LA Metro certified payroll requirements for subcontractors

Metro requires certified payroll and supporting documents through its online monitoring system on prevailing wage contracts, and the prime contractor answers for its subs, per Metro's Labor Wage & Retention Programs page, and Metro's manual makes it weekly. That is a separate filing from the DIR eCPR, and on a Metro job you may owe both.

Last reviewed against the sources it cites

The short answer

LA Metro requires certified payroll every week through its online monitoring system, due within 7 days of the payroll period on federal jobs and 10 days on state-funded jobs. Metro's own manual also says to file a DIR eCPR, except on Project Labor Agreement jobs. DIR's certified payroll FAQ also lists a small project exemption, so check your contract.

  • Metro's Labor Wage & Retention Programs page says certified payroll and supporting documents go through Metro's online monitoring system, and the prime contractor is responsible for the compliance of its subcontractors.
  • Metro's 2024 Labor Compliance Manual sets weekly submission, with a schedule that says to upload to LCP Tracker within 7 days of the payroll period on federally funded contracts and 10 days on state-funded ones.
  • The same manual says contractors registered with DIR must also file eCPR, and that contractors under Metro's Project Labor Agreement requirements do not, but DIR's eCPR FAQ makes the project labor agreement exemption subject to the Labor Commissioner's discretion.
  • Metro is not one of the four legacy labor compliance programs (Caltrans, City of Los Angeles, LAUSD, County of Sacramento) that DIR's exemptions page exempts from direct eCPR filing. DIR's certified payroll FAQ also lists a small project exemption of $25,000 for new construction, alteration, installation, demolition or repair and $15,000 for maintenance.
  • Metro's page puts prevailing wage at $1,000 and above on state or local funding and $2,000 and above on federal funding, while Labor Code section 1771 excepts projects of $1,000 or less.

What Metro asks of a sub

Metro's 2024 Labor Compliance Manual, linked from its labor page, sets the weekly rule. The contractor and every tier subcontractor submit a certified copy of the payroll each week through Metro's online monitoring system. The manual's Appendix E schedule sets the clock: within 7 days of the end of the payroll period on federally funded contracts, and within 10 days on state-funded ones.

  • Weekly certified payroll. It carries an electronic signature from the contractor's designated payroll agent, per section 4.2 of the manual.
  • A payroll officer form before work starts. Upload a completed Certificate Appointing Payroll Officer form naming the person who certifies.
  • A Statement of Non-Performance for any week with no work. Appendix E says to file it in place of a payroll. See no work performed weeks.
  • Your prime in the middle. The manual makes the prime responsible for submitting its subs' certified payrolls. Ask whether you upload your own or send them to the prime.

When prevailing wage applies on a Metro job

FundingMetro's stated lineThe law behind it
State and local$1,000 and aboveLabor Code section 1771 applies prevailing wage to public works except projects of $1,000 or less.
Federal$2,000 and aboveDOL says the Davis-Bacon Act covers federally funded or assisted contracts in excess of $2,000.

Metro's table says $1,000 and above, while the statute and Metro's manual say more than $1,000. Where state and federal rules both apply, the manual says to pay the higher of the DIR and U.S. Department of Labor rates.

Which system do you upload to

Metro's labor page and the body of the manual call it Metro's online monitoring system and never name the product. The header of the Appendix E schedule says to upload all compliance documents to LCP Tracker. The appendix is marked for reference, so confirm with Metro or your prime before you set up an account. Metro's labor compliance contact is DEODLaborCompliance@metro.net. See also LCPtracker vs DIR eCPR.

Metro and DIR side by side

ItemMetroDIR eCPR
How oftenWeekly, per the manualAt least monthly, or more often if your contract says so, under Labor Code section 1771.4(a)(3)
Who filesEvery contractor and sub, with the prime responsible for its subsEach contractor and sub for itself, per DIR's certified payroll FAQ
Late penaltyRetention and withholding, covered below$100 per day, capped at $5,000 per project, starting 14 days after the deadline, under section 1771.4(a)(3)

Do you still file the DIR eCPR on a Metro job

Usually yes. DIR's eCPR FAQ says submitting certified payroll to other agencies does not put you in compliance with the state unless you submit eCPRs directly to DIR. Metro's manual says the same in its own words: contractors registered with DIR must also submit certified payroll through the eCPR system.

