Prevailing wage for foremen, superintendents and project managers in California

The rule comes from the Labor Commissioner's Public Works Manual (October 2023 edition), section 2.3, applying Labor Code 1771 and Labor Code 1772. This page covers which titles go on certified payroll and how to record a day that mixes supervising and labor.

Last reviewed against the sources it cites

The short answer

A foreman, superintendent or project manager goes on California certified payroll for the time he or she performs labor on the public works project. The title does not decide it; the duties do. Someone who only supervises, plans or manages and does no covered work is not triggered by presence on the project alone.

  • The Labor Commissioner's Public Works Manual (October 2023), section 2.3, says a worker's title or status is not determinative; what counts is whether the duties performed on the project are covered work.
  • The same section of the Manual says a working foreman or working superintendent, one who performs labor on the project along with supervisorial duties, is entitled to not less than the prevailing rate for the type of work performed.
  • Under Manual section 2.3, a person with one of those titles who does not actually perform covered work is not triggered by presence alone.
  • Labor Code 1776(a) requires payroll records showing work classification and straight time and overtime hours worked each day and week for each employee employed in connection with the public work.
  • Section 3.2.7.1 of the Manual says that when a worker works in two or more classifications in one workday, all hours count toward overtime and the worker is paid the overtime rate for the type of work performed during the overtime hours.

Short answer: yes, if the person performs labor on the public works project. A working foreman or working superintendent is owed at least the prevailing rate for the type of work performed. A project manager, estimator or office employee who does no covered work on the project is not triggered by presence alone. The duties decide, not the title.

What the rule says

Section 2.3 of the Public Works Manual is headed "Title or Status of Worker Irrelevant." It says a worker's title or status with the employer does not decide coverage. What decides it is whether the duties performed on a public works project are covered work. Someone who performs skilled or unskilled labor on the project is entitled to the applicable prevailing wage "for the time the work is performed," whether the person holds a status such as partner or owner, or a title such as president, vice-president, superintendent or foreman.

The Manual then applies it to the titles in this page's name. A "working" foreman or a "working" superintendent, one who performs labor on the project in connection with supervisorial responsibilities, is entitled to compensation at not less than the prevailing rate for the type of work performed. If a person with one of those titles does not actually perform covered work on the project, his or her presence alone does not trigger the prevailing wage requirement.

The underlying statutes are short. Labor Code 1771 requires the general prevailing rate to be paid to all workers employed on public works, except for public works projects of $1,000 or less, and Labor Code 1772 says workers employed by contractors and subcontractors in the execution of a public works contract are deemed employed on public work.

Which titles go on certified payroll

Use the title only as a prompt to look at the duties. The Manual names foremen and superintendents; the project manager and office rows are our application of the same duties test, so check a close case with the awarding body.

PersonOn certified payroll?
Working foreman, who leads the crew and also works with the toolsYes, for the time labor is performed, at not less than the prevailing rate for the type of work performed (Manual 2.3)
Working superintendent, who supervises and also does labor on the projectYes, on the same terms (Manual 2.3)
Foreman or superintendent who only directs, inspects or coordinates and performs no covered workNot triggered by presence alone (Manual 2.3)
Project manager, estimator or office staff who perform no labor on the projectSame test: no covered work performed, so presence alone does not trigger it
Any of them who picks up tools on the project for part of a dayYes for that time. See the split day below
Owner, partner or officer who performs labor on the projectYes for the time labor is performed. Status such as owner or partner does not exempt the work (Manual 2.3)

For the wider question of who belongs on a filing at all, see our guide to who goes on California certified payroll.

Salaried supervisors

A salary does not take a working foreman or superintendent out of the rule. Manual section 2.3.1 says a salaried employee who performs skilled or unskilled labor on a public works project must be paid not less than the applicable prevailing wage for all hours during which the labor is performed. It has the employer calculate the regular hourly rate from the salary actually paid, and that rate applies only to straight-time hours. Labor during overtime hours, or on Saturdays, Sundays or holidays, must be paid at the premium rates in the determination in addition to the regular salary. Our guide to salaried employees and prevailing wage covers that calculation.

