Final certified payroll on a Davis-Bacon job: what it must say and what gets checked at closeout
This page reads the clause in 29 CFR 5.5, HUD Handbook 1344.1 chapter 4 and chapter 5, and FHWA-1273.
Last reviewed against the sources it cites
The short answer
The Davis-Bacon clause has no separate final payroll form. You submit a signed payroll with a Statement of Compliance for every week of covered work, and the last one is your final. HUD says to mark each employer's last payroll Final. Agencies can suspend payment when records are not submitted or worker interviews are refused, after written notice.
- Payrolls go in weekly for each week in which covered work is performed, each with a signed Statement of Compliance, under 29 CFR 5.5(a)(3)(ii), which eCFR showed as up to date as of November 3, 2026.
- HUD Handbook 1344.1, paragraph 4-11(C) (January 2023) says the payroll for each employer's last week of work should be clearly marked Final.
- Under 29 CFR 5.5(a)(3)(i)(A), payrolls and basic records must be kept at least 3 years after all work on the prime contract is completed.
- On a HUD-assisted project, the Handbook's paragraph 5-8 has a final closing review that can condition closing on a deposit to cover wage restitution and liquidated damages.
- FHWA-1273 (revised June 25, 2026) says a breach of its required provisions may be grounds for withholding final payment, and notes that use of the form became optional for the contracting agency on June 10, 2026.
Is there a separate "final" payroll?
Not in the federal clause. 29 CFR 5.5(a)(3)(ii)(A) says the contractor "must submit weekly, for each week in which any DBA- or Related Acts-covered work is performed, certified payrolls." Your final payroll is the payroll for the last week you had covered work on site. It carries the same content and the same signed Statement of Compliance as every other week.
HUD's Handbook, paragraph 4-11(C), says the payroll for the last week of work by each employer "should be clearly marked Final." The Georgia Department of Community Affairs (2025 federal labor standards training) says its payrolls must be numbered, with the last labeled "Final Payroll." Other pages on this site mention a Final check on the WH-347. Check the current form on the DOL page linked below before relying on it, and follow your agency's instruction.
The Wage and Hour WH-347 instructions say the Statement of Compliance must be signed by the contractor or subcontractor, or their agent who paid or supervised the payment of the workers. Legally valid electronic signatures are acceptable, and photocopied or scanned copies of signatures do not satisfy the requirement. See our WH-347 guide.
What the last payroll must say
The content is the same as for every other week: accurate and complete payroll information and a signed Statement of Compliance, under 29 CFR 5.5(a)(3)(ii)(B) and (C). Our WH-347 guide and page on HUD signatures cover the form and the signature. Falsifying any certification may bring civil or criminal prosecution under 18 U.S.C. 1001 and 31 U.S.C. 3729, according to 29 CFR 5.5(a)(3)(ii)(F). WellStanding does not sign.
One conflict to know about. HUD's Handbook (January 2023, chapter 4), paragraph 4-3(D), asks for an original ink signature and rejects photocopies and facsimiles. The current eCFR text accepts a legally valid electronic signature. Ask the HUD or local agency reviewer which it accepts before you send the last payroll, and see our page on HUD signatures.
Contracts before and after October 23, 2023
The Federal Register final rule (88 FR 57526, August 23, 2023) says its provisions, with one exception in part 1, "are applicable only to contracts entered into after October 23, 2023." So contracts entered before that date carry the earlier clause text, shown in the August 23, 2023 eCFR text, and later contracts carry the clause in the October 23, 2023 eCFR version, which is the current text apart from later edits. 29 CFR 5.5(e) says the clauses are effective by operation of law "whether or not they are included or incorporated by reference into such contract."
| Topic | August 2023 text | Current text |
|---|---|---|
| Retention clock | Records preserved "for a period of three years thereafter," after the course of the work | At least 3 years "after all the work on the prime contract is completed," for records, certified payrolls and contract documents |
| Records not produced to Wage and Hour | Suspension of payment and possible debarment | Same, plus a bar on using unproduced records as evidence in a proceeding under 29 CFR part 6 |
The clock runs from completion of all work on the prime contract, not from your own last day. A subcontractor who finishes in month three of a two year job keeps records until three years after the prime contract work ends.