Metro is not on DIR's exemption list. That list names four legacy labor compliance programs, Caltrans, the City of Los Angeles, LAUSD, and the County of Sacramento, plus projects under qualifying project labor agreements. Metro's legal name is the Los Angeles County Metropolitan Transportation Authority, per its manual, so it is not the City of Los Angeles. For City jobs, see City of Los Angeles and OCPS.

DIR's certified payroll FAQ also lists a small project exemption. It applies to public works projects that do not exceed $25,000 for new construction, alteration, installation, demolition or repair, or $15,000 for maintenance. A small Metro job may fall under it, so check the contract value before you assume you owe the eCPR.

The project labor agreement question

The manual adds that contractors subject to Metro's Project Labor Agreement requirements do not have to submit eCPR but must be registered with DIR. Metro's PLA and Construction Careers Policy page says the agreement applies to certain local and federally funded construction projects with a construction value above $2.5 million. DIR's eCPR FAQ, though, exempts only qualifying agreements, at the Labor Commissioner's discretion. Under section 1771.4(b)(2), the test is a collective bargaining agreement that binds all contractors on the project and includes a way to resolve wage payment disputes. Neither Metro's page nor DIR's says whether Metro's agreements qualify.

Ask your prime in writing whether this contract is under Metro's PLA and whether the Labor Commissioner has exempted it from direct eCPR filing. Until you have a written yes, file. Our guide to who is exempt from certified payroll covers the rest of DIR's list, and how to find a DIR Project ID covers the lookup.

What Metro's pages do not say

  • Metro's labor page does not say whether a DIR eCPR is also due. Section 1.2 of the manual does.
  • No page says which Metro projects the Labor Commissioner has exempted under a project labor agreement.
  • The manual is dated February 20, 2024. Metro's page also links its 2019 and 2013 manuals, so use the one your contract names.

Other forms on Metro's schedule

Appendix E of Metro's 2024 Labor Compliance Manual lists more than payroll. This is not every form on the schedule. Subs should know these:

  • DAS 140, if you use apprenticeable trades. Metro's schedule has it due within ten days of executing the prime contract or subcontract, with proof of transmittal uploaded before work starts. Under 8 CCR 230, the DAS 140 goes to the apprenticeship committee within 10 days of signing and no later than the first day you have workers on the job.
  • DAS 142, if you use apprenticeable trades. Under 8 CCR 230.1, a dispatch request needs at least 72 hours of written notice, not counting Saturdays, Sundays, and holidays. Metro's labor page says non-union contractors send the DAS 142 at least 72 hours before an apprentice should begin work, and that a union contractor sends it too when the union does not provide apprentices. Metro's schedule lists the DAS 142 with a 10-day due date from signing. Follow the stricter reading and meet whichever date comes first.
  • Fringe Benefit Statement. Upload it with your first certified payroll, and update it as the information changes.
  • Monthly Employment Utilization Report. Due within 15 days of month end. Each sub uploads its own.
  • Affidavit of Compliance with California Prevailing Wage Law. Due within 60 days after you finish the work.

For how the two apprenticeship forms work, see DAS 140 and DAS 142.

What a miss costs

Under section 4.4 of Metro's manual, if satisfactory payrolls for the prior month are not in by the tenth, Metro retains 10 percent of the next monthly estimate, never less than $1,000 and never more than $10,000. Section 11.3 lets Metro withhold $500 per day for repeated violations, failure to submit certified payroll among them, after notice and a chance to be heard. Separately, Labor Code section 1776(h) sets $100 per calendar day for each worker if you do not hand over requested payroll records within 10 days of a written notice. From January 1, 2027, SB 909 raises this to $140; see what SB 909 changes.