A day that mixes supervising and labor

Section 2.3 ties the entitlement to "the time the work is performed." So the unit to track is the block of time spent doing covered work, not the person's title for the day. The Manual does not set a rule for how to treat the hours the same person spends only supervising, so keep your records of the labor time clear enough to show what was labor.

When the same worker works in two or more classifications in one day, Manual section 3.2.7.1 gives the mechanics. Each block is paid at the rate for its classification, all hours in the day count for overtime, and overtime hours are paid at the overtime rate in effect for the type of work being performed during those hours. The Manual's own example is a worker who spends four hours in one classification and six in another: four hours at the first classification's straight-time rate, four at the second's straight-time rate, and two at the second's overtime rate for the hours past eight. The employer must keep records showing the worker was paid the correct rate for all hours worked in each classification. Our classification guide covers two trades in a day in full.

When the higher rate can apply to the whole task

Manual section 4.1.4 adds a caution. Where a worker does some work that resembles a lower-paid classification as part of the assigned task in a higher-paid classification, the higher rate can apply to all the hours. The Manual says that analysis is not meant to apply to every day a worker shows two classifications, and that a contractor is generally not required to pay more than the determination specifies for the type of work performed. It also says that where the records are unclear, uncertainties will likely be resolved in favor of worker testimony about the duties actually performed. Records that show the duties by block are the contractor's protection.

How to record it

Labor Code 1776(a) requires each contractor and subcontractor to keep accurate payroll records showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each employee employed in connection with the public work. Manual section 3.1 says the work classification is the craft title fixed by the Director on the prevailing wage determinations, as set under Labor Code 1773, and that records identifying a worker only by status are inadequate.

  1. Pick the craft title for the labor. Look at what the person does with the tools and use the matching classification title on the determination for that craft and county. Do not record "foreman" or "superintendent" as the classification unless the determination lists it as a title. Our classification guide explains how to find it.
  2. Log labor time by day. Have the person or the field lead note the hours of labor and the craft each day, with job and date. This is the record that shows what was labor.
  3. Enter straight and overtime hours by day and week. Count all hours in the workday toward overtime, including across classifications.
  4. Pay each block at its rate. For a salaried person, convert the salary to an hourly rate and check it against the determination (Manual 2.3.1).

The recordkeeping checklist lists the other records to keep. Read the determination and footnotes for the foreman's craft and county before you set pay.

What to do next

List the people on your crew with titles like foreman, lead, superintendent or project manager. For each, ask whether they performed labor on the project this week and keep a time note by day. Anyone with labor hours goes on the payroll at the craft's classification for those hours. Questions about a close case go to the awarding body or the Labor Commissioner, who enforces the rule.

WellStanding prepares the WH-347 and the eCPR from the payroll export you already run, and a person reviews every filing. You review the finished filing and sign the certification in one step, and nothing is filed until you have signed; we never sign for you.

Questions

Does a superintendent need to be on certified payroll?
Only for time spent performing labor on the project. Under section 2.3 of the Public Works Manual, a working superintendent is owed at least the prevailing rate for the type of work performed, and a superintendent who does no covered work is not triggered by presence alone.
Does a foreman get a different prevailing wage?
The Manual says a working foreman is entitled to not less than the prevailing rate for the type of work performed. We did not read a foreman rate in a current determination, so check the determination and footnotes for your craft and county.
What if my superintendent works the tools for only part of a day?
Record the labor block at the classification for that work and count all the day's hours for overtime (Manual 3.2.7.1). Keep a daily time note that shows what was labor.
Does a salary cover prevailing wage for a working foreman?
Only if the hourly rate worked out from the salary meets the prevailing rate, and only for straight-time hours. Overtime, Saturday, Sunday and holiday labor needs the premium rates in addition to the salary (Manual 2.3.1).

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Public Works Manual dir.ca.gov
  2. Labor Code 1771 leginfo.legislature.ca.gov
  3. Labor Code 1772 leginfo.legislature.ca.gov
  4. Labor Code 1776 leginfo.legislature.ca.gov
  5. Labor Code 1773 leginfo.legislature.ca.gov

Foreman turning a wrench? First filing free

Send the payroll export you already run. We turn it into the WH-347 and the DIR eCPR filing, checked by software and verified by a person. First filing free, before you pay us anything. $995 one time setup, then $249 per month flat for crews up to 25 workers.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallFirst filing free