DIR stop order for an unregistered contractor: what it does and what it costs
This page reads Labor Code 1771.1, the appeal procedure it borrows from Labor Code 238.1, and DIR's contractor registration page.
Last reviewed against the sources it cites
The short answer
A stop order is a Labor Commissioner order, effective the moment it is served, that bars an unregistered contractor from all California public works until it registers. Separately, Labor Code 1771.1 sets $100 a day, up to $8,000, against the unregistered contractor and up to $10,000 against a higher tier contractor that hired it. Subdivision (n) exempts small projects from the whole section, penalties included. Register, pay any penalty registration fee, and appeal on time.
- A served stop order is effective immediately and prohibits use of the unregistered contractor on all public works, except projects at or below the small project thresholds in subdivision (n), until it is registered, and does not apply to registered contractors on the job (Labor Code 1771.1(j)).
- The unregistered contractor forfeits $100 for each day of work performed in violation, up to $8,000, in addition to any penalty registration fee (Labor Code 1771.1(g)).
- A higher tier contractor that subcontracted to an unregistered sub faces $100 a day, up to $10,000, and the sub cannot be made to indemnify it (Labor Code 1771.1(h)(1) and (h)(4)).
- Employees idled by a stop order must be paid their regular hourly prevailing wage rate for the hours they would have worked, not to exceed 10 days (Labor Code 1771.1(j)(4)).
- Appeal runs under Labor Code 238.1(a): a written hearing request within 20 days after service, a hearing within five days of filing, and a writ of mandate within 45 days after the notice of findings is mailed (Labor Code 238.1).
- For a first violation in 12 months, registering requires a $2,000 additional nonrefundable penalty registration fee (Labor Code 1725.5(a)(2)(E)).
What a stop order is
When a contractor works on a public works contract without being registered, Labor Code 1771.1(j)(1) says the Labor Commissioner "shall issue and serve" a stop order. The order prohibits the use of the unregistered contractor or subcontractor on all public works until it is registered. It does not apply to work by registered contractors or subcontractors on the job.
Two points matter on day one:
- It reaches every public works job. The text says "all public works," not the project where you were found. DIR's registration FAQ adds that an unregistered contractor can be removed from any public works project it is working on.
- It is not the penalty. The stop order halts work. The dollar penalties come through a separate assessment, covered below.
Section 1771.1(n) says the section does not apply to work on a public works project of $25,000 or less for construction, alteration, demolition, installation, or repair, or $15,000 or less for maintenance. Our registration guide covers who must register and how the dollar lines work.
How it is served and when it starts
Under section 1771.1(j)(2), the Labor Commissioner can serve a stop order two ways:
- Hand delivery to the contractor or subcontractor personally.
- Signed copies left at the site with the person apparently in charge, followed by first-class mail to the address on file with the Secretary of State or the Contractors State License Board. If neither has an address for you, the mail goes to the site of the public work.
The order is effective immediately upon service (subdivision (j)(3)).
Penalties under Labor Code 1771.1
| Who | Penalty | Source |
|---|---|---|
| The unregistered contractor or subcontractor | $100 for each day of work performed in violation, up to $8,000 total, plus any penalty registration fee | Subdivision (g) |
| A higher tier contractor or subcontractor that subcontracted to an unregistered lower tier sub | $100 for each day the unregistered sub works, up to $10,000 total | Subdivision (h)(1) |
| The contractor or subcontractor, or its owner, director, officer, or managing agent, who fails to observe a served stop order | Misdemeanor: up to 60 days in county jail, a fine up to $10,000, or both | Subdivision (k) |
All three rows are in Labor Code 1771.1. The penalty rows are assessed on days worked, not days since the stop order. The subdivision (n) thresholds described above exempt a small project from section 1771.1 as a whole, so these penalties do not apply to work on a project at or below them.
If you hired the unregistered sub
Subdivision (h) has four rules a prime or upper tier sub should know:
- The Labor Commissioner uses the standards in section 1775(a)(2)(A) to judge severity and may waive the penalty for a first time violation that was unintentional and did not hinder the Commissioner's ability to monitor and enforce compliance (subdivision (h)(2)).
- You are not liable if the sub's violation is due to revocation of a previously approved registration (subdivision (h)(3)).
- The sub is not liable for the penalty assessed against you, and you may not require a lower tier sub to indemnify you or otherwise be liable for it (subdivision (h)(4)).
- The penalty is "in addition to, or in lieu of" other penalties under the chapter (subdivision (h)(1)).
A sub's failure to register is also grounds under Public Contract Code section 4107 to substitute a registered sub, with the awarding authority's consent (subdivision (d)). Check registration before each sub's first day. The debarment list guide covers the related check for debarred contractors.
