Nevada fringe benefit statement and non-performance payroll report: what each line certifies

Both forms come from the Labor Commissioner's public works forms page. This guide reads the Contractor Fringe Benefit Statement (file name dated 9.4.19) and the Non-Performance Payroll Report (file name dated 08.08.2023), with the Office of the Labor Commissioner (OLC) handbook (July 22, 2026) and overview slides (April 2026) for the rules behind them.

Last reviewed against the sources it cites

The short answer

The Contractor Fringe Benefit Statement lists, by classification, the hourly dollars you pay into each benefit fund so the awarding body can check your payrolls. OLC's slides say to send it with your first payroll, and the form says to send a Supplemental Statement if a rate changes. The non-performance report certifies that you used no employees or owner/operators in the payroll period, and the awarding body must receive it within 15 days after the month ends.

  • The Fringe Benefit Statement says its purpose is to let the awarding body verify bona fide fringe benefit rates when it checks payrolls on the contract, by listing hourly rates for each job classification.
  • Each classification block on the statement has four benefit lines: health and welfare, pension, vacation/holiday, and training and/or other, each with an hourly dollar amount and the fund it is paid to.
  • A printed note on the statement says a Supplemental Statement must be submitted during the progress of work if a change in rate is made.
  • OLC's overview slides say to submit the Fringe Benefit Statement with the first certified payroll report, and that a contractor with no fringe benefits lists nothing on the payroll and checks box 3 on the statement of compliance.
  • The non-performance report says on its face that the awarding body must receive the record no later than 15 days after the month ends.
  • Under NAC 338.098, as printed in the slides, a contractor who employs any worker in a month after sending a non-performance report must submit a certified payroll report for that month.

Two one-page forms, two different jobs

The fringe benefit statement goes in near the start of the job and again when a rate changes. The non-performance report replaces a certified payroll in a month when you had no workers. The forms page lists both under its sample forms for contractors, next to the certified payroll report. Cadence, penalties and the 15th of the month deadline are on our Nevada certified payroll guide, so this page stays on the forms themselves. For other states, see the 50 state table.

The Contractor Fringe Benefit Statement

The form opens with its own purpose: so that bona fide fringe benefit rates "can be verified when checking payrolls," the hourly rates for each benefit must be reported by job classification (statement). It matters when you credit fringes toward the prevailing rate. The handbook says contributions that count as part of wages must be itemized on the payroll as a dollar amount per hour, not a lump sum (handbook). The slides add: if you have no applicable fringe benefits, list nothing on the payroll and check box 3 on the statement of compliance (slides).

Header fields

Field on the formWhat you enter
Contract name and number, project location, today's date, PWP #The job identifiers. The form does not define PWP #. The forms page links a "Request for Public Works Identifying Number", so get the number from your awarding body or that request form.
Name of awarding body, contact person, email, telephone, faxThe public body that receives your payrolls and a contact there
Contractor or subcontractor name, address, license number, telephone, fax, emailYour own business details
Signatory to a collective bargaining agreement: Yes or NoIf Yes, the local's name and number

The classification blocks

Each block starts with a classification, an effective date and Group ID number or numbers. Under it sit four benefit lines, and each asks for an hourly dollar amount and a "Paid To" entry with the fund, plan or program name, address and telephone number (statement).

Benefit lineWhat the form asks
Health and welfareDollars per hour; fund, plan or program name, address, telephone
PensionSame four items
Vacation/holidaySame four items
Training and/or otherSame four items

The page holds two classification blocks and carries a "Page __ of __" line. The form's signature block says to use additional sheets as necessary, and the forms page links a separate additional page for the statement (forms page).

The "Paid To" lines are not decoration. The handbook says a contractor may meet part of the wage obligation with fringes only if the contribution goes to a third person under a fund, plan or program in the worker's name. Unless the money leaves the contractor and reaches that administrator in the worker's name, "there can be no discharge of any obligation" (handbook).

What your signature certifies

The signature block reads: "I certify that the Bona Fide Fringe Benefits meet the requirements of Assembly Bill 190 and that the payments are made to the approved plan, fund(s), or program listed above" (statement). That is two statements. The benefits qualify, and the payments go to the fund named on the form. The handbook defines a bona fide fringe benefit as a contribution made at least monthly to an independent third party under a fund, plan or program set up for the sole and exclusive benefit of the worker and his or her family and dependents, with no assets reverting to the contributing employer (handbook). Check each "Paid To" entry against that definition before you sign.

