DC Water Certified Payroll: What the Contract Requires and How DC Water Checks It

Read from DC Water's own documents: the Instructions to Bidders template (IFB template dated September 20, 2014), the General Conditions (January 2020), the DC Water Works Program (effective October 1, 2016, amended March 11, 2020) and a January 9, 2013 Governance Committee presentation.

Last reviewed against the sources it cites

The short answer

On DC Water construction work subject to Davis-Bacon, every contractor at any tier submits weekly certified payroll with a signed Statement of Compliance through DC Water's automated online reporting system (Art. 14.2). DC Water checks it with onsite worker interviews and desk audits. According to a 2013 DC Water presentation, responses to violations may run from a memo to file up to withholding and debarment.

  • The DC Water Instructions to Bidders template (Art. 14.2) says certified payrolls from contractors at any tier are submitted to DC Water through the automated online reporting system.
  • The DC Water Works Program (effective October 1, 2016, amended March 11, 2020), section 10.2, requires weekly certified payroll reports from contractors with construction contracts of $2,000 or greater on applicable DC Water projects.
  • Under Art. 14.5 of the template, each certified payroll must come with a Statement of Compliance signed by the person who pays or supervises the payment of the employees.
  • DC Water's January 9, 2013 Governance Committee presentation lists wage restitution, contract payment withholding and potential debarment as possible remedies for serious and willful violations.
  • On projects subject to the Service Contract Act, section 10.2.1 of the DC Water Works Program replaces weekly payroll with quarterly reports of workers, classifications and hourly rates.

Your project is assigned a compliance officer who reviews the periodic Works Program reports (Works Program, section 11.1), and DC Water's 2013 presentation lists certified payroll review among its checks. If a payroll is missing from DC Water's system, a classification does not match the wage decision, or a worker's answer on site does not match your report, this page shows what the documents say happens next.

Two limits apply. The Instructions to Bidders is a template, not your contract, and the Governance presentation is from 2013. Your contract's Section 00 76 00 (Labor Provisions) and the wage decision in it control. DC Water's procurement page is where current solicitations are listed, so read your own bid documents against what follows.

Who submits payroll to DC Water, and where

The template says all construction contractors performing physical work on the jobsite are subject to the Davis-Bacon wage determination, which requires weekly certified payroll. Payrolls from contractors at any tier go to DC Water through its automated online reporting system (Instructions to Bidders, Art. 14.2). The requirements flow down to every tier working onsite (Art. 14.3). Each tier reports.

The Works Program names a DC WaterWorks Compliance Database that tracks payment of prevailing wages, resident workforce hours, apprenticeship hours and new hires, and says all compliance reports are submitted through it (sections 2.0 and 10.4). The Instructions to Bidders separately says payrolls go through an automated online reporting system. Neither document names a software vendor, so ask your DC Water compliance officer which login to use.

The Works Program ties weekly payroll to construction contracts of $2,000 or greater on applicable projects (section 10.2). Your wage decision settles what is applicable. The template also carries two alternatives in Art. 14.1, the DC Living Wage Act or prevailing wage, and tells the drafter to delete the one that does not apply. Check which one your contract kept.

What goes on each weekly payroll

ItemWhat the document says
ClassificationsMust conform to the job classifications in the wage determination, including the Work Classification Group number if applicable (Art. 14.4)
Statement of ComplianceRequired with each certified payroll, as federal requirements provide, signed by the person who pays or supervises payment of the employees (Art. 14.5)
FormThe 2013 presentation says WH-347 "or similar approved form" for prime and subs. Federal rules allow Form WH-347 or any other format with the required information (29 CFR 5.5(a)(3)(ii)(B)). DC Water's 2013 deck says "approved" and the federal rule allows any format with the required information. Use the form your DC Water compliance officer accepts in the online system, or ask before the first submission.
Reviewed itemsNames and addresses, Social Security number, hours (standard, overtime, double time), pay rate checked against the prevailing wage, deductions, net pay, how fringes are paid, and an original signature from an authorized employee (2013 checklist). The deck is from 2013. The federal rule now says weekly payrolls need only an individually identifying number for each worker, such as the last four digits of the Social Security number (29 CFR 5.5(a)(3)(ii)(B)).
Weeks with no workA contractor that has reported before but has no employees on the project that week submits a "no work" report (2013 checklist)
Wage decision timingA wage determination issued after the contract was executed does not apply (Art. 14.8)

For how to complete the form itself, see WH-347, explained and which WH-347 version to use.

Payroll is not the only report

DC Water Works is a local hiring program that runs next to the wage rules. Under the template, the contractor and each first and second tier construction and professional services subcontractor with a contract over $300,000 must take part, and the program includes weekly certified payroll reports and monthly collection of employment statistics (Art. 16.1). Those contractors also submit a project personnel roster listing each employee by city, state of residence and zip code, through an automated online reporting system (Art. 16.2, which covers both construction and professional services). A construction subcontractor over $300,000 gives an Employment Plan with the Subcontract Approval Request (Art. 16.3). Art. 14.2 sets no dollar floor, Works Program section 10.2 sets $2,000, and Art. 16.1 lists weekly payroll within the over $300,000 program. The documents do not say which controls, so read the thresholds in Section 00 76 00 of your contract and ask the compliance officer.