How the penalty is assessed
Under subdivision (i), the Labor Commissioner issues a civil wage and penalty assessment under section 1741 after determining penalties under subdivisions (g) and (h)(1). Review of that assessment is requested under section 1742, and the Director's regulations on review of assessments apply. The steps, deadlines, and what to file are in our guide to the Civil Wage and Penalty Assessment, and what happens at the hearing is in CWPA hearing and writ of mandate.
The stop order has its own appeal track, described next.
Appealing the stop order
Subdivision (j)(3) says the stop order can be appealed by the party contracting with you, by you, or both, and that the appeal, hearing, and any further review follow the procedures and time limits in Labor Code 238.1(a). That subdivision sets these steps:
- File a written request for a hearing with the Labor Commissioner within 20 days after service.
- The hearing is held within five days from the date of filing. The Labor Commissioner notifies you of the time and place by mail.
- At the end of the hearing the stop order is affirmed or dismissed. Within 24 hours the Labor Commissioner serves written findings by registered or certified mail.
- A writ of mandate may be taken to the superior court. It must be taken within 45 days after the mailing of the notice of findings.
The stop order is effective on service, and the statute text does not say that a hearing request stays it. Section 238.1(a) also lets the Labor Commissioner file an action in superior court for injunctive and other appropriate relief to enforce the stop order, with costs and attorney's fees recoverable if any relief is obtained.
Section 238.1 is written for a different violation, so some of its wording speaks of "the employer" and "Section 238." Section 1771.1(j)(3) is what brings its procedures and time limits into a registration stop order. Because the deadlines are short, talk to an attorney about representation before the 20 days run. WellStanding does not appear at hearings or give legal advice.
What you owe your crew
Under subdivision (j)(4), an employee of an unregistered contractor who is affected by the work stoppage must be paid at the regular hourly prevailing wage rate by that employer for any hours the employee would have worked but for the stoppage, not to exceed 10 days. The statute puts the cost on that employer. Our guide to reading a prevailing wage determination shows where to find the rate.
How to get back to work
The stop order runs "until the unregistered contractor or unregistered subcontractor is registered" (section 1771.1(j)(1)). So registration is the way out. What registering costs depends on your history:
| Your situation | What DIR and the statute say |
|---|---|
| First violation of the registration requirement in 12 months | The period of disqualification is waived if you pay an additional nonrefundable penalty registration fee of $2,000 (section 1725.5(a)(2)(E)). DIR says this is in addition to the $400 registration fee (DIR FAQ). |
| A second violation within 12 months | The $2,000 waiver in section 1725.5(a)(2)(E) applies only to a contractor that has not previously been found in violation within the preceding 12 months. DIR says contractors found in violation of the registration requirement twice in 12 months can be disqualified from public works for up to 12 months at a time (DIR registration page). |
| Registration lapsed and you missed the renewal | DIR lists a $400 penalty for a late renewal between July 1 and September 30 when the lapse was accidental, and $2,000 when it was not accidental. For renewal after September 30 or reactivation, DIR lists $2,000 if you bid on, were awarded, or worked on a public works project while unregistered in the past 12 months (DIR registration page). If the failure to pay was inadvertent, you may renew retroactively by paying a penalty renewal fee equal to the renewal fee within 90 days of the due date (section 1725.5(c)). |
DIR says credit card payments can be processed within 24 hours, while other forms of payment may delay registration up to eight weeks (DIR registration page). With a stop order in force, pay by card. The portal steps and the certification questions are in our guides to renewing DIR registration and DIR registration.
The registration penalty fee is separate from the civil penalty. Section 1771.1(g) adds the $100 a day penalty "in addition to" any penalty registration fee.
Where certified payroll fits
Our certified payroll penalties guide covers the separate penalties for late or missing payroll records. WellStanding prepares the WH-347 and the eCPR from the payroll export you already run, and a person reviews every filing. You review the finished filing and sign the certification in one step, and nothing is filed until you have signed; we never sign for you.
Questions
Does a DIR stop order apply to every job I have, or only the one where I was caught?
How much is the penalty for working on public works without registration?
How long do I have to appeal a stop order?
Do I still have to pay my workers while the stop order is in effect?
I hired a sub that turned out to be unregistered. Can I pass the penalty to it?
Is it a crime to keep working after a stop order is served?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Labor Code 1771.1 leginfo.legislature.ca.gov
- Labor Code 238.1 leginfo.legislature.ca.gov
- contractor registration page dir.ca.gov
- Labor Code 1725.5(a)(2)(E) leginfo.legislature.ca.gov
- registration FAQ dir.ca.gov