HUD FHA multifamily Davis-Bacon payroll: which loans, what you owe, what ECSP means

This page covers FHA-insured multifamily construction. It reads HUD's Multifamily Accelerated Processing (MAP) Guide (revision of March 19, 2021), 24 CFR 200.33, HUD's Handbook 1344.1 REV-3 (January 2023) and Notice H 2015-09.

Last reviewed against the sources it cites

The short answer

Davis-Bacon applies to FHA-insured new construction and substantial rehabilitation, such as Section 221(d)(4), 220 and 231 loans. 223(f) refinances (24 CFR 200.33(a)(1)) carry no Davis-Bacon, and a 223(a)(7) refinance cannot include work that would trigger it. Site work finished before a pre-application or firm commitment application is submitted to HUD is also outside coverage. Ask your HUD labor standards specialist, in writing, which channel and cadence apply.

  • HUD's MAP Guide, section 3.2.6 (March 19, 2021) requires the general contractor and every subcontractor on FHA-insured new construction or substantial rehabilitation to comply with Davis-Bacon and Copeland weekly payroll rules.
  • The same section says Davis-Bacon does not apply to off-site improvements or to site demolition and improvements completed before the federal nexus, which it defines as submitting a pre-application or firm commitment application to HUD.
  • 24 CFR 200.33(a)(1) says the labor standards provisions do not apply to projects insured under section 207 or 232 pursuant to section 223(f).
  • 24 CFR 200.33(d) makes an advance on a loan subject to section 212 ineligible for insurance unless a certificate that the laborers and mechanics were paid the required wages is filed with the application for the advance.
  • Notice H 2015-09 (October 5, 2015) says in-house labor compliance is performed for all multifamily insured projects and names the system the "Davis-Bacon ECSP"; HUD's January 2023 handbook, paragraph 4-3(A) calls the system the Electronic Payroll System (EPS).
  • MAP Guide section 19.2.2.1 says the Regional Center Director will not give administrative clearance to close or endorse the note until DBLS clearance is received and its conditions are met.

Which FHA multifamily loans carry Davis-Bacon?

Davis-Bacon follows the type of work, not the lender. The MAP Guide's section 3.2.6 says the general contractor and all subcontractors on FHA-insured new construction or substantial rehabilitation must comply with the Davis-Bacon Act and the Copeland Act. Davis-Bacon sets the prevailing wage. Copeland brings the weekly certified payroll.

Here is how the rule falls across the programs listed in MAP Guide section 1.3.2.

FHA loanDavis-Bacon?Source
221(d)(4): new construction or substantial rehabilitation of apartmentsYesMAP Guide 3.2.6 for the rule, 1.3.2 for the program
220: new construction or substantial rehabilitation of mixed-use projects in urban renewal areasYesMAP Guide 3.2.6 for the rule, 1.3.2 for the program
231: new construction or substantial rehabilitation of housing for the elderlyYesMAP Guide 3.2.6 for the rule, 1.3.2 for the program
223(f): refinance or purchase of an existing projectNoMAP Guide 3.7.9, Handbook paragraph 2-5
223(a)(7): refinance of an FHA-insured mortgageNo, unless the repairs are extensive enough that Davis-Bacon applies, in which case the project is not eligible for this refinanceMAP Guide 3.8.7
241(a) supplemental loan on a first mortgage insured under 221(d)(4), 220 or 231, or on a HUD-held mortgage originally insured under a covered programYesMAP Guide 19.6 (NHA 241(b)(5)), 24 CFR 200.33(a)(2)
241(a) supplemental loan on a 223(f) or 223(a)(7) first mortgageNoMAP Guide 3.2.6
241(a) supplemental loan on a project with a Secretary-held mortgage that never had a Davis-Bacon FHA loanNoMAP Guide 3.2.6

24 CFR 200.33(a)(2) says a section 241 supplemental loan follows the rule for the section under which the original mortgage was insured. Section 232 healthcare loans are not in the MAP Guide, which says the Office of Healthcare Programs administers them. The regulation excludes 232 loans made under 223(f). Mortgagee Letter 2015-25 treats healthcare construction loans under sections 232 and 242 and Title XI as covered by its payroll system, so confirm a healthcare loan with HUD.

