California's debarred contractors list: where it is and how to check a sub
The list is the DLSE Debarments page, required by Labor Code 1777.1(f) and described in the Labor Commissioner's Public Works Manual (October 2023 edition).
Last reviewed against the sources it cites
The short answer
The Labor Commissioner posts California's debarred public works contractors on the DLSE Debarments page, with the period of debarment for each entry and a CSLB license number on most. Check the name, license number where shown, then read the period and any note about a court stay. Also check the CSLB license, the federal list, and DIR registration.
- The DLSE Debarments page lists contractors barred from bidding on, accepting, or performing any public works contract, as a contractor or a subcontractor.
- Labor Code 1777.1(f) requires each entry to carry the contractor's name, CSLB license number, and effective period of debarment, and requires the Labor Commissioner to notify awarding bodies of the list at least annually.
- The DLSE page tells you to read the "Period of debarment" for each entry, and its own entries include periods that have ended and one order marked as stayed by a superior court.
- Under Labor Code 1777.1(h), "any interest" in a bidding or working entity includes receiving payments from it or contracting with it during the debarment, so a debarred person's other company is not a clean substitute.
- Under 8 CCR 16801(K), the Labor Commissioner keeps a record of each debarment for 5 years and releases it to the public on written request.
Where the list is
California's list of debarred public works contractors is on the Labor Commissioner's DLSE Debarments page. It is also linked from the DLSE Databases page, where it appears as "DLSE Debarments (Public Works Contractors)". The DLSE page has no search form. It is one posted page, with the newest orders first as of November 13, 2026, that you search with your browser's find function.
The page describes itself as a list of contractors barred from bidding on, accepting, or performing any public works contract, as a contractor or as a subcontractor. This page does not repeat how a contractor lands on the list. For the four triggers and the length of each, read prevailing wage debarment in California.
How to read an entry
Labor Code 1777.1(f) requires the list to carry the contractor's name, the CSLB license number, and the effective period of debarment. Most entries on the DLSE page show a CSLB license number, but some older entries show none, only names and addresses. Some entries list several periods, and one entry (Fast Demolition, Inc.) lists stacked periods that run to 3/31/47, so check each period against today's date.
| What you see | What to do with it |
|---|---|
| Company name plus individuals | Entries often name the officers too. For purposes of section 1777.1, subdivision (g) defines the covered "contractor or subcontractor" as the firm and its responsible managing officer, plus any supervisors, managers, and officers the Labor Commissioner found personally and substantially responsible for the willful violation. Search each person's name, not only the company. |
| CSLB license number | For entries that show a number, match on it, because names change and numbers do not. Some entries list two license numbers. For entries with no number, match on the company name, each individual's name, and the address. |
| Period of debarment | The DLSE page says to refer to this period for the status. Section 1777.1 makes a party ineligible for the stated period, so compare that period with today's date. |
| A note that the order is stayed | One entry on the page says the debarment order is stayed by order of a superior court. |
| Decision link | Entries link to the decision. |
Who else the bar reaches
Subdivisions (a), (b), and (c) of 1777.1 each make "a firm, corporation, partnership, or association in which the contractor or subcontractor has any interest" ineligible too. Subdivision (h) defines "any interest" broadly: an interest as owner, partner, officer, manager, employee, agent, consultant, or representative. It also includes receiving payments from the bidding or working entity, or contracting with it for services, vehicles, tools, equipment, or supplies, from the start of the debarment proceedings until the end of the period. A clean company name on the list is therefore not proof that the people behind it are clear. Subdivision (d), the apprenticeship debarment under Labor Code 1777.5, is worded differently: it reaches the contractor or subcontractor and its responsible officers, not firms with "any interest", so the any-interest rule does not apply to every entry. The debarment guide covers it.
What it means for a prime that uses a debarred sub
Under Labor Code 1777.1(a)(2), (b)(2), and (c)(2), a debarred party is ineligible to perform work as a subcontractor on a public works project. Ask the awarding body how it wants the work handled, in writing, and talk to an attorney about your contract.
