How to challenge a California prevailing wage rate or ask for a special determination
The rules are in Labor Code 1773.4 and the DIR regulations at 8 CCR 16302 and 8 CCR 16202. The Labor Code text was read on a public republisher because the legislature's own site refused automated access.
Last reviewed against the sources it cites
The short answer
A prospective bidder, a craft representative, or the awarding body can file a verified petition with DIR within 20 days after the call for bids starts advertising. A copy goes to the awarding body within two days (excluding weekends and holidays under the regulation). For a craft with no general determination, 8 CCR 16202 has the awarding body request a special determination at least 45 days before advertising.
- Labor Code 1773.4 lets a prospective bidder, a representative of a craft involved, or the awarding body file a verified petition within 20 days after advertising of the call for bids begins.
- Under 8 CCR 16302(d), a petitioner that is not the awarding body files a copy with the awarding body within two days, excluding weekends and holidays, and an affidavit of that filing with DIR within five days.
- 8 CCR 16202(a) requires an awarding body's request for a special determination to be submitted at least 45 days before the bid advertisement date.
- On notice of a petition, the awarding body must extend the bid closing date until five days after the Director's determination, per Labor Code 1773.4.
- A petition is filed only when DIR actually receives it: 8 CCR 16302(b) deems a paper filed upon actual delivery and receipt.
There are two separate routes. A petition to review challenges a rate the Director already set. A special determination fills a gap when a craft has no rate at all. Both start with the call for bids, so the dates matter most.
The 20-day petition to review a rate
The statute gives you 20 days "after commencement of advertising of the call for bids" to file a verified petition with the Director of Industrial Relations. The statutory ground is that the rate was not determined in accordance with Labor Code 1773.
Who can file
Section 1773.4 names three filers: a prospective bidder or the bidder's representative, a representative of any craft, classification or type of worker involved, and the awarding body. The regulation sends you to the definition of interested party in 8 CCR 16000. That definition includes a contractor or subcontractor likely to bid on or perform the work.
What the petition must contain
8 CCR 16302(c) lists the contents. The main items are:
| Item | What 16302(c) asks for |
|---|---|
| Who you are | Name, address and telephone of the filer and verifier, and whether you are an awarding body, a prospective bidder or a craft representative |
| The bid | The awarding body, the date and place the call for bids was first published, and an accurate copy of it |
| The defect | How the rate fails to comply with Labor Code 1773, and the rate you claim is correct with the facts behind it |
Where to file, and when the clock stops
- Count 20 days from the first advertisement.
- File with the Director. 8 CCR 16302(a) allows filing by mail to the Chief of the Division of Labor Statistics and Research, P.O. Box 420603, San Francisco, CA 94142, or in person at 455 Golden Gate Avenue, 5th Floor, San Francisco, CA 94102. Under subdivision (b), a paper is filed on "actual delivery to and receipt by" the recipient.
- Copy the awarding body. The statute requires a copy within two days. The regulation lets you send it with the original petition or within two days after, excluding Saturdays, Sundays and holidays.
- File the affidavit. If you are not the awarding body, you must file an affidavit of that filing with the Chief within five days, excluding Saturdays, Sundays and holidays.
The petition covers the rate "specified in or referred to in the call for bids." For a coverage question, see our guide to formal DIR coverage determinations.
What happens to the bid while the petition is pending
The statute puts the bid on hold. When the awarding body gets notice of the petition, it must extend the closing date for bids, or the start of work, until five days after the Director's determination. The Director's determination must be included in the contract.
How long DIR has to decide
Labor Code 1773.4 sets the target: within 20 days after the petition is filed, or a longer period agreed by the Director, the awarding body and all interested parties, the Director makes a determination and sends it in writing to the awarding body and the interested parties.
8 CCR 16304(d) says that when a hearing is held, the decision goes to all parties no later than 20 days after the hearing, "except earlier or later as special circumstances warrant." Ask the Division of Labor Statistics and Research which date it is working to.
If there is a hearing
Under 16304, notice goes to the known interested parties at least one week ahead, witnesses testify under oath, and parties may present evidence and argument. After a hearing, the decision under 16304(d) is final for judicial review, although the Director may reconsider on the Director's own initiative only.
Under 8 CCR 16303(a), review is under Code of Civil Procedure section 1085. Talk to an attorney about representation at a hearing and about any court challenge.
Special determinations for a craft with no rate
A general determination may not list the craft, classification or type of worker your contract needs. 8 CCR 16202 covers that case in two parts:
- Awarding body request. The awarding body "shall request" a determination from the Director for a craft not covered by a general determination, and must submit the request at least 45 days before the bid advertisement date. DIR's prevailing wage FAQ words it as "may request," with the same 45-day lead.
- If the awarding body does not state the rate. Where the awarding body does not specify the rate as Labor Code 1773.2 requires, an interested party may petition under section 1773.4. The Labor Commissioner may also ask the Director for a determination before the bid is let.
Referral to the Director's office and other steps
The petition route is tied to the 20-day window. Separately, 8 CCR 16301 says any new or unresolved issue, other than of a routine nature, as to coverage or the amount of the prevailing wage, raised by an awarding body or other interested party, may be referred to the Chief of the Division of Labor Statistics and Research for final determination, subject to 8 CCR 16300(b), under which the Director reserves the right to make all final determinations. See our guides on reading a determination and on predetermined increases.
A classification dispute is a scope question. See which craft classification applies.
Getting the payroll right once the rate is set
Whatever the Director decides becomes the rate on your certified payroll. WellStanding prepares the WH-347 and the eCPR from the payroll export you already run, and a person reviews every filing. You review the finished filing and sign the certification in one step, and nothing is filed until you have signed; we never sign for you.
Questions
Can I file a petition after I have won the bid?
Does a petition delay my bid?
Do I have to send a copy to the awarding body?
Can a subcontractor file?
Can I ask DIR for a special determination myself?
Can I appeal the Director's decision?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Labor Code 1773.4 leginfo.legislature.ca.gov
- 8 CCR 16302 dir.ca.gov
- 8 CCR 16202 dir.ca.gov
- Labor Code 1773.4 california.public.law
- Labor Code 1773 leginfo.legislature.ca.gov
- 8 CCR 16000 dir.ca.gov
- 8 CCR 16304 dir.ca.gov
- 8 CCR 16303 dir.ca.gov
- prevailing wage FAQ dir.ca.gov
- Labor Code 1773.2 leginfo.legislature.ca.gov
- 8 CCR 16301 dir.ca.gov
- 8 CCR 16300 dir.ca.gov