Mississippi MDOT certified payroll: CAD-880, CAD-881 and the held estimate

This page follows MDOT's own Contract Administration rule on statements and payrolls (also on Cornell LII) and MDOT's FHWA-1273 checklist document.

Last reviewed against the sources it cites

The short answer

On Mississippi federal-aid projects, MDOT's rule requires each contractor and subcontractor to submit two copies of the weekly payroll with forms CAD-880 and CAD-881. The Project Engineer checks the payrolls and forwards them to the Compliance Officer. The warrant for the monthly estimate will not be issued if the required payrolls have not been received.

  • MDOT's Contract Administration rule on statements and payrolls requires, in paragraph 2, two copies of the weekly payroll with CAD-880 and CAD-881 on federal-aid projects, and CAD-880 on 100 percent state funded projects.
  • Paragraph 2 of the same rule says the warrant will not be issued to the contractor for the monthly estimate if the required payroll reports have not been received.
  • A week with no work still needs a negative (NO WORK) statement, and the last payroll must be noted as FINAL, per paragraph 2 of the rule.
  • A wage violation is recorded on form CAD-882, and paragraph 3 of the rule says it may not be cleared until the Compliance Officer has a supplemental payroll, proof of restitution signed by the employee, a letter of explanation and a final FHWA or Secretary of Labor determination.
  • On LPA projects, MDOT's supplement to FHWA-1273 dated October 6, 2026 requires LPA Form SCC-1 to be attached to LPA Form RSP-1 when you ask permission to subcontract.

Mississippi has no state prevailing wage law in the table our state comparison page relies on, so the payroll duties below come from MDOT's rule on federal-aid and state funded projects.

What stops your money if payrolls are missing

MDOT's rule says it directly: "The warrant will not be issued to the Contractor for payment of the monthly estimate if the required payroll reports have not been received." The rule sits in Sub-Part 7401, Chapter 04000. The quoted sentence is paragraph 2 of the rule. Paragraph 101 says the rule conforms to Section 110 of the Mississippi Standard Specifications, Title 29 of the CFR, Title 23 of the U.S. Code and the Davis-Bacon Act.

The federal clause says the same kind of thing from the other side. FHWA-1273 (revised June 25, 2026) says a breach of its provisions may be grounds for withholding progress payments, withholding final payment, termination, suspension or debarment. Under the rule above, a missing payroll holds up the monthly estimate.

The prime contractor is responsible for its subcontractors' payrolls under the same federal clause. If a sub is late, your estimate is the one that waits. Our WH-347 guide covers the federal form that the payroll content follows.

What MDOT requires each week

ItemWhat the rule says
Federal-aid projectsTwo copies of the weekly payroll with forms CAD-880 and CAD-881
100 percent state funded projectsTwo copies of the weekly payroll with form CAD-880
Week with no workA negative (NO WORK) statement for the period
Last payroll on the contractNoted as FINAL on the payroll
Who checks itThe Project Engineer has one week to check the payrolls and forward them to the Compliance Officer
Where the forms come fromContract Administration

Paragraph 2 says each contractor and subcontractor submits this once work has begun. It says the Project Engineer checks the payrolls. Paragraph 1 (predetermination of wage rates) sends 2 copies of CAD-880 to the Project Engineer and the County Engineer weekly, and one is forwarded to the Compliance Officer. See the CAD-880 form (Rev. 9-2007) for the layout.

What CAD-880 is

CAD-880 is titled Weekly Summary of Wage Rates. Per its instructions, you list the hourly rate paid and the number employed for each MDOT pay-code classification on that week's payroll. Report the rate received by the largest number of workers in a classification and list other rates in the blank spaces. Do not report salaried employees, supervisors, foremen or clerks. Report straight time rates only, not overtime rates. Its footer says to submit the original and one copy to the Project Engineer.

Paragraph 1 says MDOT uses this information to determine future wage rates. CAD-880 is a wage summary, not a substitute for the payroll itself.

What CAD-881 is

The rule names CAD-881 as the weekly statement required on federal-aid projects, and the State Aid office's procedure SA II-2-10 (March 3, 2009) calls it the Weekly Statement of Compliance. The CAD-881 form (Rev. 9-2007) is a one-page statement signed by a named signatory. It says that all persons employed were paid the full weekly wages earned, that the payrolls are correct and complete, that wage rates are not less than the contract wage determination, and it has sections for fringe benefits paid to plans or in cash and for exceptions by craft. It warns that willful falsification may bring civil or criminal prosecution. The rule says the form can be obtained from Contract Administration. The Office of State Aid also hosts CAD-880 and CAD-881, listed as Rev. 09-01-2007, and the CAD-881 instructions on its State Aid forms page.