What work is covered and what is not?

Coverage has a start line. Section 3.2.6 says Davis-Bacon rates do not apply to off-site improvements, or to site demolition or improvements completed before the federal nexus. It defines the nexus as the submission of a pre-application or a firm commitment application to HUD. On industrialized housing, MAP Guide section 5.7.4 limits Davis-Bacon rates to the onsite construction work.

Ask the lender and the HUD labor standards specialist, in writing, which work falls after the application date. If an early start of construction is approved, section 19.2.2.3 says HUD labor staff work with the regional center so wage rates are selected before work starts.

If your state also has a prevailing wage law

HUD's handbook says that on projects with mixed funding the stricter rule usually applies, and that if state rates are higher the state rates apply, and if the federal rates are higher the federal rates apply. It also says HUD labor staff do not enforce state rates and would refer a state-rate failure to the state agency (Handbook paragraph 5-4). See the state-by-state table for your state's law.

What do the general contractor and subcontractors owe?

  1. Get the wage decision into the contract. The lender obtains the current wage rates from HUD and must make sure the design team and general contractor have them (MAP Guide section 5.12.1). The wage decision and form HUD-92554M must be part of the subcontracts for all tiers (section 12.2.1). The labor standards clauses in the contract are explained on the HUD-4010 page.
  2. Pay at least the wage decision, weekly. Handbook paragraph 4-1 says all contractors and lower-tier subcontractors pay prevailing wages at least once a week, and that the prime contractor is responsible for making sure every tier complies.
  3. Submit a certified payroll each week. Each employer prepares, certifies and submits weekly payroll reports starting with its first week on site (paragraphs 4-1 and 4-3). The report goes with a signed Statement of Compliance. The sources conflict on who receives it and how often. Handbook paragraph 4-3 says weekly reports go to the sponsor, applicant or owner. MAP Guide section 12.12.1 says contractor payrolls go directly to HUD labor staff at least once a month. Ask the HUD labor standards specialist, in writing, who receives payrolls and how often. Our suggestion, which is not a HUD rule: keep submitting weekly until you have the answer. For a weekly payroll in the federal format, see the WH-347 guide.
  4. Certify each advance. The pre-construction conference covers a certification of compliance with Davis-Bacon wage rates with each request for advances (section 12.2.1). 24 CFR 200.33(d) is the matching regulation.
  5. Keep records and allow interviews. Employers keep payroll records and make them available to HUD, and HUD can interview employees on the job site (paragraphs 4-4 and 4-5). The interview form is covered on the HUD-11 page.

Who reviews the payroll, and what can they do?

HUD staff do. Notice H 2015-09 says in-house labor compliance is performed for all multifamily insured projects. The handbook's chapter 5 names HUD Labor Standards Specialists as the staff who administer and enforce labor standards on FHA-insured multifamily projects.

The handbook lists the consequences, so read them before a payroll goes missing:

  • If a payroll is not submitted, the specialist contacts the prime contractor and the HUD office, and further advances or payments on the prime contract may be reduced or suspended after 30 days' written notice (paragraph 5-10(A)).
  • An employer that uses an unacceptable payroll format or Statement of Compliance must resubmit it for each week affected, and every correction payroll must carry a properly executed Statement of Compliance (paragraph 5-10).

