HOME and Davis-Bacon: how the 12-unit count works
This page reads 24 CFR 92.354 (eCFR, up to date as of November 5, 2026) together with HUD's own interpretation in Labor Relations letter LR 96-02 (August 21, 1996) and the HUD labor standards applicability page.
Last reviewed against the sources it cites
The short answer
Davis-Bacon wages apply to a HOME construction contract that includes 12 or more HOME-assisted units. The count is per construction contract, not per project. Contracts with 11 or fewer are not covered, unless the contracts were arranged to avoid coverage. Once covered, the whole project is covered, including units HOME does not assist.
- The wage provisions go into every construction contract that includes 12 or more units assisted with HOME funds, under 24 CFR 92.354(a)(1) (eCFR, current as of November 5, 2026).
- Four 4-unit HOME projects pooled into one construction contract make a covered contract, per HUD Labor Relations letter LR 96-02 of August 21, 1996.
- HOME money spent on land, soft costs or other non-construction items still triggers coverage, and coverage then reaches non-assisted units too (24 CFR 92.354(a)(2), eCFR).
- Splitting one project into separate contracts of 11 or fewer units to avoid Davis-Bacon is prohibited, and in LR 96-02 HUD accepted phasing where it appeared to protect the lender (case 1) and rejected a split of single-family units made only to avoid wages (case 2, HUD).
- The participating jurisdiction must collect and review certified weekly payrolls, and must require a certification of compliance before it makes any payment under a covered contract (24 CFR 92.354(a)(3)(iii) and (vi)).
The short rule: 12 HOME-assisted units in one construction contract
The regulation says every contract for the construction of housing "that includes 12 or more units assisted with HOME funds" must require Davis-Bacon prevailing wages for "all laborers and mechanics employed in the development of any part of the housing." The same paragraph adds overtime under the Contract Work Hours and Safety Standards Act (24 CFR 92.354(a)(1)).
HUD's letter reads that as a bright line: "contracts with 12 or more HOME units are covered; contracts with 11 or less HOME units are not" (LR 96-02, "Unit Threshold" section). The unit of count is the construction contract, not the project or the construction work.
The federal wage rules that apply once a contract is covered are the same ones described on the housing authority page and the WH-347 page. This page is about the step before that: whether your contract is covered at all.
How the 12 is counted
Which units count
Only HOME-assisted units count. A contract can include units that HOME does not assist, and those do not add to the 12. The participating jurisdiction (PJ) sets the number of assisted units in a project, mainly for other HOME purposes, and HUD's offices agreed that this number is acceptable for the Davis-Bacon threshold (LR 96-02, "Unit Threshold" section). That letter notes the PJ counts units per project, not per construction contract, so you may need the PJ's project figure and the contract's scope side by side.
Group homes and single room occupancy (SRO) projects have a special rule. A PJ may treat a group home as one HOME unit or classify it as SRO units, and Davis-Bacon applies if the HOME-assisted SRO dwelling units covered by the construction contract total 12 or more (LR 96-02, special note on group home and SRO projects).
HUD's applicability page adds that the count follows the units identified as HOME units under the program definition, whether set pro rata, by specific designation or another method CPD allows.
Which contracts are tested
- Take the PJ's count of HOME-assisted units for each project.
- List the construction contracts.
- Add up the HOME-assisted units each contract covers. Twelve or more means covered.
Two consequences follow, both from the "Unit Threshold" section of LR 96-02 and the regulation. A project of 12 or more units built under several contracts, each with 11 or fewer HOME units, is not covered, so long as the split is not a device to avoid coverage. And several small projects pooled under one contract are covered once the contract totals 12 or more. HUD's example is four projects of four HOME units each in one contract.
HUD's worked cases
LR 96-02 is still marked "effective until it is amended, superseded, or rescinded." It is a 1996 document, so check with your PJ that HUD has not issued a newer position. Rows 1, 2, 5, 6, 7 and 8 are HUD's decisions from its case studies (part III). Rows 3 and 4 are not decisions on a submitted proposal. They are HUD's hypothetical variation on case 2, from its "special notes" under that case.
| Facts | HUD result | Reason given |
|---|---|---|
| 59-unit subdivision built in phases of 10 or 11 units, separate contract per phase | Not covered | The PJ, as lender, funds phases only after the earlier one succeeds. HUD found the split "appears" to be a precaution to protect the lender, not a way to avoid wages. |
| 60-unit multifamily plus 100 single-family homes, 33 of them HOME-assisted, split into three contracts of no more than 11 | Whole development covered | The multifamily building is covered. Nothing explained the three contracts except avoiding prevailing wages. |
| Hypothetical on case 2: the same 100 homes set up as three separate projects of 11 HOME units, each with its own contract | Not covered | The rule bars splitting contracts inside one project. It does not bar several projects in one proposal. |
| Hypothetical on case 2: those three 11-unit projects grouped under one contract | Covered | The contract now holds 12 or more HOME units. |
| 40 homes under one contract, each entered as its own project, sales contracts signed before construction | Covered | Land ownership and separate database entries do not matter. The contract holds 40 assisted units. |
| Six projects totaling 22 units, each with its own application, loan and contract | Not covered | No contract holds 12 or more. Entering them the same day changes nothing. |
| 15 units in two buildings (9 and 6). The first contractor was dismissed, so the work was re-contracted one building at a time to protect tax credits | Not covered | The split was to keep the work moving, not to avoid Davis-Bacon. |
| Two buildings of 8 HOME units each, one contract, HOME money spent only on land and soft costs | Covered | HOME triggers on construction and non-construction costs alike. The contract holds 16 assisted units. |
The pattern is that HUD asks why contracts were divided. A lender or schedule reason survived. A stated aim of avoiding wages did not.