Keep your DIR registration current

Metro's registration page says contractors must be registered with DIR at bid, at award, and throughout the contract. DIR's page sets the fee at $400, $800, or $1,200 for one, two, or three fiscal years. Our registration guide covers lapse penalties.

Where WellStanding fits

You send the export from your own payroll system. We prepare the DIR eCPR and the WH-347, which Metro's manual names for federally assisted contracts. A person reviews every filing, you read and sign the certification, and we file the eCPR. At setup we confirm where each project's filings must go, including Metro's system. Pricing is $995 one time setup and $249 per month for crews up to 25 workers, or $449 for 26 to 50 workers. First filing free. See who signs certified payroll.

Questions

Does LA Metro require certified payroll from subcontractors?
Yes. Metro's labor page says all contracts and subcontractors must submit the required items, and its manual has every tier subcontractor submit weekly. The prime is responsible for its subs' compliance.
Does LA Metro use LCPtracker?
Metro's labor page calls it an online monitoring system and does not name a product. The submittal schedule in Appendix E of Metro's 2024 manual says to upload compliance documents to LCP Tracker. Confirm with your prime or DEODLaborCompliance@metro.net before you rely on it.
If I upload to Metro, do I also file with DIR?
Usually yes. DIR says submitting to other agencies does not put you in compliance unless you submit eCPRs directly to DIR, and Metro's manual says DIR-registered contractors must file eCPR as well. The main exception is a project covered by a qualifying project labor agreement. DIR's certified payroll FAQ also lists a small project exemption for projects that do not exceed $25,000 (new construction, alteration, installation, demolition or repair) or $15,000 (maintenance). Check your contract.
Is a Metro job under a project labor agreement exempt from DIR?
Metro's manual says PLA contractors do not have to submit eCPR. DIR says qualifying agreements are exempt at the Labor Commissioner's discretion. Get written confirmation that the exemption covers your contract, and file until you have it.
How soon after the week ends is the Metro payroll due?
Metro's Appendix E schedule says within 7 days of the end of the payroll period on federally funded contracts and within 10 days on state-funded ones. DIR's rule is at least monthly, so Metro's clock is the shorter one.
What if my crew did no work on the Metro project this week?
Metro's schedule says to submit a Statement of Non-Performance for a week with no work. DIR has its own handling for a week with no work, covered in our no work performed guide.
Who signs the payroll on a Metro job?
Your designated payroll agent signs electronically, and Metro's manual has you upload the Certificate Appointing Payroll Officer form before work starts. A filing service can prepare the payroll, but the contractor signs the certification.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Metro's Labor Wage & Retention Programs page metro.net
  2. Metro's manual dropbox.com
  3. DIR's eCPR FAQ dir.ca.gov
  4. DIR's exemptions page dir.ca.gov
  5. DIR's certified payroll FAQ dir.ca.gov
  6. Labor Code section 1771 leginfo.legislature.ca.gov
  7. DOL dol.gov
  8. Labor Code section 1771.4(a)(3) leginfo.legislature.ca.gov
  9. Metro's PLA and Construction Careers Policy page metro.net
  10. 8 CCR 230 dir.ca.gov
  11. 8 CCR 230.1 dir.ca.gov
  12. Labor Code section 1776(h) leginfo.legislature.ca.gov
  13. SB 909 leginfo.legislature.ca.gov
  14. Metro's registration page metro.net
  15. DIR's page dir.ca.gov
  16. WH-347 dol.gov

On a Metro job and filing twice? First filing free

Send the payroll export you already run. We turn it into the WH-347 and the DIR eCPR filing, checked by software and verified by a person. Your first weekly filing is free, before you pay us anything. $995 one time setup, then $249 per month flat.

Got it. We reply the same business day. Next: we confirm your payroll system and the project, you send one export, and your first filing comes back for your review before anything is submitted.

First filing free