Minneapolis certified payroll: who submits what in LCPtracker, and what the city holds back
This page reads the City of Minneapolis prevailing wage page (updated March 19, 2026), its reporting tools page, the city's fact sheet and checklist (both reviewed March 2025), and Ordinance 2016-044, which amended Chapter 24 of the city code. PDF links here go to archived copies.
Last reviewed against the sources it cites
The short answer
On a Minneapolis city construction contract, contractors with on-site labor hours submit payroll in LCPtracker, bi-weekly, and weekly on Davis-Bacon projects. The checklist has the prime approve subcontractor payrolls. For lower tiers, the Prime Approver Guide says the city then accepts; the prime's own payroll may go straight to the city. For missing payrolls, section 24.240, as amended by Ordinance 2016-044 (June 2016), has the finance officer withhold payments for the periods missed.
- Section 24.240, as Ordinance 2016-044 amended it in June 2016, has the city withhold payments to the contractor for the periods of noncompliance when certified payroll reports are not supplied.
- The city's contractor compliance checklist, last reviewed March 20, 2025, says subcontractors sync from CCIMS to LCPtracker, so the prime must add them in CCIMS first.
- The same checklist says payrolls are bi-weekly in LCPtracker and that Davis-Bacon projects require weekly certified payroll submittals.
- As amended by Ordinance 2016-044 (June 2016), a section 24.250 contract clause lets the city charge liquidated damages of 5 percent of the entire contract price when an underpayment stays uncured 30 days after written notice.
- Under section 24.260, as amended by Ordinance 2016-044 (June 2016), a contractor on the default list gets no new city contracts for as long as it is in default or for three years from default, whichever is longer.
- The Contractor Quick Start Guide of December 2024 says the agency or the prime creates a contractor account, the Prime Approver Guide says the agency may let subcontractors set up their own lower-tier subs, and LCPtracker emails the new user a user ID and temporary password.
A payroll is missing and the city is holding payment
Section 24.240 says that when a contractor fails to supply certified payroll reports, or the reports show the required wage is not being paid, the Department of Civil Rights notifies the city finance officer, who withholds payments to the contractor for the periods of noncompliance. This text comes from the June 2016 amendment, a PDF that shows struck and inserted words together without markup, so check the live code for changes since.
The fact sheet makes the general contractor responsible for its own and its subcontractors' bi-weekly submissions in LCPtracker, so the prime answers for your payrolls. Where to start:
- Check the payroll status. The prime sees an Accept Status for each payroll: Submitted, Updated, Resubmitted, Permit Edit or Rejected (Prime Approver Guide).
- Read the rejection, or ask for Permit Edit. A rejection carries the prime's reason, sent to you as an admin notice and an email. If you found a mistake after certifying, ask the prime for Permit Edit, which unlocks the record, unless the city has restricted this once it accepts the payroll.
- Involve the city. The checklist tells primes to work with the city to resolve all non-compliance issues.
Does the Minneapolis rule apply to your job?
The city page says the ordinance covers city construction projects of $50,000 or more where the city contracts directly with a general contractor. Development agreements may not be covered, it says; the fact sheet says they are not.
The city page's wording differs on the dollar line: its opening line says "more than $50,000" and its overview says "greater than or equal to." The ordinance text is plain. Section 24.200 lifts sections 24.200, 24.230, 24.245 and 24.265 only where the estimated total cost of the entire project is less than $50,000, so a project at exactly $50,000 is covered. Below $50,000 the project stays subject to sections 24.220 (the wage clause), 24.250 (failure to pay) and 24.260 (the default list). The payroll section, 24.240, is in neither list, so if your job is near or under $50,000, read your contract's labor clauses and ask the Contract Compliance Officer.
| Rule | Without Davis-Bacon | Federal funding (Davis-Bacon) |
|---|---|---|
| Pay employees | Every two weeks (city page) | Weekly (city page, fact sheet) |
| Certified payroll in LCPtracker | Bi-weekly (checklist) | Weekly (checklist) |
For the federal form, see our WH-347 guide and which version to use. For MnDOT and Hennepin County, see the Minnesota page. Saint Paul has its own program: Saint Paul prevailing wage certified payroll.
Who submits what, to whom, in which system
The reporting tools page says you must use CCIMS and LCPtracker. CCIMS syncs contract information to LCPtracker, the payroll system.
- Before award, the prime sends a booklet. Section 24.230 has the apparent successful bidder give the Department of Civil Rights a signed wage compliance certificate and a pre-construction booklet. It lists each subcontractor's benefits administrator, wage classifications, anticipated hours and rates.
- The prime names a Prime Approver and adds you in CCIMS. The checklist says subcontractors sync from CCIMS to LCPtracker, so they must be added to CCIMS first.