The Works Program describes it slightly differently: an Employment Plan within 30 days of contract start from contractors of all tiers with $300,000 or more on a single project, and a bi-monthly employment report (sections 3.0, 4.0 and 10.3). The template says monthly statistics; the program says bi-monthly. Your contract's wording controls, and the project's compliance officer can confirm the cadence.

The program also sets a goal of 60 percent local residents in the workforce, and requires apprentices at no less than one apprentice to three journeymen from contractors in apprenticeable trades on contracts over $500,000 (sections 1.0 and 7.0). Exemptions include financial and legal service contracts, goods-only contracts, emergency purchases, and work outside the DC Water user jurisdiction (section 12.0). Those are exemptions from the Works Program, and section 12.0(a) says federal labor laws and regulations prevail where the program conflicts with them. A Davis-Bacon payroll duty in your contract is separate. Contractors with collective bargaining agreements or project labor agreements are excused from using DC Water as the first referral source but still submit the bi-monthly report. For the District's separate First Source rules, see Washington, DC certified payroll.

How DC Water checks your payroll

Onsite interviews

The template says a designated DC Water employee or Third Party Compliance Officer performs periodic site visits to question tradesmen on the accuracy of the certified report (Art. 14.6). The 2013 presentation says interviews run semi-annually on most projects and quarterly on others, that answers are confidential, and that the employee's identity is not disclosed to the contractor (site visits section). Visits also check that wage posters and rates are displayed.

Desk audits and review

The presentation lists certified payroll review, site visits, random desk audits and sample testing of pay stubs and employee files, and a semi-annual survey to site superintendents. The Works Program says each project is assigned a compliance officer who enforces contract language and reviews the periodic reports (section 11.1).

Records

The presentation says DC Water keeps its own labor standards files, including certified payrolls, for five years after project completion. For contractors, its checklist says to keep a set of payrolls for three years after the project is completed. Those are different clocks. The General Conditions' records clause is a third one: books and records on costs for three years after final settlement, or the statute of limitations, whichever is longer (General Conditions, Retention of Records). Federal rules require contractors to keep payrolls for 3 years after all the work on the prime contract is completed (29 CFR 5.5(a)(3)(i)).

What happens when a payroll is wrong

The presentation lists the common problems: posters not posted or not conspicuous (called the most common), rates not communicated to workers, wage computation discrepancies, extraordinary deductions, unpaid fringes, kickbacks, misclassification, and workers paid below the prevailing rate.

SeverityPossible response (2013 presentation, remediation)
Minor discrepanciesMemo to file; corrections tracked and noted; more site visits
Serious and willfulFormal letter or citation, General Counsel involvement, complaint sent to the US Department of Labor, wage restitution, withholding of contract payments, potential debarment, more site visits and desk audits
Falsified reportDebarment from future contracts and criminal penalties

The presentation says each remedy "may" apply, so DC Water chooses. The General Conditions separately say a contractor that submits a false claim may face civil penalties, damages, debarment and criminal prosecution (paragraph 15.3, General Conditions). By its wording, this clause is about claims for costs or damages. If a worker was underpaid, correct the payroll and pay the difference before an interview or audit finds it.

Service Contract Act projects

Projects subject to the Service Contract Act submit quarterly reports in place of weekly payrolls. They identify workers assigned to DC Water with the wage classification and hourly rate (section 10.2.1). Construction contracts of $2,000 or more owe weekly payroll (section 10.2).

These documents do not say which funding sources trigger Davis-Bacon on a given job, so your contract's labor provisions answer that. For how other states differ, see certified payroll requirements by state. DC Water's user jurisdiction includes counties in Maryland and Virginia.

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

Do I email my certified payroll to DC Water?
The contract template says payrolls go through an automated online reporting system (Art. 14.2). The Works Program says compliance reports go through an Online Compliance Database (section 10.4). The two documents use different names, so ask your DC Water compliance officer which login to use.
Do subcontractors report separately?
Yes. The template applies the weekly requirement to contractors at any tier and flows it down to every subcontractor working onsite (Art. 14.2 and 14.3).
Who signs the Statement of Compliance?
The person who pays or supervises the payment of the employees under the contract (Art. 14.5).
What happens when a worker says something different from my payroll?
The 2013 presentation says interviews test the accuracy of the certified report and check for misclassification (site visits section). Minor discrepancies can end in a memo to file; serious ones can lead to restitution, withholding and debarment.
Is a Work Classification Group number required?
The template says to include it if applicable to the wage determination (Art. 14.4). Use the one printed in your wage decision.
Does DC Water Works apply to every job?
No. Section 12.0 of the Works Program exempts financial and legal service contracts, goods-only contracts, emergency purchases, work outside the user jurisdiction, and Green Infrastructure agreement work, among others.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Instructions to Bidders template dcwater.com
  2. General Conditions dcwater.com
  3. DC Water Works Program dcwater.com
  4. January 9, 2013 Governance Committee presentation dcwater.com
  5. procurement page dcwater.com
  6. any other format ecfr.gov

Questions about your project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us