Certified payroll on FTA-funded transit construction: who collects it

This page rests on 49 U.S.C. 5333(a), the current 29 CFR 5.5, FTA's October 2016 Best Practices Procurement Manual (a copy hosted by the City of Augusta, Georgia) and payroll documents from Colorado DOT and the Chicago Transit Authority, plus contract clauses from the Metropolitan Council. FTA's own web pages could not be read when this page was written, so it does not rely on them.

Last reviewed against the sources it cites

The short answer

On an FTA-funded construction job, Davis-Bacon applies through section 5333(a) of Title 49. Where FTA is not a party to the contract, the regulation sends weekly certified payrolls to the entity that maintains the records, for transmission to FTA. The two agency systems documented here are run by a transit agency and by a state DOT with its subrecipient. Ask which one runs yours.

  • 49 U.S.C. 5333(a) directs the Secretary of Transportation to ensure that laborers and mechanics employed by contractors and subcontractors on construction financed with a grant or loan under chapter 53 are paid the locally prevailing wage, as the Secretary of Labor determines it.
  • Under 29 CFR 5.5(a)(3)(ii)(A), where the federal agency is not a party to the contract, certified payrolls go weekly to the applicant, sponsor, owner or other entity that maintains the records, for transmission to the agency, and the prime contractor is responsible for the submission of all certified payrolls by all subcontractors.
  • Section 3.2.11 of FTA's October 2016 Best Practices Procurement Manual requires the recipient to put the current Department of Labor wage determination in each solicitation and to condition award on acceptance of it.
  • The model employee-protections clause in that manual (Appendix A.10) and the Metropolitan Council's FTA supplemental conditions dated 10/23, which repeat it, tell the contractor to comply with 29 CFR part 5 but do not say where payrolls go.
  • On Colorado DOT's FTA flowchart C-3-0, the subrecipient's project engineer or manager accepts or rejects each weekly payroll in LCPtracker, and CDOT's Civil Rights Business Resource Center does a quality review.
  • A Chicago Transit Board ordinance of September 11, 2019 says CTA uses LCPtracker, provided through its B2Gnow contract, to collect certified payroll information and confirm prevailing wages for applicable work by disadvantaged business enterprises on its construction projects.

Where does certified payroll go on an FTA job?

FTA makes grants. The construction contract is between the grantee and the contractor, which FTA's manual calls a third party contract (section 3.2.11). When the federal agency is not a party to the contract, 29 CFR 5.5(a)(3)(ii)(A) has you submit certified payrolls every week to the "applicant, sponsor, owner, or other entity" that maintains the records, for transmission to the agency. The regulation names that entity only as the one that maintains the records, and FTA's own web pages and Master Agreement could not be read for this page. An older edition of FTA's Best Practices Procurement Manual (a copy hosted by the Florida Department of Transportation, with revisions listed through October 2005) tells grantees to make clear to whom payrolls should be transmitted, and says FTA may ask them to hold payrolls on site instead. Your contract documents or the grantee name the entity that maintains the records. The prime contractor is responsible for the submission of all certified payrolls by all subcontractors.

FTA's manual shows where the records end up. It mentions payrolls in three places, and none tells a contractor to send them to FTA. Its contract closeout list (section 5.6.2) names the contractor's final payroll records and wage rate certifications among the documents the recipient collects, and its sample contract file index (Appendix B) lists certified payrolls. Appendix A.10, in the Contract Work Hours clause for awards not involving construction, says the contractor shall maintain payrolls and make them available for inspection, copying or transcription by authorized representatives of FTA and the Department of Labor. The manual also makes the recipient put the current Department of Labor wage determination in each solicitation and condition award on accepting it.

Why your contract may not say which system

FTA's model clause for employee protections (Appendix A.10 of the 2016 manual) tells the contractor to comply with the Davis-Bacon Act and 29 CFR part 5 and to pay wages at least once a week. The Davis-Bacon language does not mention submitting payrolls. The FTA supplemental conditions that the Metropolitan Council posts for construction, dated 10/23 in the header, copy that language, and the document never uses the word payroll. A contract can say only "comply" and leave the portal to another document.

Look for the FTA clauses or FTA supplemental conditions in your bid documents. Then ask the grantee, or your prime, which system collects payroll and what your project number is.

