AB 1198: mid-project prevailing wage increases on California public works

This page reads the chaptered text of AB 1198 (Haney), which the Governor signed on September 27, 2026, against Littler's alert and DIR's prevailing wage FAQ. The official leginfo bill text refused our automated read, so the statutory wording below was read in the copy of the chaptered bill on CalMatters Digital Democracy, which lists it as Chapter 513, Statutes of 2026. Check leginfo before you rely on a section number.

Last reviewed against the sources it cites

The short answer

AB 1198 (Chapter 513, Statutes of 2026) changes Labor Code 1773.6 so a new prevailing wage determination applies on its effective date to covered contracts, even after bids. The law is operative July 1, 2027, and covers contracts awarded, or noticed to bidders, after July 1, 2027, with an awarded prime contract value of $35 million or more. Affordable housing projects that are 100 percent restricted keep the old rule.

  • New Labor Code 1773.6(a)(2) applies a determination on its effective date to a contract awarded or noticed to bidders after July 1, 2027, if the awarded prime contract value is $35,000,000 or greater.
  • Section 1773.6(b) (leginfo bill text; CalMatters copy) lets a contractor, awarding body, or craft representative file a verified petition within 20 days after publication of the new determination, on the ground that it was not determined under section 1773.
  • Under 1773.6(c), a determination issued by the Director is effective 10 days after issuance, and DIR's FAQ says general determinations issue February 22 and August 22.
  • Section 1773.6(d) and new section 1773.65 keep the old no-mid-project-change rule for housing developments that are 100 percent restricted as affordable, excluding managers' units.
  • Littler's alert notes the new law does not say who bears the cost of a mid-project increase.

The short version

Until now, once an awarding body published the notice to bidders, a newer determination did not reach that contract. For large contracts, AB 1198 ends that. The amended Labor Code 1773.6 becomes operative on July 1, 2027. From then, a new determination applies on its effective date to a covered contract, so rates can change while you are on the job. Littler's alert says the bill takes effect January 1, 2027 but its substance is not operative until July 1, 2027, and that the current section stays in force until then.

Who is covered

All of the following must be true, per new section 1773.6 as it reads in the chaptered text:

  • The contract is one "under this chapter," meaning the public works prevailing wage chapter of the Labor Code.
  • It is awarded, or the notice to bidders is published, after July 1, 2027 (1773.6(a)(2)).
  • The awarded value of the prime contract is $35,000,000 or greater (1773.6(a)(2)).
  • It is not a qualifying affordable housing project (see the exception below).

The test is the value of the prime contract, not your subcontract. Littler reads it that way: a subcontractor on a covered project is covered whatever the size of its own scope. A $400,000 subcontract under a $60 million prime is inside the rule. A $20 million subcontract under a $30 million prime is not.

How it differs from the asterisk and predetermined-increase rules

RuleWhat moves your rateKnown at bid?
Predetermined increase (Labor Code 1773.9(c)(1))A definite, predetermined change in a collective bargaining agreement that the Director builds into the determinationYes. It is in the determination you bid from (see our asterisk guide)
Current 1773.6, until it goes inoperative on July 1, 2027Nothing after the notice to bidders: a later determination "shall not be effective as to any contract for which the notice to bidders has been published"Yes
New 1773.6, operative July 1, 2027, contracts awarded or noticed after that dateAny new determination, on its effective date, whether or not it was foreseeable at bidNo

Littler adds that AB 1198 does not amend section 1773.9, so predetermined increases still work as before, but on a covered contract a new determination applies mid-project whether or not the increase would have counted as predetermined.

How a mid-project change works

  1. The cycle. The statute now speaks of a "semiannual period" in place of a quarterly one. DIR's FAQ says general determinations issue twice a year, on February 22 and August 22.
  2. The effective date. Under 1773.6(c), a determination is effective 10 days after issuance, and the Director must put an issue date on it. It stays in effect until the Director modifies, rescinds or supersedes it. Littler flags uncertainty over how the 10-day rule interacts with a pending petition.
  3. The petition. Under 1773.6(b), any contractor, awarding body, or representative of an affected craft, classification or type of work may file a verified petition within 20 days after publication of the new determination. The only ground is that the rate was not determined in accordance with section 1773. A copy goes to the awarding body within two days, and the petition must set out its facts.
  4. The decision. The Director investigates or holds a hearing and decides within 20 days after filing, or a longer period agreed by the Director, the awarding body and all interested parties. That decision is final.

The pre-bid petition in section 1773.4 is separate and unchanged by the text we read. See our petition guide for that route.

The exception for affordable housing

Section 1773.6(d) says the new section does not apply to contracts for a housing development project if 100 percent of the units, excluding managers' units, are restricted by deed, a regulatory agreement with a governmental agency, or another recorded document as affordable housing for persons and families of low or moderate income as defined in Health and Safety Code section 50093, or are covered by an agreement providing housing subsidies for that purpose. For those projects, new section 1773.65 keeps the old rule: a determination is not effective as to a contract for which notice to bidders has been published or that has been awarded. Littler reads the exemption as narrow and says mixed-income projects do not appear to qualify.