- Your LCPtracker account is created for you. The Quick Start Guide (December 12, 2024) says the agency or prime creates the contractor account, and LCPtracker emails the user ID and temporary password. The Prime Approver Guide says the agency may instead let each subcontractor set up its own lower-tier subs. If you are a lower-tier sub, ask whoever assigned you to the job who sets up your account.
- You enter and certify each payroll. For lower-tier subs, the Prime Approver then reviews it and the city accepts it. Depending on the city's setup, the prime's own payroll may go straight to the city without Prime Approver approval.
- The city checks. Civil Rights staff visit job sites, interview employees and audit books (city page). Section 24.245 adds payroll review.
What you enter and certify
Section 24.240 says each payroll shows, for every laborer and mechanic, the classification, daily hours, rate, gross pay, deductions, net pay, hourly benefit contributions, and the name and address of each benefit administrator.
- Get the payroll in. The Quick Start Guide is LCPtracker's general guide for all its agencies, not a Minneapolis document, and it describes certifying each week. It lists five ways to enter a payroll: copy a previous payroll, upload a payroll export, upload the Excel template, a direct payroll interface, or manual entry. Which upload routes are enabled on a Minneapolis job is up to the city's setup. A worker in two classifications gets two records.
- Clear the notices. You cannot certify until they are cleared. Per the Prime Approver Guide, whether a wrong rate blocks you depends on the city's setup: a notice stops certification, a warning does not, and a hidden validation can still be seen in the Violations tab.
- Certify. Pick the project, payroll type (a work week or no-work weeks), week-ending date, and your name and title. The statement of compliance asks how fringes are paid: 4a into a plan, 4b in cash, 4c exceptions. The eSignature is yours.
- Check your start date. The prime sets it when assigning you to the project, and the guide says the Late CPR Summary report uses it.
The fact sheet says an owner working with a crew reports their own hours and trade, and an owner working alone must be on the payroll of the prime or subcontractor they work for. Apprentice approvals and extra classifications go to the Contract Compliance Officer (checklist). Section 24.265 lets the city require proof of subcontractor status: a written subcontract, a Secretary of State filing, workers' compensation and unemployment insurance. A self-employed independent contractor must also be working under an independent contractor exemption certificate as defined by Minnesota Statutes sections 181.723, subd. 4 and 326B.701. Without that proof, the workers go on the engaging company's payroll as employees owed the prevailing wage.
What the Prime Approver can do
The Prime Approver Guide (version 2, February 23, 2023) says primes can check lower-tier payrolls before the city receives them for final review and acceptance. The prime can reject with a reason or unlock a record with Permit Edit. The guide says to delete a payroll for just three reasons: a wrong week-end date, project or location. It also says to watch that payroll numbers stay in sequence and none is marked final by mistake.
The guide lists settings an agency may choose, including barring a prime from rejecting or permitting edits once the city has accepted a payroll.
When a payroll is late, rejected or wrong
The ordinance rows below rely on the June 2016 amendment, so check the live code before relying on them.
| What happened | What the city says |
|---|---|
| Reports not supplied, or they show the wage is not paid | Finance officer withholds payments to the contractor for the periods of noncompliance (24.240) |
| Employees not paid every two weeks | Withholding of payment to the general contractor (city page) |
| Underpayment uncured 30 days after written notice | Contract clause under 24.250: the city may withhold up to the underpayment on this or other city contracts, charge 5 percent liquidated damages on the entire contract price, use a suspended or debarment list, and end the right to proceed |
| On the default list | No new city contracts while in default or for three years from default, whichever is longer (24.260) |
| You disagree | Written appeal within 30 days of the decision to the governing body of the contracting agency (24.250) |
The city page promises due process, and the ordinance has the Department develop rules for it.
How long to keep records
Section 24.240, the city page and the fact sheet all say to keep payrolls at least one year after completion. On public works projects funded in whole or in part with state funds, Minn. Stat. 177.30 requires records to be kept for three years after the contracting authority makes final payment. The Minnesota page covers the state rules.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Who submits certified payroll on a Minneapolis city contract?
Is it weekly or bi-weekly?
What happens if my payroll is late?
Can the prime reject my payroll after the city accepts it?
Does the $50,000 threshold exempt my small job?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- prevailing wage page minneapolismn.gov
- reporting tools page minneapolismn.gov
- fact sheet web.archive.org
- checklist web.archive.org
- Ordinance 2016-044 mcclibraryfunctions.azurewebsites.us
- Prime Approver Guide web.archive.org
- Contractor Quick Start Guide web.archive.org
- Minn. Stat. 177.30 revisor.mn.gov