Detroit Executive Order 2024-02 (formerly 2021-2): DPP reports, residency proof and workforce contributions
What the City of Detroit's resident-hours order asks of contractors on City-funded construction, read on November 6, 2026 from Executive Order 2024-02, the Incentives Compliance Team page of the Civil Rights, Inclusion and Opportunity Department (CRIO), its FAQ and its fact sheet.
Last reviewed against the sources it cites
The short answer
Executive Order 2024-02, which replaced 2021-02 in July 2024, requires at least 51 percent of hours on covered City-funded construction to be worked by bona fide Detroit residents. A Designated Point Person reports to the City's civil rights department, and a contractor that falls short owes a workforce contribution. After written notice and a challenge window, unresolved non-compliance can mean withheld payments, refused bids or debarment for up to one year.
- The City's executive order list includes Order No. 2024-02, the order is dated July 9, 2024 and supersedes Executive Order 2021-02 of April 14, 2021, and the Incentives Compliance Team page monitors projects under 2024-2.
- A covered project is a City construction contract above $3,000,000, or construction the City or its affiliates support with more than $3,000,000 of the assistance the order lists, and at least 51 percent of its hours must be worked by bona fide Detroit residents, unless a grant's terms prohibit these requirements (EO 2024-02, paragraphs 1, 4 and 12).
- The City's Incentives Compliance Team page lists a Project Information Form for before reporting starts, a monthly contribution form and a monthly Employee Residency Verification Form.
- Paragraph 7 of EO 2024-02 charges 5, 10 and 15 percent of the average hourly wage across the first 10 percent, second 10 percent and remaining 31 percent of the shortage percentage.
- After a written notice of non-compliance a contractor has 15 days to challenge it in writing, and if it takes no corrective action within 30 days after the notice and any challenge decision the City may withhold all future payments, refuse bids or debar it for up to one year (EO 2024-02, paragraph 10).
- The City's FAQ says a workforce contribution invoice is due 30 days from its creation and the due date cannot be changed.
Which order applies: 2024-02, not 2021-2
The City's executive order list includes Order No. 2024-02, and the Incentives Compliance Team page says it monitors projects under Executive Order 2024-2. The order is dated July 9, 2024 and supersedes Executive Order 2021-02 of April 14, 2021. CRIO's FAQ (undated, filed under September 2021) and fact sheet (filed under February 2024) still say 2021-2. The order leaves earlier orders in place for a project whose construction had started by July 9, 2024, and paragraph 11 requires covered contracts to carry its terms, so check which order your contract cites.
Michigan's state rules are in our Michigan certified payroll guide, other states in the state by state table.
Which projects it covers
| Project | Test in the order |
|---|---|
| City construction contract | Contract value above $3,000,000 (paragraph 1(a)). |
| Construction the City supports | More than $3,000,000 of City or affiliate help: land sold below appraised value, direct money, outside government money needing City approval, or tax increment financing (paragraph 1(b)). |
| Proposal N demolition or rehab | Residential work under a City contract above $50,000 (paragraph 2). |
| Excluded | A contract, or part of one, funded by a grant whose terms prohibit these requirements (paragraph 12). |
What the order requires
- The target. At least 51 percent of project hours must be worked by bona fide Detroit residents, who can show Detroit residency at least 30 days before starting (paragraphs 3 and 4).
- Who carries it. Every contractor and subcontractor must comply, but the party contracting directly with the City is solely responsible for requiring each subcontractor to meet the target or contribute (paragraph 5). The Incentives Compliance Team page says the charge goes to the general contractor; read your subcontract for how it passes down.
- The reports. CRIO decides at contract signing whether the target is measured monthly or quarterly, and the contractor reports total hours, Detroit resident hours and any shortfall each period (paragraph 6). Failing the order is a material breach that may bring immediate termination (paragraph 5).
The monthly package: who sends what, and where
The contractor appoints a Designated Point Person (DPP). The FAQ says the DPP completes the project information form, submits monthly reports, receives invoices and is CRIO's main contact, with the submission due on the 15th for the previous month. The order lets CRIO choose a quarterly period, so confirm yours with CRIO through its department page.
| Item | What it is |
|---|---|
| Project Information Form | A form the DPP completes before reporting begins, per the Incentives Compliance Team page. |
| EO 2024-02 Contribution Form | An Excel workbook (September 2026 file) titled Monthly Contractor Summary Report. Each contractor's row holds workers, hours, average hourly wage and workers and hours in column groups for STEP only, Detroit only, Detroit and STEP, and Fast Track; the workbook calculates the shortfall and contribution. |
| Employee Residency Verification Form | An Excel workbook (September 2026 file) titled Payroll and STEP Summary Report. It lists every Detroit resident and STEP union member with address, trade, union, primary and secondary proof, hours and pay. |
| Certified payrolls | The FAQ asks for each subcontractor's. The City names no format, so ask your analyst whether a WH-347 works (which WH-347 to use). |
| DPP Upload | The upload form where the DPP submits (FAQ). The Incentives Compliance Team page button opens a Smartsheet form whose fields could not be read. |
| Prop N form | A separate monthly form for Prop N demolition and abatement contractors. |
Send the proofs and the STEP summary every month even if your crew did not change, because CRIO reviews month by month (FAQ). The fact sheet says CRIO checks payrolls and proofs against the 51 percent target and posts compliance on a public dashboard.