What the law does not settle

Littler lists open questions it says DIR guidance or courts will have to answer. The ones that matter most to a subcontractor:

  • Whether the rule applies when notice to bidders was published before July 1, 2027 but the award came after.
  • How the $35 million test works if change orders move the prime contract above or below it after award.
  • Which rate governs payroll while a petition is pending, since a Director's decision takes effect 10 days after issuance.
  • How the new petition process fits with section 1773.4.

Littler also says the law does not say who pays for a mid-project increase, and that DIR had not yet issued guidance specific to AB 1198. We found no DIR guidance either. Treat the cost allocation as a contract question, not a statutory one. The law creates no new penalties; an unpaid updated rate falls under the existing enforcement rules. Separately, SB 909 raises several of those penalties.

Worked example

This is a hypothetical, built from the statute's own text. An awarding body publishes a notice to bidders in September 2027 for a $52 million prime contract. You hold a $1.8 million electrical subcontract, and the job runs 30 months. It is covered: it is noticed after July 1, 2027 and the prime is over $35 million. A new general determination issues February 22, 2028. Ten days later, on March 3, 2028, its rates apply to the work you perform. If you want to challenge it, a petition is due within 20 days after publication, and a copy goes to the awarding body within two days of filing. Had the same job been a $34 million prime, none of this would apply and your bid-date rates would hold, subject to any predetermined increase.

What to do next

  1. Confirm coverage at bid. Ask for the awarded prime contract value, the notice-to-bidders date, and whether the project is a fully restricted affordable housing development.
  2. Price the risk. The bid-date rate may no longer hold on a covered job. Look at escalation, change-in-law, notice and flow-down terms in your subcontract, because the statute does not say who bears the cost.
  3. Calendar the cycle. Check each February and August determination for your classifications, and note the 20-day petition clock from publication.
  4. Split payroll at the effective date. Hours worked on or after the effective date take the new rate, in the middle of a pay period if need be. Our determination guide shows where to find the issue date and classification rows.
  5. Keep the record. On a job near the threshold, keep the original awarded value and every change order.

Handing it over

WellStanding prepares the WH-347 and the eCPR from the payroll export you already run, and a person reviews every filing. When a rate changes mid-job, the right rate has to land on the right week's report. You review the finished filing and sign the certification in one step, and nothing is filed until you have signed; we never sign for you. See certified payroll deadlines for the filing clock.

Questions

What is AB 1198?
It is a 2026 law, Chapter 513, Statutes of 2026, that amends Labor Code 1773.6 and adds 1773.65. The law is operative July 1, 2027, and covers contracts awarded or noticed to bidders after that date. A new prevailing wage determination then applies on its effective date to covered public works contracts, including a determination that issues after bids are submitted. Whether a notice to bidders published before July 1, 2027 with an award after is covered is unsettled.
Which contracts does AB 1198 cover?
Contracts awarded, or noticed to bidders, after July 1, 2027, where the awarded value of the prime contract is $35,000,000 or greater, other than fully restricted affordable housing developments (chaptered text, 1773.6(a)(2) and (d)).
Does it apply to a subcontractor with a small subcontract?
Yes. The threshold is the awarded value of the prime contract, and Littler reads that to mean a subcontractor is covered regardless of the size of its own subcontract.
Can I challenge a new determination on my job?
A contractor, awarding body, or craft representative can file a verified petition within 20 days after publication, on the ground that the rate was not determined under section 1773. The Director decides within 20 days of filing unless the parties agree to longer.
Does AB 1198 change predetermined increases or the asterisk rules?
Littler says it does not amend Labor Code 1773.9. Our asterisk guide covers those rules. On a covered contract, a new determination now applies whether or not it was predetermined.
Who pays for a mid-project increase?
The law does not say, according to Littler. Check your subcontract's escalation and change-in-law terms before you bid.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Littler's alert littler.com
  2. prevailing wage FAQ dir.ca.gov
  3. leginfo bill text leginfo.legislature.ca.gov
  4. CalMatters Digital Democracy calmatters.digitaldemocracy.org
  5. Section 1773.6(d) leginfo.legislature.ca.gov
  6. Labor Code 1773.9 leginfo.legislature.ca.gov
  7. section 1773 leginfo.legislature.ca.gov
  8. section 1773.4 leginfo.legislature.ca.gov

Rates changing mid-job? First filing free

Send the payroll export you already run. We turn it into the WH-347 and the DIR eCPR filing, checked by software and verified by a person. First filing free, before you pay us anything. $995 one time setup, then $249 per month flat for crews up to 25 workers.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallFirst filing free