One more case matters to site subcontractors. In a 14-unit HOME subdivision, the site improvements were under one contract and covered, while the later contracts for individual houses were not. HUD treated the site work as incidental to the housing and applied a residential wage schedule (LR 96-02, case 7).
What HOME money counts, and when homebuyer aid counts
Coverage turns on "assisted", not "financed". The regulation applies the wage clause if HOME funds pay any project cost allowed under 24 CFR 92.206, "including construction or nonconstruction costs" (24 CFR 92.354(a)(2)). HUD's page lists land acquisition and architect and engineer fees as non-construction costs that still trigger it (HUD).
Homebuyer aid has its own test. If HOME money assists buyers of single-family housing and pays no other project cost, the wage provisions apply when there is a written agreement with the owner or developer that HOME will assist buyers, and the construction contract covers 12 or more housing units to be bought with HOME assistance (same paragraph).
Once covered, the whole project is covered
The wage provisions must be written into the construction contract "so as to cover all laborers and mechanics employed in the development of the entire project, including portions other than the assisted units" (24 CFR 92.354(a)(2)). HUD's example is that steering all HOME dollars to one part of a project does not narrow coverage to that part (LR 96-02, "Scope of Coverage" section).
The regulation excludes two groups of workers. Paragraph (b) exempts an individual who receives no compensation, or only expenses, reasonable benefits or a nominal fee, and who is not otherwise employed in the construction work; the paragraph points to 24 CFR part 70 for volunteers. Paragraph (c) exempts members of an eligible family who work in exchange for a home or in place of rent. HUD Handbook 1344.1 REV-3 (January 2023), chapter 2 repeats the sweat equity exemption and says volunteer projects need records.
What the PJ must do, and what it means for your payroll
The PJ is responsible for contractor and subcontractor compliance. Under 24 CFR 92.354(a)(3) it must:
- put the labor standards provisions and the Department of Labor wage determinations in bid and contract documents;
- conduct on-site inspections and employee interviews;
- collect and review certified weekly payroll reports;
- correct violations promptly and keep records of its actions; and
- require certification of compliance with the section before making any payment under the contracts.
For you, the last item is the practical one. The PJ must have the compliance certification before it makes any payment, and it must also collect and review your weekly certified payrolls. 24 CFR 92.354 was last amended at 90 FR 888 (January 6, 2025). Under 24 CFR 92.354(a)(3), contractors and subcontractors must comply with the regulations issued under the Davis-Bacon and related acts. The weekly payroll comes with a signed Statement of Compliance, as the Nebraska manual below shows (it asks for form WH-348). The clause at 29 CFR 5.5(a)(3)(ii)(A) makes the prime contractor responsible for submitting all subcontractors' certified payrolls. See the WH-347 guide for the form. Employee interviews are covered on the HUD-11 page.
Certified payrolls are submitted weekly under 29 CFR 5.5(a)(3)(ii)(A). The 5.5 text cited on this page is the current eCFR text, and the clause version in your own contract controls. As one example of a deadline, Nebraska's HOME Administration Manual chapter 12 (revised August 2021) says contractors should submit payrolls within seven working days of the payroll end date, and its checklist says a copy of the first two payrolls must be submitted to the state. Ask your PJ for its deadline in writing. The same manual notes that contracts under 12 assisted units are still subject to the Fair Labor Standards Act.
HOME compared with CDBG
CDBG asks about property: its labor standards cover the rehabilitation of residential property only if the property has 8 or more units (HUD reads the exemption for 7 or fewer units to reach new construction too), and apply to work financed in whole or in part with CDBG (HUD applicability page). HOME asks about assisted units per construction contract, and reaches non-construction spending. See the CDBG page for that program.
Where tax credits and other layers fit
HOME money in the same building can bring in Davis-Bacon if a contract holds 12 or more HOME-assisted units. See the tax credit page for other layers. For state-by-state differences, see certified payroll requirements by state.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Is a HOME project with 11 units exempt from Davis-Bacon?
Do the non-HOME units in the building count toward the 12?
Can the owner phase the work to stay under 12?
Does Davis-Bacon apply if HOME paid only for land?
Who tells me whether my contract is covered?
Is the threshold 12 today?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- 24 CFR 92.354 ecfr.gov
- Labor Relations letter LR 96-02 hud.gov
- HUD labor standards applicability page hud.gov
- HUD Handbook 1344.1 REV-3 (January 2023), chapter 2 hud.gov
- 29 CFR 5.5(a)(3)(ii)(A) ecfr.gov
- HOME Administration Manual chapter 12 (revised August 2021) opportunity.nebraska.gov