MHDC Davis-Bacon certified payroll: the review, the 30 days, and the draw
This page covers what Missouri Housing Development Commission (MHDC) adds on its multifamily developments. It reads MHDC's Prevailing Wage Policy (June 2025), its Davis-Bacon workshop deck, and its Construction Disbursement Guide (January 2025).
Last reviewed against the sources it cites
The short answer
Weekly certified payrolls go to MHDC, with the general contractor coordinating the submission. MHDC reviews every one and emails the general contractor a list of issues, and the 2023-24 deck gives 30 days to resolve them before disbursements may be delayed. The wage determination in effect when the construction loan documents are signed is locked in. Neither the policy nor the deck states a payroll penalty; the disbursement guide warns of disapproval from future MHDC programs.
- MHDC's 2023-24 application workshop deck says MHDC reviews all certified payrolls, emails the general contractor a list of issues, and allows 30 days to resolve them, after which unresolved issues may delay disbursements.
- Under MHDC's June 2025 policy, the wage determination in effect on the date the construction loan documents are signed is locked in, and later updates do not change the development's wage rates.
- The same policy puts developments with buildings of four or fewer stories under the Residential wage determinations and developments with buildings of five or more stories under the Building ones.
- Each monthly draw request on a project with 12 or more HOME units carries MHDC Form 2450, a certificate from the general contractor and the inspecting architect that the work followed Davis-Bacon and that no compliance issues are outstanding.
- The policy requires a separate certification for each weekly pay period, prohibits one certification covering several, and says the last report should be labeled Final Payroll.
- MHDC's Workforce Eligibility Compliance Handbook has each contracting party submit a Workforce Eligibility Affidavit before any work starts and a copy of its E-Verify Memorandum of Understanding as proof of enrollment.
MHDC emailed a list of payroll issues. What is the clock?
The deck says MHDC reviews all certified payrolls and emails a list of issues to the general contractor. You then have 30 days to resolve them. After 30 days, unresolved issues may delay disbursements. The email goes to the general contractor, so ask your general contractor for the list.
- Get the full list from your general contractor.
- Sort the items against the deck's common issues in the table below. Four of the seven are missing documents, not wrong pay.
- Treat underpayments separately. The policy has the general contractor correct all underpayments within 30 days with a Restitution Payroll and proof of payment. That 30 days is for correcting underpayments once MHDC notifies the contractor, and the deck's 30 days is for the issues list. Neither source says whether the two overlap. Our Missouri certified payroll page lists the items.
- Ask for confirmation. Neither document says how MHDC confirms an item is cleared, so ask MHDC staff to confirm in writing through the MHDC contact page.
Neither the policy nor the deck states a penalty or a debarment for a late or wrong payroll. The one consequence they state is the possible delay of disbursements. Separately, the Construction Disbursement Guide has a Failure to Meet clause warning that missing its time frames and requirements may result in disapproval of the principals or the general contractor from future MHDC multifamily housing programs. That clause is about the guide's draw requirements, not wage rates. MHDC's Workforce Eligibility Compliance Handbook (modified February 20, 2024), attached to its Participant Conduct Certification (Exhibit D), is separate. It covers worker eligibility, not wage rates, and says noncompliance may bring suspension and revocation of funding and suspension and debarment from MHDC programs.
The seven common issues in the deck
| Deck item | What MHDC's documents ask for |
|---|---|
| Affidavit of Worker Eligibility | The handbook in Exhibit D has each contracting party submit a Workforce Eligibility Affidavit before any work starts. The form (MHDC-2507, Rev. 05/2022) is sworn before a notary. |
| E-Verify MOU | A copy of your Department of Homeland Security Memorandum of Understanding is the proof of enrollment, per the handbook. The affidavit form says to attach it. A business with no employees uses the form's alternative statements. |
| Fringe documentation | If the wage determination lists a fringe rate, the policy says the certification must show whether it was paid into a plan or in cash. If you offset the basic wage with fringes, MHDC wants a letter itemizing each plan and amount and certifying the fringes were paid. |
| "Other deduction" documentation | A deduction not required by law or a collective bargaining agreement needs the employee's written authorization, sent with the first payroll. For a court-ordered deduction, MHDC accepts the court order letter. |
| Job classifications | Use classifications from the wage determination, include any subclass or group number, and ask MHDC staff if you need an additional one. Classification follows the work actually performed in the pay period. |
| Apprentices | Each apprentice must be registered in a bona fide Department of Labor program. MHDC wants the Office of Apprenticeship certification, the wage rate documentation, and the ratio schedule for each class. With no certification you pay the full classification rate, and with no ratio information MHDC defaults to 1 apprentice to 1 journeyman. |
| Authorized signatures | The deck says a principal of the company signs, or you give written documentation of an authorized representative. |
Which wage determination applies
The lock date
The policy says one wage determination applies to a development: the one in effect on the date the construction loan documents are signed. It is locked in, and later updates or modifications do not change the rates. The deck, posted as MHDC's 2023-2024 application workshop with no date on the slides, says MHDC issues the final wage determination within 10 days of construction closing and that each one is unique to its development. The two describe different moments, and the policy is the newer document. If the determination in your bid package differs from the one MHDC issues after closing, ask MHDC in writing which is final. MHDC's required contract language also has the determination bound into the Drawings and Specifications and incorporated into the contract (Exhibit D, where prevailing wage applies).
