SCDOT certified payroll: paper to the RCE, an exception on the estimate, and a 10 day audit clock
The South Carolina Department of Transportation (SCDOT) explains certified payroll in staff guides and contract documents. This page reads its payroll entry guide and payment estimate guide (both April 2023), the 2025 Standard Specifications, and its Local Public Agency required provisions.
Last reviewed against the sources it cites
The short answer
Per its April 2023 guide, SCDOT takes certified payroll on paper, sent to the Resident Construction Engineer, and staff key the dates into AASHTOWare. An overdue payroll exception shows on the payment estimate when a daily work report lists your firm on site and no payroll is entered for that week. If your contract uses the 2025 Standard Specifications, Subsection 105.17 lets SCDOT withhold all payments when requested audit records, including the payroll register, are not produced within 10 days.
- SCDOT's April 2023 AASHTOWare payroll guide says prime and subcontractors on federally funded contracts submit certified payrolls to the RCE, and SCDOT staff enter the period dates and received date once the hard copy is received and verified.
- The same guide says an overdue payroll exception appears on the Payment Estimate when a Daily Work Report marks a contractor on site and no payroll is entered for that week, and entering the missing week clears it.
- SCDOT's payment estimate guide says exceptions must be resolved, overridden or acknowledged before an estimate can be submitted for approval, and lists overdue payrolls among the most common.
- Subsection 105.17 of the 2025 Standard Specifications lets SCDOT withhold all payments if requested documents, including the payroll register and job payroll ledger, are not available within 10 days of the request.
- SCDOT's April 2015 audit update says Social Security numbers are no longer required on payrolls submitted to SCDOT.
- SCDOT's LPA procedures, revised May 2014, say the local agency monitors prevailing wage and payroll requirements on federally funded LPA projects.
An overdue payroll exception on your estimate
SCDOT's payroll guide says that when a Daily Work Report (DWR) marks a contractor on site and no payroll is entered for that week, an overdue payroll exception shows on the Payment Estimate. It clears when the missing week's payroll is entered and exceptions are recalculated.
The payment estimate guide says exceptions must be resolved, overridden or acknowledged before an estimate can be submitted for approval, and the RCE role submits it. It lists overdue payrolls among the most common exceptions, but the exceptions it says carry automatic item adjustments are item overruns and insufficient materials. Neither guide says an overdue payroll withholds money or how long an open exception can delay an estimate.
What to do, in order
- Find the week. Ask which DWR dates list your firm; the guide names a "DWR Contractors Payroll" report.
- If your employees worked, get the signed payroll to the RCE and ask that the received date be entered.
- If your firm was not on site, ask the inspector to mark you not on site on the DWR, as the guide allows for a contractor added to create an item posting. After approval, staff create a "dummy" payroll entry for the DWR date.
- If you are the prime and did no work, the guide has staff check the "No employee hours for period" box.
Who submits what, to whom, and how often
| Question | What SCDOT's documents say |
|---|---|
| Who submits | Prime and subcontractors on federally funded contracts submit certified payrolls to the Resident Construction Engineer (RCE). The FHWA-1273 text in the LPA required provisions, Section III, 3.b.(1), makes the prime responsible for the submission of every subcontractor's payroll. SCDOT's guide has every contractor submit to the RCE. Follow your subcontract and the RCE's instruction on how subcontractor payrolls reach the RCE. |
| Form and entry | A hard copy. Once it is received and verified, SCDOT staff in four roles (RCAP, PROJ ENG, ARCE, RCE) enter the period and the received date. The clause allows Optional Form WH-347 or another format with a signed Statement of Compliance (3.b.(2), (4)); see our WH-347 guide. |
| How often | Weekly for each week with covered work (3.b.(1)). Prime payrolls are entered each week after the Work Start Date, and a subcontractor's payroll is required for each period its employees are actively working on the project. |
| Period dates | A period ends 6 days after it begins, and the next begins the day after: seven day weeks, back to back. |
| Social Security numbers | SCDOT said in an April 2015 audit update that they are no longer required on payrolls submitted to it. The current FHWA-1273 text bars full numbers on weekly transmittals; an identifying number such as the last four digits is enough. |
SCDOT's AASHTOWare page offers an external login for consultants and contractors, but the April 2023 payroll guide describes only hard copies entered by SCDOT staff. SCDOT's payroll guide covers the Construction and Materials module, not the Civil Rights and Labor module in our AASHTOWare guide.
What the RCE does with it
A 2010 internal audit of RCE offices, with SCDOT's responses updated in April 2015, shows what verification involved. Inspectors interviewed employees and recorded their rate and job on a Wage Regulation Report that the RCE signed.