What a HUD closeout reviews
On a HUD-assisted project, paragraph 5-8 requires the Labor Standards Specialist or Local Contracting Agency to run a final closing review. The review asks whether any labor standards issue cannot or will not be resolved before closing. It covers the project files and compliance review records, including any noted discrepancies or enforcement actions.
The specialist then gives written clearance in one of two forms. Either there are no outstanding issues and closing goes ahead without condition, or issues remain and closing is conditioned on a deposit to the U.S. Treasury large enough to cover wage restitution and liquidated damages found or likely to be found due. For a Local Contracting Agency, HUD "imposes no particular protocols" but says all issues must be fully resolved or covered by something like an escrow account.
What the reviewer sees comes from monitoring during the job. Paragraph 5-9 describes spot-checks of payrolls for completeness, certification, obvious underpayments, unapproved classifications and signs of falsification, plus on-site worker interviews. Interview forms are compared with the matching payroll, and the closing review covers noted discrepancies. Our HUD-11 guide explains that form.
What FHWA-funded jobs add
FHWA-1273, section I, paragraph 3, says a breach of the required contract provisions "may be sufficient grounds for withholding of progress payments, withholding of final payment, termination of the contract, suspension / debarment or any other action." Section III repeats the 3 year retention rule for certified payrolls. The form's first note says that effective June 10, 2026 the requirement to physically incorporate it was eliminated and its use is now optional for the contracting agency, It also says "Contracting agencies must continue to ensure compliance with the provisions cited in Form FHWA-1273 in accordance with the provisions regardless of the use of Form FHWA-1273." See also our page on the 2026 FHWA-1273 changes.
The regulation itself also ties payment to records. Under 29 CFR 5.5(a)(3)(iv)(B), if records are not submitted or made available, or worker interviews on the job are refused, the agency may, after written notice, suspend further payment, advance or guarantee of funds.
A closeout checklist
- List every pay week in which you had covered work on the site. Match each to a signed payroll the agency has.
- For idle weeks, follow your agency's rule. Our no work week guide compares them. HUD paragraph 4-3(C) says employers need not report no work weeks "provided that" the payroll reports are numbered sequentially or the employer has given written notice that its work was suspended.
- Mark the last payroll as the agency requires. On HUD work, write Final.
- Answer any open worker interview or payroll discrepancy. If an underpayment is found, pay it and send the corrected payroll. See restitution and corrected payroll.
- Confirm the apprentice registrations and fringe records behind each payroll are in your file.
- Start the 3 year retention clock from completion of all work on the prime contract. Ask the prime contractor for that date.
State and local agencies add their own rules
The Georgia Department of Community Affairs training shows a closeout package beyond payrolls. It lists a Final Wage Compliance Report that is completed at the end of the project, captures restitution information and is required in the closeout package. Arizona DOT's certified payroll guide and the City of Sierra Vista's submittal page both refused our fetch, so this page does not describe their closeout rules. Ask your agency for its closeout steps in writing.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Do I have to write "Final" on the last payroll?
Can the agency hold my last payment over payroll problems?
How long do I keep the payrolls after the job?
Does the final payroll need a Statement of Compliance?
What if the project closes with a wage issue still open?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- 29 CFR 5.5 ecfr.gov
- HUD Handbook 1344.1 chapter 4 hud.gov
- chapter 5 hud.gov
- FHWA-1273 fhwa.dot.gov
- 2025 federal labor standards training dca.georgia.gov
- WH-347 instructions dol.gov
- final rule (88 FR 57526, August 23, 2023) federalregister.gov
- August 23, 2023 eCFR text ecfr.gov
- October 23, 2023 eCFR version ecfr.gov