Proof of residency
Show two proofs, one from each list, each with a Detroit address (paragraph 3). The City's documents differ.
| List | Order | FAQ | Current workbook menu |
|---|---|---|---|
| Primary | Michigan ID card, Michigan driver's license, Detroit municipal ID | Adds Mexico Consular ID; ID must be valid and current | The same four |
| Secondary | Voter card, vehicle registration, latest tax return, lease, latest utility or water bill, landlord utility affidavit | Adds property tax bill, cable bill and cell phone bill | Adds student loan bill and cell or cable bill; no property tax bill |
The order accepts other proof "under unique circumstances", so ask your analyst about a document on some lists and not others. The FAQ says a worker with no secondary proof can use a sworn affidavit from a landlord or roommate that the worker pays utilities in the home.
How the contribution is calculated
A contractor that misses the target contributes to CRIO's Workforce Training Fund (paragraph 7). The first 10 percent of the shortage percentage is charged at 5 percent of the average hourly wage the contractor paid on the project in the preceding period, the next 10 percent at 10 percent, and the remaining 31 percent at 15 percent. For demolition or rehab, paragraph 9 sets $200 per employee.
The City's own examples count the tier hours differently. Take 1,000 total hours, 250 worked by Detroit residents, a 26 percent shortage.
| Source | Hours at 5% | Hours at 10% | Hours at 15% | Charge as multiple of average hourly wage |
|---|---|---|---|---|
| EO 2021-02 footnote 1: shares of total hours (1,000) | 100 | 100 | 60 | 24 |
| EO 2024-02 footnote 1: shares of shortage hours (260) | 26 | 26 | 15.6 | 6.24 |
| Workbook formulas (September 2026 file), same figures: shares of non-qualified hours (750) | 75 | 75 | 45 | 18 |
The Auditor General's April 2023 audit of CRIO, covering the contribution formula in the earlier Executive Order 2016-1, read it as total hours. It found CRIO's template used total hours minus qualified hours and estimated a potential fee loss of $819,125 for December 2016 to June 2019. Footnote 2 of 2024-02 says paragraph 7 was reworded to cure ambiguity and is meant to reflect, not change, CRIO's earlier formula, yet the workbook's formulas and the order's example give different hours.
The City's current workbook, and the practice the Auditor General found CRIO following, both use non-qualified hours, and footnote 1's example gives a smaller figure. Ask your assigned inclusion analyst for the calculation and compare it with the order your contract cites before you pay or dispute it.
Union hours (STEP)
On construction, labor from a union meeting its goals under the Detroit Skilled Trades Employment Program (STEP) is deemed to meet the target (paragraph 8). The City's STEP brochure lists electricians (IBEW Local 58), laborers (Local 1191), plumbers (Local 98) and carpenters (Locals 687, 1234 and 1045), but CRIO decides periodically whether a union meets its goals, tested at the date the contractor signs. The FAQ says Local 1191 is part of the program but that, per its agreement, its workers are treated differently (the FAQ text is cut off there), so ask your analyst how Local 1191 hours count. Demolition and rehab instead need more than 51 percent Detroit hours plus paid DOL-approved apprenticeship training (paragraph 9).
If an invoice is late, wrong or unpaid
- Treat the due date as fixed. The FAQ says an invoice is due 30 days from creation and cannot get a new date. The fact sheet says failing to submit documentation or pay a contribution makes a contractor non-compliant.
- Correct payroll errors through the DPP Upload. The FAQ says to tell your assigned inclusion analyst and re-upload the documents.
- Use the challenge window. CRIO must give written notice of non-compliance. You then have 15 days to send a written challenge with your reasons. A panel of the City's Corporation Counsel, the head of Administrative Hearings and the head of Buildings, Safety, Engineering, and Environment, or their designees, decides it in writing (paragraph 10).
- Know the consequences. If you take no corrective action within 30 days after the notice and any challenge decision, the City may withhold all future payments under the contract until you comply, refuse your bids and aid applications until you cure, or debar you for up to one year. The City may also re-bid the work or use its own workforce (paragraph 10). The invoice's 30 days comes from the FAQ and this one from the order; the sources do not say how they fit.
Help with the payroll
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
What is the DPP Upload Form?
Is Detroit's order 2021-2 or 2024-02?
Can I get more time to pay a workforce contribution invoice?
Do I resubmit residency proof if my workers have not changed?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Executive Order 2024-02 detroitmi.gov
- Incentives Compliance Team page detroitmi.gov
- FAQ training.detroitmi.gov
- fact sheet devtraining.detroitmi.gov
- executive order list detroitmi.gov
- Executive Order 2021-02 detroitmi.gov
- department page detroitmi.gov
- Project Information Form detroitmi.gov
- EO 2024-02 Contribution Form detroitmi.gov
- workbook detroitmi.gov
- Employee Residency Verification Form detroitmi.gov
- workbook detroitmi.gov
- Prop N form detroitmi.gov
- dashboard detroitmi.maps.arcgis.com
- April 2023 audit detroitmi.gov
- STEP brochure detroitmi.gov