The audit also described a four week window after the close of the pay period for submitting payrolls. The FHWA-1273 clause in SCDOT's LPA required provisions says weekly and does not mention four weeks. Read your contract's clause.
Where the RCE reads your payroll again
SCDOT's Equal Opportunity Manual (updated June 19, 2024) has the RCE start the regular Stage-Type Inspection when a project reaches 25 percent of contract value, or as soon as work begins if the project is expected to finish in six months or less. The RCE sends you the form, you complete it and return it to the RCE, and the Office of Civil Rights Programs reviews it. That office may also request one at any time. It covers the prime on every contract of $10,000 or more, and on-site subcontractors (those required to submit certified payrolls) with subcontracts of $10,000 or more who are working in the two weeks after the prime's employee interviews. The form asks for the week ending of your most recent pay period with employees on site and tells you to attach that week's certified payroll, and its headcount table must be based on that payroll. For the July report, see our FHWA-1391 guide. SCDOT's OJT manual (March 4, 2025) has the RCE verify trainee hours against the certified payroll; see our SCDOT OJT guide.
Subsection 105.17: the records audit clock
If your contract references the 2025 Standard Specifications, Subsection 105.17 lets SCDOT audit the contractor's records during the project and for up to 3 years after the closeout letter, whether or not a claim is pending. The audit may begin after 10 days' notice. If requested documents are not made available within 10 days of the request, SCDOT may withhold all payments to the contractor, and the contractor pays the audit costs.
The minimum list includes daily time sheets and superintendent's daily reports, the payroll register, earnings records, payroll tax returns, canceled payroll checks and the job payroll ledger, along with cost, claim and financial records. It is a general records-audit clause: it does not name certified payrolls and sets no payroll penalty.
The clause requires a similar audit clause in every subcontract, and Subsection 108.1 requires subcontracts to carry the same or substantially similar terms, so read the version in yours. Certified payrolls have their own three years, counted from completion of all work on the prime contract (FHWA-1273, Section III, 3.b.(7)), while the audit right counts from the closeout letter. Keep payroll records to the later date.
Local public agency projects
SCDOT's LPA page says SCDOT may delegate management of certain federal-aid projects to a local public agency (LPA). Under its LPA procedures (revised May 2014), the LPA advertises and awards the construction contract (award needs SCDOT's written concurrence), monitors prevailing wage and payroll requirements, and keeps the official project files, and the RCE is given access to them. The FHWA-1273 clause in the LPA required provisions, (its FHWA-1273 text is marked revised June 25, 2026) sends weekly payrolls to the "contracting agency." The payroll guide does not separate LPA projects from SCDOT-let ones, so ask which office takes yours.
SCDOT's LPA supplemental specification lets FHWA-1273 be incorporated by reference, while Subsection 108.1 of the 2025 specifications asks for a certification that federal-aid requirements are physically included in subcontracts. See our FHWA-1273 guide.
Falsification and missing records
The contractor or the agent who pays or supervises payment of the workers signs the Statement of Compliance (3.b.(3)). Falsifying it may bring civil or criminal prosecution under 18 U.S.C. 1001 and 31 U.S.C. 3729 (3.b.(6)), and under 3.d.(2), if records are not submitted or made available, the Federal agency may, after written notice, cause the suspension of any further payment, advance or guarantee of funds, and the failure may also be grounds for debarment. SCDOT's staff guides attach none of this to the overdue payroll exception. See our false certified payroll guide.
Is there a South Carolina prevailing wage law?
The Title 41 chapter list (Labor and Employment) shows no prevailing wage chapter, and the state wage office lists payment of wages and child labor, so none was found. The weekly payroll on SCDOT jobs comes from the federal Davis-Bacon provisions. Other states are in our state requirements table.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Does SCDOT have a portal where I upload certified payroll?
The estimate shows an overdue payroll exception but I sent the payroll. What now?
Do I send a payroll for a week my crew did not work?
How long do I have to produce records in an SCDOT audit?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- payroll entry guide scdot.org
- payment estimate guide scdot.org
- 2025 Standard Specifications scdot.org
- Local Public Agency required provisions scdot.org
- April 2015 audit update scstatehouse.gov
- LPA procedures scdot.org
- AASHTOWare page scdot.org
- Equal Opportunity Manual scdot.org
- OJT manual scdot.org
- LPA page scdot.org
- Title 41 chapter list scstatehouse.gov
- lists payment of wages and child labor llr.sc.gov