The closing hold

Unresolved payroll problems follow the project to the end. MAP Guide section 19.2.2.4 has the regional center director obtain written confirmation from the Office of Davis-Bacon and Labor Standards that all labor relations issues are resolved, or that mitigants are in place, and clearance at least 5 business days before the confirmed final closing date. If issues remain, the clearance can require a deposit to the U.S. Treasury sized to cover wage restitution and liquidated damages, or a Labor Standards Deposit Agreement on form HUD-4732. For a contractor with no identity of interest with the owner, retainage can be released at the next to last advance only if, among other conditions, all Davis-Bacon payroll requirements have been satisfied. A contractor with an identity of interest above a 5% equity interest in the owner generally waits until final endorsement (section 12.15.5, items C and D). Correct underpayments and missing weeks as you go, so no one has to resolve them at closing.

What is the ECSP, and is it the same as the EPS?

Notice H 2015-09 and Mortgagee Letter 2015-25, both issued October 5, 2015, call the system the Davis-Bacon Electronic Certification Submission Program, or ECSP. They apply it to FHA-insured construction loans, section 542 Risk Share construction loans, healthcare construction loans and public housing authority construction loans, and make it mandatory after March 31, 2016 for projects less than 50 percent complete. The notice says it stays in effect until amended, superseded or rescinded. It makes each user's PIN the electronic signature and sends users to the website of the vendor, Elation Systems.

HUD's later documents use different words. The January 2023 handbook, paragraph 4-3(A) says employers on an FHA project are "highly recommended" to use the HUD-authorized Electronic Payroll System (EPS), and requires a WH-347-equivalent if another format is used. Paragraph 5-10(B) refers to "the HUD system in use for Electronic Payroll." The MAP Guide section 12.2.1 lists the contractor's registration with Elation Systems among the pre-construction conference topics.

The documents do not say whether ECSP and EPS are one system, or whether the 2015 mandate or the 2023 "highly recommended" wording governs a new job. The conflict is HUD's. Resolve it by asking your HUD labor standards specialist, in writing, which channel and signature method apply to your project, and keep the reply with your payroll records. The housing authority page covers the same two documents on public housing work. For credentials and who to call when access fails, see the Elation Systems page, which is an independent reading and not vendor support. Signature rules are on the Statement of Compliance page.

Questions

Does a 221(d)(4) project need Davis-Bacon certified payroll?
Yes. The MAP Guide, section 3.2.6 says the general contractor and all subcontractors on FHA-insured new construction or substantial rehabilitation must follow Davis-Bacon and Copeland, which includes weekly certified payroll. Section 221(d)(4) is a new construction and substantial rehabilitation program.
Does Davis-Bacon apply to a 223(f) refinance?
No. The MAP Guide, section 3.7.9 says Davis-Bacon requirements do not apply to Section 207/223(f), and 24 CFR 200.33(a)(1) says the labor standards provisions do not apply to projects insured under section 207 or 232 pursuant to 223(f). If the repairs are extensive enough to trigger Davis-Bacon, the MAP Guide says the project is not eligible for a 223(a)(7) refinance (section 3.8.7).
What happens if my subcontractor does not submit payroll?
The HUD specialist contacts the prime contractor, and further advances or payments on the prime contract may be reduced or suspended after 30 days' written notice (Handbook paragraph 5-10(A)). The prime contractor is responsible for making sure every tier complies (paragraph 4-1(B)).
Is the ECSP still the required system?
HUD's documents do not settle it. The 2015 notice says the ECSP is mandatory after March 31, 2016 for projects less than 50 percent complete and stays in effect until rescinded. The 2023 handbook says employers are highly recommended to use the EPS. Ask your HUD labor standards specialist in writing.

We prepare certified payroll for public works contractors. Tell us about your project.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Multifamily Accelerated Processing (MAP) Guide hud.gov
  2. 24 CFR 200.33 ecfr.gov
  3. Handbook 1344.1 REV-3 hud.gov
  4. Notice H 2015-09 hud.gov
  5. January 2023 handbook, paragraph 4-3(A) hud.gov
  6. Handbook paragraph 2-5 hud.gov
  7. Mortgagee Letter 2015-25 hud.gov

Questions about your project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us