Two sets of instructions on copies

MDOT's rule and the State Aid office's 2009 procedure give different recipients. Paragraph 1 of the rule sends 2 copies of CAD-880 to the Project Engineer and County Engineer weekly, and the CAD-880 footer says original and one copy to the Project Engineer. Section 2.2 of the procedure says each contractor and subcontractor on a federally funded project submits one copy of CAD-880 weekly to the County Engineer and one copy to State Aid. Section 2.3 gives CAD-881 the same schedule. The procedure also says certified payroll sheets should accompany CAD-880 and CAD-881, and that no-work weeks use CAD-880 with "No work performed during this period" written across it.

The rule is MDOT Contract Administration's and the procedure is the Office of State Aid's. Neither says which one controls, and the rule carries no date while the procedure is dated March 3, 2009. Neither names a submission system or medium, so ask the Project Engineer or the Office of State Aid which instruction applies and how your job accepts payrolls.

Payment holds in the Office of State Aid procedure (2009)

The 2009 State Aid procedure adds a second hold. Section 4.1 says no progress estimate will be processed for payment until the properly executed and signed Form CAD-440 (Labor Questionnaire) is received by the Office of State Aid. State Aid also checks each payroll (section 4.2), as described below. The procedure routes FHWA-1391 differently from the rule: section 3.1 says the report is due for work performed in the last week in July, with one copy to the County Engineer and one to State Aid, and section 4.3 makes the prime contractor responsible for collecting subcontractors' forms.

Wage violations and form CAD-882

Under paragraph 3 of the rule, the Compliance Officer computes violations and records them on form CAD-882, and a copy goes to the contractor as notification. The copy shows the action required to fix it. The violation may not be cleared until the Compliance Officer has all four of these:

  1. A supplemental payroll.
  2. Proof of restitution signed by the employee.
  3. A letter of explanation from the contractor.
  4. A final determination by the Federal Highway Administration or the Secretary of Labor, or both.

Paragraph 3 says the rule conforms to the Work Hours Act of 1962. Section 4.2 of the 2009 procedure says a payroll with an error is returned for correction and must come back with a written affidavit from each affected worker that proper payment was made.

Interviews, annual reports and trainees

The same rule covers other paperwork on federal-aid work (paragraphs 4, 7 and 8):

  • Employee interviews (paragraph 4): form CAD-440 is the reporting instrument for labor compliance interviews.
  • FHWA-1391 (paragraph 7): each prime and each subcontractor holding a subcontract of $10,000 or more submits the annual report. The Compliance Officer sends the form to the prime each year, and the prime passes it to subs. See our FHWA-1391 guide.
  • Trainees (paragraph 8): submit FHWA-320 in duplicate to the Compliance Officer when each trainee is assigned, and CAD-685 weekly to the Project Engineer. The rule notes that training is a pay item under the contract.

The October 2026 LPA subcontract supplement

MDOT's supplement to FHWA-1273, dated October 6, 2026, sits on MDOT's LPA (Local Public Agency) project documents and applies to LPA subcontract requests. It says each Request for Permission to Subcontract (LPA Form RSP-1) must include a copy of the subcontract, and a completed LPA Form SCC-1 must be attached. It requires the federal contract provisions to be physically incorporated into the subcontract.

The same document says FHWA ended the requirement to physically incorporate Form FHWA-1273 on June 10, 2026 and made its use optional for agencies (91 FR 25492). The supplement keeps the physical incorporation requirement for LPA subcontracts. Our FHWA-1273 changes guide explains the federal change.

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

Who do I send the weekly payroll to on an MDOT project?
The CAD-880 form footer says original and one copy to the Project Engineer. Paragraph 1 of MDOT's rule says CAD-880 goes to the Project Engineer and County Engineer, and paragraph 2 says the Project Engineer has one week to check the payrolls and forward them to the Compliance Officer. The 2009 State Aid procedure instead routes copies to the County Engineer and State Aid, and neither document says which controls, so ask the Project Engineer.
Do I send a payroll for a week with no work?
Yes. The rule requires a negative (NO WORK) statement for the period. When the work is complete, mark the last weekly payroll FINAL.
Which forms apply on a 100 percent state funded project?
The rule requires two copies of the weekly payroll with CAD-880 on those projects. CAD-881 is named for federal-aid projects.
How do I clear a CAD-882 violation?
Per the rule, it stays open until the Compliance Officer has a supplemental payroll, restitution proof signed by the employee, your letter of explanation, and a final FHWA or Department of Labor determination.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Contract Administration rule on statements and payrolls mdot.ms.gov
  2. Cornell LII law.cornell.edu
  3. FHWA-1273 checklist document mdot.ms.gov
  4. CAD-880 form (Rev. 9-2007) osarc.ms.gov
  5. procedure SA II-2-10 (March 3, 2009) osarc.ms.gov
  6. CAD-881 form (Rev. 9-2007) osarc.ms.gov
  7. State Aid forms page osarc.ms.gov

Questions about your project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us