Silence in the contract does not remove the duty where paragraph (e) applies. Under 29 CFR 5.5(e), the Davis-Bacon clauses are part of every prime contract that the statutes referenced by 29 CFR 5.1 require to include them, by operation of law, whether or not the contract includes them, unless the Administrator grants a variance, tolerance or exemption. That paragraph speaks to prime contracts. Paragraph (a)(6) requires the prime and each subcontractor to put the clauses in every subcontract.

Clause copies also age. The 2016 manual and the Council's 10/23 copy both state liquidated damages of $10 per day for overtime violations. The current 29 CFR 5.5(b)(2) says $33 per day, and older clause copies still print $10. See our CWHSSA page for the overtime rule.

FTA's statute: 5333(a) is not 5333(b)

Two subsections of the same section get mixed up. Only the first sets wages.

ProvisionWho it coversWhat it requiresPayroll
49 U.S.C. 5333(a)Laborers and mechanics employed by contractors and subcontractors on construction financed with a grant or loan under chapter 53Wages not less than those prevailing on similar construction in the locality, as the Secretary of Labor determines. DOT may approve a grant or loan only after being assured the labor standards will be maintainedThe Davis-Bacon payroll rules reach the job through the contract clauses (manual section 3.2.11)
49 U.S.C. 5333(b)Employees affected by the assistanceProtective arrangements the Secretary of Labor finds fair and equitable, such as continued collective bargaining rights and priority of reemploymentNone. It sets no wage rates and does not mention payrolls

What agency documents show

These are the payroll channels this page could document from agency pages. They are examples, not a list of every FTA grantee. Your own contract controls.

Source and dateWhat it says about payroll
Colorado DOT, FTA capital construction flowcharts (2024 page footer)Prime and subs enter payroll in LCPtracker. The subrecipient's project engineer or manager accepts or rejects it. CDOT's civil rights office sets up B2GNow and LCPtracker and reviews quality
Chicago Transit Authority, Board ordinance 019-84 (September 11, 2019)CTA uses LCPtracker, provided through its B2Gnow contract, to collect certified payroll information and confirm prevailing wages for applicable work by disadvantaged business enterprises on its construction projects
Metropolitan Council, FTA supplemental conditions (10/23)Names 49 U.S.C. 5333(a), the Davis-Bacon Act and 29 CFR part 5. Gives no payroll submission instruction
FTA model clause, manual Appendix A.10 (October 2016)Same language. Gives no payroll submission instruction
University copy of an older model clause, University of Arkansas, model clauses file (undated)Payrolls go "to the [insert name of grantee] for transmission to the Federal Transit Administration." Its wording is older: it still says WH-347 can be bought from the Government Printing Office

The CTA ordinance speaks of DBE work, so ask CTA how it treats your tier. CTA's compliance page lists the Illinois Prevailing Wage Act and the Davis-Bacon Act among its regulations and policies. For the Illinois state rules, see our Illinois page. Our requirements by state page covers other states. For a California transit example, see our LA Metro page.

Colorado: one weekly payroll, four hands

On CDOT's FTA flowcharts, the subrecipient that awards the contract is the party that gives CDOT a copy of the award. CDOT's offices set up and review the system.

  1. Set up. The subrecipient sends a copy of the award to CDOT's Division of Transit and Rail, and CDOT's Civil Rights Business Resource Center sets up the project in B2GNow and LCPtracker (flowchart C-2-0).
  2. Enter and certify. The prime confirms the project is set up, enters its payroll and certifies it in LCPtracker, including no-work weeks. Each subcontractor does the same (flowchart C-3A-0).
  3. Prime approval. Subcontractor payrolls go to the prime approver, who approves or rejects each one (C-3A-0).
  4. Subrecipient acceptance. The subrecipient's project engineer or manager reviews the payroll and accepts or rejects it in LCPtracker. CDOT's civil rights office then runs a quality review (flowchart C-3-0).

A missing classification takes another route. The contractor completes an SF 1444, the subrecipient's project engineer sends it to CDOT, and CDOT's civil rights office sends it to the U.S. Department of Labor and loads a presumptive wage in LCPtracker (flowchart C-4-0). Our SF-1444 page covers the form, and our Colorado page covers CDOT's other work.

