employ and train apprentices under the committee's standards or the council's regulations, and gets no dispatch within 72 hours of the request (excluding Saturdays, Sundays and holidays), is not in violation for failing to employ apprentices for the remainder of the project, provided the request was made in time to meet the ratio. If a committee dispatches fewer apprentices than you requested, you are in compliance if you employ those dispatched, provided that, where more than one committee is able and willing to dispatch unconditionally, you requested dispatch from all committees that train in the craft and whose area includes the site.

The 72 hour timing

Under 8 CCR 230.1(a), send the DAS 142 at least 72 hours (excluding Saturdays, Sundays and holidays) before you need apprentices. The DAS public works page words this as "at least three business days." Send earlier if you can.

Check the apprentice before you put the name on payroll

DAS runs two more searches from the same public works page. The registered apprentice search takes a nine character string: the first four letters of the last name, the first letter of the first name and the last four digits of the Social Security number. DIR says a miss can mean the person is not registered, the string is wrong, or the apprentice agreement has not reached DAS or been entered; agreements must be submitted within 30 days of signing. The graduated apprentice search looks up building and construction trades graduates by name, occupation and graduation date. Neither is the committee lookup, but the first is the place to confirm an apprentice is registered.

Training fund payments have their own check: the CAC training fund search.

What we do

WellStanding prepares the DAS 140 and DAS 142 and the WH-347 and eCPR from the payroll export you already run, and a person reviews every filing. You review and sign; nothing is filed until you have signed, and we never sign for you.

Questions

Where do I find which apprenticeship committee covers my county and craft?
Use DIR's public works program search. Select the county of the jobsite and the occupation group, and it lists registered program sponsors. If your craft is not on the list, it may be a sub-craft of a main occupation, and you can contact the DAS office for the county.
Do I send the DAS 140 to DAS?
No. The DAS 140 says "Do not send this form to the Division of Apprenticeship Standards," and 8 CCR 230(a) directs the contract award information to apprenticeship committees. Send it to the committees the lookup returns.
Do I have to send it to every committee the lookup returns?
If you are not already approved to train, send it to every committee that covers the jobsite county for your craft, as the lookup returns them. The rule is all applicable committees whose geographic area includes the project, for each apprenticeable craft (8 CCR 230(a)). If a committee has approved you, you send it to that committee for each applicable craft.
A committee asked me to sign its own agreement before it sends apprentices. Do I have to?
The DAS public works FAQ says you are not required to sign additional documents such as the DAS 7 or agree to other conditions. If a program will not dispatch unconditionally and you have contacted all the appropriate programs, DAS says you have met your obligation. Talk to an attorney if the committee pushes back.
Does the lookup guarantee the committee will send an apprentice?
No. DIR's disclaimer says the list does not signify that a sponsor will dispatch apprentices, and that sponsors decide individually when they will.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Division of Apprenticeship Standards public works page dir.ca.gov
  2. 8 CCR 230 dir.ca.gov
  3. 8 CCR 230.1 dir.ca.gov
  4. public works program search dir.ca.gov
  5. DAS 142 form dir.ca.gov
  6. DAS Offices page dir.ca.gov
  7. DAS public works FAQ dir.ca.gov
  8. DAS contact page dir.ca.gov
  9. DAS 140 dir.ca.gov
  10. DAS requirements page dir.ca.gov
  11. registered apprentice search dir.ca.gov
  12. graduated apprentice search dir.ca.gov

Not sure who gets your DAS 140? First filing free

Send the payroll export you already run. We turn it into the WH-347 and the DIR eCPR filing, checked by software and verified by a person. First filing free, before you pay us anything. $995 one time setup, then $249 per month flat for crews up to 25 workers.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.