The prime has a separate, better known exposure: unpaid prevailing wages on a sub's crew. That is governed by Labor Code 1775(b), covered in general contractor liability for a sub's violations.
Other lists to check
The DLSE page itself says, as part of due diligence, to also check the contractor's status with the Contractors State License Board and the federal debarment list. Caltrans' 2023 Labor Compliance Manual, section 21-6-3, points its staff to the same three places: the DIR debarment page, the CSLB site, and the federal excluded parties listing. For the federal side, see Davis-Bacon debarment.
| List | What it adds |
|---|---|
| DLSE Debarments page | Labor Commissioner orders under Labor Code 1777.1, statewide. |
| Local debarments in DIR's project registration database | Under Labor Code 1771.1(o), awarding authorities submit their own local debarments and suspensions each year. The list gives the specific jurisdiction where each applies. DIR says it does not verify those entries. |
| Labor Code 1741(c) public list | Under Labor Code 1741(c), a different list: contractors found to have committed a willful violation of section 1775, or subject to a final assessment order no longer open to judicial review. It shows the assessment date, wages and penalties assessed, and the amount collected, and a name stays for three years from the assessment or until it is satisfied, whichever is later. This is not a debarment list. |
| DIR contractor registration | Registration under Labor Code 1725.5(a)(2)(D) requires that the contractor is not currently debarred under 1777.1 or under any other federal or state debarment law. Look the sub up through "Find Public Works Contractors" on DIR's Public Works page. |
The Public Works Manual's own list of resources points to the DLSE Databases page for the 1741(c) judgments. That page has a "Judgment Search" link, but we could not confirm what it contains. Our guides to DIR registration and registration renewal cover the registration side, and the stop order guide covers what happens to a sub working unregistered.
A due diligence routine before you hire a sub
- Get the sub's legal name, every owner and officer, and the CSLB license number before you sign.
- Search the DLSE Debarments page for the company, each principal, and any company name that has appeared with them. Match on license number.
- Read the period and any stay note on every hit. Open the decision.
- Check the CSLB license and the federal list, as the DLSE page directs.
- Check DIR registration, and the local debarment list in the project registration database if the job is for a local agency.
- Save a dated copy of each result in the job file. A list changes, and the date you checked is the fact that matters later.
If you are the sub
If your company or one of your owners appears on the list, the period on your entry controls, not your own reading of the decision. If the entry says an order is stayed, ask the awarding body in writing how it treats your status, and talk to an attorney. If an old entry is yours, read its period of debarment, which is what the DLSE page directs you to use for status.
How to get the record itself
The Labor Commissioner is required by 8 CCR 16801(K) to notify awarding bodies when a debarment order is served and to keep a record of each debarment for 5 years from its date. The record lists the contractor's name and last known address, the date, and the term. It is available to the public on written request that encloses a self-addressed, stamped envelope.
Under Labor Code 1777.1(c), debarment follows a failure to produce certified payroll within 30 days after the Labor Commissioner's written notice, unless the failure was outside your control. See the Labor Code 1776 records request guide. WellStanding prepares the WH-347 and the eCPR from the payroll export you already run, and a person reviews every filing. You review the finished filing and sign the certification in one step, and nothing is filed until you have signed; we never sign for you.
Questions
Where is the California debarred contractors list?
Is there a search tool for the list?
If a name is on the list, is the contractor barred today?
Does the list cover local agency debarments?
Can a debarred owner work through a new company?
What if I hired a sub who turns out to be debarred?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- DLSE Debarments page dir.ca.gov
- Labor Code 1777.1 dir.ca.gov
- Public Works Manual dir.ca.gov
- 8 CCR 16801 dir.ca.gov
- DLSE Databases page dir.ca.gov
- 2023 Labor Compliance Manual dot.ca.gov
- DIR's Public Works page dir.ca.gov