Missouri PW-4: what the affidavit of compliance says and why final payment waits for it
This page reads the Division of Labor Standards PW-4, MoDOT's PW-4-MODOT and RSMo 290.290 side by side, plus MoDOT's Engineering Policy Guide section 110.3. For payroll timing and the rest of the state rules, see Missouri certified payroll.
Last reviewed against the sources it cites
The short answer
The PW-4 is a sworn, notarized affidavit that a contractor or subcontractor signs at the end of a Missouri public works job. It states eight things, from full compliance with the prevailing wage law to records kept for inspection. The statute bars final payment until it is filed, and the form carries no deadline of its own.
- RSMo 290.290.2 requires each contractor and subcontractor to file the affidavit upon completion of the public work and before final payment, and says no public body may make final payment until it is filed in proper form and order.
- The PW-4 (07-14) has eight numbered statements, and the last one swears there has been no exception to compliance with a named Annual Wage Order and section for the project county.
- The PW-4-MODOT (03-16) has the same eight statements in substance. Its statement 8 names a General Wage Order number and calls the job a MoDOT project in the county.
- Both forms warn that falsification may bring criminal prosecution under RSMo 290.340, 570.090, 575.040, 575.050 or 575.060 (see the PW-4 text).
- MoDOT's 2026 Standard Specifications, Sec 105.15.2.1, lists the prevailing wage affidavit among the project documentation that can be required before final acceptance.
What the PW-4 is
The PW-4 is the end-of-job affidavit under RSMo 290.290.2. Each contractor and subcontractor on a public work signs one for its own work. The statute says it is filed "upon completion of the public work and prior to final payment," and that no public body may make final payment until it is filed "in proper form and order."
Two versions are in use. The state's PW-4 carries the footer date 07-14. MoDOT's PW-4-MODOT carries 03-16. Both are Missouri Department of Labor and Industrial Relations forms. Both are sworn before a notary, and both have a line for receipt by an authorized public representative.
The eight sworn statements, line by line
You are not filling in a payroll. You are swearing to facts about your own company's work and records. Read each line before you sign.
| No. | What you swear |
|---|---|
| 1 | Your name, your title, and your company. The form does not say which titles qualify. |
| 2 | All requirements of RSMo 290.210 to 290.340 on paying wages to workers on public works have been fully satisfied for your company's work on the named project. |
| 3 | You have reviewed and are familiar with the prevailing wage rules in 8 CSR 30-3.010 to 8 CSR 30-3.060. |
| 4 | You have completed full and accurate records showing each worker's name, occupation and craft, hours, and actual wages for each class of work; the payroll deductions; and the amounts paid for fringe benefits. |
| 5 | Any fringe benefit amounts were irrevocably made to a fund, plan or program on behalf of the workers. |
| 6 | The payroll records are kept, have been provided for inspection to the public body's authorized representative, and will stay available to that body and the Department. |
| 7 | The records will not be destroyed or removed from the state for one year after completion of your company's work on the project. |
| 8 | There has been no exception to full compliance with the wage order for the project. The PW-4 names an Annual Wage Order number and section. The PW-4-MODOT names a General Wage Order number and calls the job a MoDOT project in the county. Both name the project in statement 2 and give the county and the completion date. |
No exceptions
Statement 2 says the requirements were "fully satisfied." Statement 8 says there was no exception to "full and complete compliance." The form has no place to note an open problem. If you know of a classification dispute or an unpaid amount, deal with it before you sign.
The retention wording differs from the statute
The form's statement 7 runs one year from completion of "this company's work." The statute, RSMo 290.290.1, runs one year from "completion of the public work." The two dates can differ if your crew left before the project ended. As advice, not something either source says: keeping records until a year after the whole project is complete would cover both wordings.
Who signs, who notarizes, who receives
You sign with your title and company name, in front of a notary. The notary block asks for the date and the commission expiry. The last line is receipt by an authorized public representative, so the public body acknowledges what it gets. The form does not say who may sign for a company, so ask the public body if the person who ran payroll is not an owner or officer.
The warning above the signature is specific. You acknowledge that falsifying any information in the affidavit may subject you to criminal prosecution under RSMo 290.340, 570.090, 575.040, 575.050 or 575.060. Read your own payroll records before you swear to them.
Is there a deadline to submit it?
No number of days appears on either form. The statute's timing is "upon completion" and "prior to final payment." In practice the public body sets the pace, because the affidavit is what holds up your final payment. Ask it, and read your contract. The Department's page for public bodies tells public bodies to collect a completed affidavit from every contractor and subcontractor before making final payments, and to send a copy to the Division of Labor Standards. For the rest of the state rules, see the Missouri certified payroll guide.
On a MoDOT job, the affidavit is part of final acceptance
MoDOT's 2026 Standard Specifications, Sec 105.15.2, say the engineer makes final acceptance on receipt of "all project documentation required by the contract" and verification that the material was inspected. Sec 105.15.2.1 says that, when the contract requires it, the documentation consists of:
- the Contractor's Affidavit Regarding Settlement of Claims (Form C-242);
- the final change order;
- the DBE participation list and final verification; and
- the Affidavit of Compliance with the Prevailing Wage Law.
A missing PW-4-MODOT from any sub can therefore stand between the prime and final acceptance. If you get a notice about missing affidavits, ask the resident engineer in writing what is outstanding and by when.
A subcontractor will not sign because of a pay dispute
MoDOT's EPG 110.3 covers this directly. It says a sub sometimes refuses to sign the affidavit because of a pay dispute with the prime. It calls that refusal a violation of Missouri law, because the affidavit is required by RSMo chapter 290. It says the prime has the right to withhold final payment if the sub does not submit it, and that the prompt payment law is not enforceable until the sub submits it.
The guide tells its staff to notify the sub that refusing "will only harm the subcontractor and not the prime." It points subs to a claim against the bonding company or a civil action against the prime instead. That is guidance to MoDOT engineers, not statute text, and the guide does not cite the prompt payment section, so check it with your contract before relying on this.
What this means for each side
- If you are the sub: the guide itself points you to the bond claim or a civil action, not to withholding the affidavit. Statement 2 is a sworn statement about wages, so do not sign it for a job where your own workers are unpaid.
- If you are the prime: final payment depends on every tier's affidavit. Ask each sub for its PW-4 before it leaves the job.
Getting it right the first time
- Confirm which form the public body wants: the state PW-4 or, on MoDOT work, the PW-4-MODOT.
- Find the wage order number in your contract documents before you complete statement 8.
- Check your payroll and fringe records against statements 4 to 6.
- Sign in front of the notary, not before.
- Have the public representative complete the receipt line, and keep a copy.
The public body keeps its own list of what to collect. See the PW-5 and PW-8 check-off lists, and certified payroll rules in every state for other states.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Does Missouri have a deadline to submit the PW-4?
Does the PW-4 have to be notarized?
What is the difference between PW-4 and PW-4-MODOT?
Can a prime hold final payment if a sub will not sign?
Where does the completed affidavit go?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Division of Labor Standards PW-4 labor.mo.gov
- PW-4-MODOT epg.modot.org
- RSMo 290.290 revisor.mo.gov
- Engineering Policy Guide section 110.3 epg.modot.org
- 2026 Standard Specifications modot.org
- Department's page for public bodies labor.mo.gov