If the construction loan is not from MHDC
If construction financing comes from another source, the developer must notify MHDC within 10 days of the construction loan closing and give it a copy of the executed construction contract (see the policy).
Residential or Building
Under the policy, a development with buildings of four or fewer stories falls under the Residential wage determinations. A development with buildings of five or more stories falls under the Building wage determinations. The policy does not say how a development with buildings on both sides of that line is classed, so ask MHDC before you price.
What an MHDC payroll has to look like
- One certification per weekly pay period. The policy requires a separate report and certification for each weekly pay period and prohibits one certification for several. Label the last report "Final Payroll".
- Working foremen. A foreman or supervisor who regularly spends more than 20 percent of the time on construction work is paid the prevailing wage for the matching classification.
- Owners. If a company is run by its owner or owners alone, they go on the upper-tier contractor's payroll. If an owner works with employees, the owner lists a name, classification, "Owner", and total hours, with no pay amount.
- Signature. The policy requires the original report with an original signature and does not accept photocopies. Our Missouri certified payroll page gives the sequence: email first, then the signed original by mail. The policy does not mention electronic signatures. DOL's WH-347 page says legally valid electronic signatures are acceptable but photocopies or scans of signatures are not, and 29 CFR 5.5(a)(3)(ii)(E) accepts a handwritten or legally valid electronic signature. Before you use an electronic signature on an MHDC payroll, get MHDC's answer in writing.
- Address. MHDC's policy requires each employee's current address and the last four Social Security digits on every certified payroll. The federal clause differs: 29 CFR 5.5(a)(3)(ii)(B), in the eCFR text up to date as of November 5, 2026, says full Social Security numbers and last known addresses must not be on weekly transmittals sent to the agency, and a number such as the last four digits is enough. Follow MHDC's policy, and confirm with MHDC through its contact page only if your payroll system omits the address. Either way, subparagraph (a)(3)(iv)(C) has you keep the full number and address in your own records.
The draw side: MHDC Form 2450
The Construction Disbursement Guide is written for construction loans administered by MHDC. Each monthly draw request on a project with 12 or more HOME units includes the Contractor's Prevailing Wage Certificate, MHDC Form 2450. It certifies that the work in the current AIA G702 application for payment was done in line with Davis-Bacon and that no compliance issues are outstanding. The general contractor and the inspecting architect both certify it. Read that next to the deck's 30 days: the draw package asks for a statement that nothing is outstanding.
The guide ties Form 2450 to 12 or more HOME units. The policy lists other Davis-Bacon triggers, while MHDC's Davis-Bacon page and the deck name just the HOME one. If your development is covered through another source, ask MHDC whether Form 2450 applies. Our HOME page explains how the 12 units are counted, and our tax credit page covers whether a LIHTC project triggers Davis-Bacon and when HOME or other federal money brings it in.
On site, and what your general contractor passes down
The policy says MHDC makes periodic on-site inspections with confidential worker interviews, and that the wage determination must be posted where employees can see it. Where prevailing wage applies, MHDC's required contract language, in Exhibit D, has the contractor post a wage notice, put the wage determination and the HUD-4010 into every subcontract, and obtain the WH-347 or a similar form from each subcontractor. Our HUD-4010 page explains that form.
State law and other states
Missouri's own prevailing wage law is a separate layer. Our Missouri certified payroll page covers it, along with MHDC's email-then-mail cadence and retention. For other states, see certified payroll rules in every state.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Who sends the weekly payroll to MHDC, the general contractor or each subcontractor?
Does MHDC publish a penalty for a late or wrong payroll?
Which wage determination do I use?
Does every MHDC job need Form 2450?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Prevailing Wage Policy (June 2025) mhdc.com
- Davis-Bacon workshop deck mhdc.com
- Construction Disbursement Guide (January 2025) mhdc.com
- Workforce Eligibility Compliance Handbook mhdc.com
- MHDC contact page mhdc.com
- form mhdc.com
- DOL's WH-347 page dol.gov
- 29 CFR 5.5(a)(3)(ii)(E) ecfr.gov
- MHDC's Davis-Bacon page mhdc.com