If your payroll is rejected or a payment is held

  1. Read the reason. If the grantee runs LCPtracker, its help article says to check Administrator Notices under the Notices tab, and to contact the project's administrator if no reason is listed.
  2. Find the person who can act. The same article says the Show Info button beside each project names its labor compliance or prevailing wage administrator, and the contact can differ by project. It also sends disputes over loaded wage rates back to that administrator, because LCPtracker support only sees what is loaded.
  3. Correct and resubmit. Our LCPtracker rejected payroll page covers the fix.
  4. Ask about another method. The regulation lets an agency or prime require an electronic system only if it permits other methods of submission when a contractor cannot use or access the system (29 CFR 5.5(a)(3)(ii)(A)).
  5. If a progress payment is held, ask in writing what is missing. Under 29 CFR 5.5(a)(3)(iv)(B), when a contractor fails to submit required records, the federal agency may, after written notice, cause suspension of further payment, advance or guarantee of funds. The same paragraph says failing to submit required records on request may be grounds for debarment. Check your contract's payment article for how payroll receipt affects progress payments.

A week with no work has its own rules; see our no-work payroll page. The regulation lets payroll go on WH-347 or in any other format with the required information (29 CFR 5.5(a)(3)(ii)(B)). A grantee or prime may require an electronic system, but must permit other methods when a contractor cannot use it.

Other federal programs and highway work

Highway jobs have their own channel; see our pages on FHWA-1273 changes and AASHTOWare Civil Rights and Labor. Airport work funded by FAA has its own page: FAA AIP airport payroll.

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

Do I send certified payroll to FTA?
Not directly, as the regulation is worded. Where the federal agency is not a party to the contract, 29 CFR 5.5(a)(3)(ii)(A) has you submit to the applicant, sponsor, owner or other entity that maintains the records, for transmission to the agency. Ask your prime or the grantee which entity that is.
Is 49 U.S.C. 5333(b) the same as Davis-Bacon?
No. Subsection (a) is the prevailing wage rule for construction financed with a chapter 53 grant or loan. Subsection (b) requires protective arrangements for employees affected by the assistance. It sets no wage rates and does not mention payrolls.
My contract only says to comply with Davis-Bacon. Do I still submit weekly?
Yes. 29 CFR 5.5(e) makes the clauses part of a covered prime contract by operation of law, unless the Administrator grants a variance, tolerance or exemption, and paragraph (a)(6) requires them in every subcontract. Paragraph (a)(3)(ii)(A) sets the weekly submission. Ask the prime or grantee how it collects.
Does Davis-Bacon apply to a small FTA-funded construction contract?
FTA's October 2016 manual says third party contracts for construction, alteration or repair exceeding $2,000 must include Davis-Bacon provisions (section 3.2.11), even when the recipient uses micro-purchase procedures (section 3.4.1). The flow-down in its Appendix A.10 states the $2,000 figure for prime contracts. Subcontract flow-down is in 29 CFR 5.5(a)(6). Read the clause in your contract for the current threshold.
How do I find out which system my transit agency uses?
Check the bid documents for the FTA clauses, then ask the grantee's contract compliance office or your prime. If the system is LCPtracker, the Show Info button beside each project names its administrator.
Where is the FTA Master Agreement language?
FTA's 2016 manual says the Master Agreement, published annually, holds a current but not all-inclusive list of requirements for recipient procurements, Davis-Bacon among them, and that recipients must evaluate which apply to each federally funded procurement (section 3.6.3). Read the current edition on FTA's grant agreements page.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. 49 U.S.C. 5333(a) govinfo.gov
  2. 29 CFR 5.5 ecfr.gov
  3. Best Practices Procurement Manual augustaga.gov
  4. Metropolitan Council's FTA supplemental conditions dated 10/23 metrocouncil.org
  5. FTA flowchart C-3-0 codot.gov
  6. Chicago Transit Board ordinance of September 11, 2019 transitchicago.com
  7. Best Practices Procurement Manual fdot.gov
  8. 29 CFR 5.1 ecfr.gov
  9. FTA capital construction flowcharts codot.gov
  10. model clauses file procurement.uark.edu
  11. compliance page transitchicago.com
  12. flowchart C-2-0 codot.gov
  13. flowchart C-3A-0 codot.gov
  14. flowchart C-4-0 codot.gov
  15. help article kb.lcptracker.com

Questions about your transit project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us