Kansas City, Missouri prevailing wage certified payroll: what the City Water Services contract we read requires
This page is built from two City documents: an executed Water Services contract on the City Clerk site (general conditions dated October 2020, project manual addendum November 2021) and the City's Certified Payroll Report Instructions (form footer dated June 2013). The City's department web pages refused automated reads, so this page does not describe them.
Last reviewed against the sources it cites
The short answer
On the City of Kansas City, Missouri Water Services construction contract we read (general conditions October 2020), the contractor and each subcontractor submit payrolls electronically in the City's format, with a signed payroll certification, and send daily labor force reports every day. Each underpaid worker costs a $100 per day statutory penalty plus $100 per day as liquidated damages, and final payment waits for compliance affidavits.
- The executed Water Services construction contract on the City Clerk site (general conditions October 2020) requires a Daily Labor Force Report to be submitted to the City each day.
- The City's certified payroll instructions (form footer dated June 2013) say payrolls are due within two weeks after the payroll week ends, and a no-work week still needs a payroll.
- Under the general conditions (October 2020), the City charges a $100 statutory penalty per underpaid worker per day, and the same amount again as liquidated damages.
- The same contract gives the contractor 14 calendar days to correct record errors or violations after City notice.
- The City will not make final payment until prevailing wage compliance affidavits from the contractor and every subcontractor are submitted, per the contract.
What the Water Services contract asks you to submit
The general conditions of the Water Services contract we read bind the contractor and every subcontractor to the Missouri prevailing wage law (RSMo 290.210 to 290.340), its rules (8 CSR 30-3.010 to 3.060) and the state Annual Wage Order. The statewide picture is on our Missouri certified payroll page. This page covers what the City adds.
The contract lists four things you owe the City:
- A Daily Labor Force Report, on the City's form, with each worker's name, classification, group, skill and hours. You submit it to the City each day.
- Certified Payroll Report information, submitted electronically in a format the City prescribes: name, address, Social Security number, occupation, hours and actual wages paid.
- A Payroll Certification, also electronic, signed by the employee or agent who pays or supervises the payment of the workers.
- The same from every subcontractor, which the contractor must require.
The bid instructions in the same contract say you must use the City's internet-based Prevailing Wage Reporting System and its protocols, and submit user applications for your personnel, and your subcontractors' personnel, when the City asks. The contract does not name the product. The contract's Prevailing Wage Certified Payroll Report Instructions say they apply to contracts that include Prevailing Wage or Davis Bacon provisions, that the contractor and subcontractors must enter data on a timely basis, and that the City will assist in training their personnel. Ask the City's project manager which system is live for your contract.
When payrolls are due
The City's payroll instructions say all payrolls are submitted within two weeks after the ending date of the payroll week. That is a deadline for submitting, not a pay schedule, so you still need the week's payroll finished on time. The same instructions add rules that differ from a plain weekly federal form:
- Number payrolls from 1 for each contractor or subcontractor's first week of work, continuing without gaps.
- For a week with no work, submit a payroll showing no work.
- Mark a revised payroll with the letter R after its number.
- Check the FINAL box on the last payroll.
- Hours on the payroll must equal or exceed the hours on your Daily Labor Force Reports.
That last point is where small contractors get caught. The daily report and the payroll are two records of the same hours, and the City's instructions tell you they must agree. See our WH-347 guide if you also owe the federal form on federal money.
One conflict to resolve before you sign a payroll
The 2013 instructions say the report must come with a payroll certification "including original signature." The general conditions (October 2020) say the Payroll Certification is submitted electronically in the City's format. Both appear in the same contract package and neither says which controls, so confirm with the City's project manager whether the City wants wet ink on your job.
Rates: the higher rate wins
The instructions to bidders say you pay the rate in the Missouri Annual Wage Order or the Federal Wage Determination in the project manual, and where they conflict the higher rate applies. The general conditions add a timing rule: if you do not start work within 60 days of the contract effective date, you pay under any new Wage Order issued in that window, even if an older one is attached to your documents.
What happens when payroll is wrong or underpaid
| Event | What the contract says |
|---|---|
| Error in your or a subcontractor's records, or a prevailing wage violation | Correct it within 14 calendar days after notice from the City. |
| A worker paid below the prevailing rate | $100 statutory penalty per worker per day or part of a day, withheld from payments due to you. |
| Same underpayment, damages clause | Another $100 per day per worker as liquidated damages. The contract says it approximates the City's added costs, including a special division under the City Manager that monitors prevailing wage compliance. |
| City notice of underpayment | The notice lists the workers and amounts. You have 14 calendar days to respond, extendable on written request. No response makes the notice final. If you respond, the City issues a written final decision within five days of finishing any investigation. |
| Project completion | Affidavits from you and each subcontractor that you complied with the Missouri law must be submitted before final payment. The City will not pay the final amount without them. |
The contract states no specific consequence for a late payroll. Its 14-day clause covers record errors and violations after City notice, and the City's system instructions require contractors to enter data on a timely basis. If a subcontractor is behind, you carry the exposure, because the contract makes the contractor responsible for the subcontractor's records and wages.
Records, interviews and public access
- The prevailing wage section says to keep records open to the City and the Missouri Department of Labor and Industrial Relations, and not to destroy them or remove them from Missouri, for one year after the public work is completed. Section H (Records) of the same general conditions separately says to retain all Records, meaning any document made or received in connection with the contract, for five years after the contract expires or ends, and to give the City access on ten days written notice. The contract gives neither period priority over the other.
- The records are treated as public records. The City can require you to provide them in its format within three working days of a request, at your cost.
- The City and the state may interview workers during working hours at your expense.
- Post the prevailing wage rates where workers can see them at the site.
- Before a subcontractor starts, collect the City's Form 00490 Pre-contract Certification of its prevailing wage and tax compliance history for the two years before the bid. Keep it one year and give it to the City within five days of a written request.
Other reports on bigger contracts
The contract's Workforce Monthly Report Instructions apply only to construction contracts above $300,000 and 800 projected labor hours, and its HRD Form 5 text says the monthly reports are due to the HRD Director by the 15th of each month, through B2GNow, with paper allowed only if online submission is a hardship. That is a separate workforce compliance report, not the payroll. Federal money adds federal rules on top: see our guide to WH-347 versions and the state-by-state table.
Read your own contract's general conditions and supplementary conditions.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Do I send Kansas City payroll to the state or the City?
Can I use the WH-347 for Kansas City?
What if I had no work one week?
How do I fix a payroll already submitted?
Does the $100 penalty apply to late paperwork?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- executed Water Services contract on the City Clerk site clerk.kcmo.gov
- Certified Payroll Report Instructions city.kcmo.org