When to send it, and when to send another

  1. At the start. The slides say to submit the statement with the first certified payroll report (slides).
  2. When a rate changes. A printed note on the form says a Supplemental Statement must be submitted during the progress of work if a change in rate is made (statement).
  3. When the awarding body asks. The handbook says a contractor who counts fringes toward wages must give the Commissioner and the awarding body any information requested to verify compliance (handbook).

The forms page lists no separate Supplemental Statement form, only the statement and its additional page, so ask your awarding body how it wants the new rate shown.

The Non-Performance Payroll Report

This is the form for a period in which you had no workers. NAC 338.098, as printed in the slides and the handbook, says a contractor or subcontractor who employs no workers in a calendar month while engaged on the work submits this report to the awarding body in place of a certified payroll for that month, on the Labor Commissioner's form. The form states the receiving rule on its face: the awarding body must receive the record no later than 15 days after the month ends (report). The copy read here is OLC's, not a copy hosted by any other agency.

Fields

Field on the formWhat you enter
Report #Your running report number
Regular Weekly Report or Final Report for ProjectTick one of the two boxes. The slides ask for a weekly report when non-performance lasts less than a month and on any project with federal dollars; see our Nevada guide
Bid/Project # and PWP-The bid or project number and the PWP number (see the header table above for where it comes from)
Project title; prime contractor nameAs on the contract
Two subcontractor name linesThe form has two subcontractor name lines. The slides' field list names a "2nd Tier Subcontractor (If applicable)" entry
Public body awarding contractThe awarding body
Payroll periodMonth, day and year of the start and the end
Name and title, signature, dateThe person certifying

What the signature certifies

The certification reads: "no employees or owner/operators were used on the construction of this Public Works project during the payroll period above" (report). It covers owners as well as employees. The handbook says there is no owner exception under NRS 338 and that owners and their family members must be paid the prevailing rate for the work they do on the site (handbook). If an owner worked on the job in that period, the report's words do not fit.

Rules around it

  • Any worker ends it. If you employ any worker in a calendar month after submitting a non-performance report, you submit a certified payroll for that month (NAC 338.098(1), in the slides).
  • Not needed on day one. The slides say non-performance reports need not be sent at the start of a project; the first payroll submitted should be a performing one.
  • Three idle months. After 3 consecutive calendar months with no workers, the Commissioner or the awarding body may ask for a final non-performance report or other documentation that your work is complete (NAC 338.098(3), in the handbook).
  • Date stamp. The awarding body stamps each certified payroll or non-performance report with the date it received it (NAC 338.100, per the handbook), so keep proof of delivery.

Before you sign either one

Confirm the form version with your awarding body, since the forms page labels these as sample forms and the handbook says reports may be submitted electronically on the prescribed form (section V.a, handbook), and an awarding body that uses an electronic system must make the reports available electronically (NAC 338.098(4)). Then check the job identifiers against the contract and the PWP number. If a month has even one paid worker, you need a payroll, not the no-work form. See the WH-347 guide if a federal program is also involved.

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

Do I need a Nevada fringe benefit statement if I pay no fringes?
The slides tie the statement to contractors who have applicable fringe benefits. They say that if you have none, you list nothing on the payroll and check box 3 on the statement of compliance (slides).
What is a Supplemental Statement?
It is named in the note printed on the Fringe Benefit Statement: one must be submitted during the progress of work if a change in rate is made.
Who signs the fringe benefit statement?
The form has a printed name and title, signature and date line under the certification (statement). It does not say which officer signs.
Can I use the non-performance report if I worked only a few days in the month?
NAC 338.098(1) is written by calendar month, and if you employed any worker in the month it requires a certified payroll for it (slides). The April 2026 slides add that a non-performing stretch shorter than a month needs a weekly non-performance report, and weekly on any project with federal dollars. Ask your awarding body which cadence it wants. Our Nevada certified payroll guide covers the conflict in full.
Where do these forms go?
The non-performance report goes to the awarding body, not the Labor Commissioner (NAC 338.098, in the handbook). The slides say to provide the Fringe Benefit Statement with the certified payroll report (slides), but no source names who receives it, so ask your awarding body. The slides word this two ways, "with the first CPR" in one place and "with CPR" in another, so ask whether it wants the statement once or with every payroll.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. public works forms page labor.nv.gov
  2. Contractor Fringe Benefit Statement labor.nv.gov
  3. Non-Performance Payroll Report labor.nv.gov
  4. handbook labor.nv.gov
  5. overview slides labor.nv.gov

Questions about your project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us