Nebraska DED CDBG-DR Davis-Bacon: what has to be in before a payment is processed

This page reads Nebraska DED's Chapter 14: Davis-Bacon of its CDBG-DR manual and its Davis-Bacon and Labor Standards page. Chapter 14 is undated; its file address shows a September 2022 upload.

Last reviewed against the sources it cites

The short answer

On Nebraska DED CDBG-DR work, the subrecipient (the organization DED funds) confirms that every weekly payroll and Statement of Compliance is in and every discrepancy is resolved before it approves a payment. Payrolls go to the subrecipient, typically within 10 business days of the pay period, and on to the Department of Labor through DED. If underpaid wages are found, the prime contractor gets 30 days after written notice to correct them, and the prime answers for subcontractors' restitution.

  • Under Chapter 14 section 14.7.1, a progress payment waits on every weekly payroll and Statement of Compliance being received and reviewed and every discrepancy being resolved.
  • Section 14.6.1 of Chapter 14 has the prime contractor send payrolls to the subrecipient within a reasonable time, typically no more than 10 business days after the payroll period ends, and the subrecipient sends them to the Department of Labor through DED.
  • When a review finds underpayments, the subrecipient notifies the prime in writing and the prime, not a subcontractor, has 30 days to correct them, reporting the restitution on a corrected certified payroll (Chapter 14 section 14.8).
  • DED's CDBG-DR page, read November 6, 2026, still lists an end-of-FY26 payment request (drawdown) deadline of June 5, 2026 for the DR-4420 Winter Storm Ulmer grant.
  • Section 14.11.4 of Chapter 14 gives a subcontractor on a work break three options, while section 14.3.1 lists a missing payroll for a no-work week as an error DED enforces.

Your payment request is held: what the review checks

On DED CDBG-DR work, the subrecipient (or successful applicant), the organization DED funds, checks your labor paperwork before it approves a payment. For a progress payment, section 14.7.1 has it confirm that every weekly payroll and Statement of Compliance is received and reviewed with discrepancies resolved, and that employee interviews were checked against payrolls and the wage decision. For a final payment, section 14.7.2 adds that every interview discrepancy is resolved and the files are complete.

Other passages tighten this. Failure to pay the specified wages means payments are withheld until discrepancies are resolved, and may bring restitution, liquidated damages or a debarment recommendation (section 14.5.1). A deduction outside the Copeland Act list needs the worker's written permission, and an unspecified one must be resolved before further payments (14.5.1). No payment may be approved after construction starts without your certification, and your subcontractors', of Davis-Bacon compliance on file (section 14.4.1).

To find what is holding yours:

  1. Ask in writing. Ask the subrecipient's Labor Standards Officer (LSO), whom DED's page says each subrecipient must designate, which payrolls are missing or flagged.
  2. Count the weeks from your first day on site to the end of the billing period, including no-work weeks and your subcontractors' weeks.
  3. Ask about interviews. The LSO interviews workers at least twice per project and compares each interview with the payroll (section 14.6.2). See our HUD-11 guide.

Which grant this is, and whether it is still open

DED's CDBG-DR page says the program serves communities recovering from Winter Storm Ulmer, disaster DR-4420, in 2019. DED's labor standards page says Davis-Bacon applies to the Infrastructure Match Program and the Affordable Housing Construction Program, on federally funded or assisted construction contracts over $2,000 and residential projects of eight or more units. Section 14.2 lists exceptions: contracts at or below $2,000, residential rehabilitation or construction of 7 or fewer units, simple water and sewer line extensions without pumps or tanks, and demolition-only contracts where no federally funded construction is anticipated on the site. For 8 or more units it says compliance "may be applicable." DED's FAQ says Davis-Bacon applies to the Infrastructure Match Program "(except for the projects as listed above)". The list above it on that page is HUD's guidance on how Davis-Bacon applies around the July 7, 2021 grant agreement date, under which work completed before that date is not covered. On Infrastructure Match projects, work finished before the July 7, 2021 grant agreement is outside Davis-Bacon; work ongoing or not yet begun that day is covered from then on (section 14.1.1). HUD's April 2025 bulletin 2025-02 covers 2020 to 2023 disaster grants; its footnote 1 puts 2015 to 2019 grants under a separate 2020 waiver. DR-4420 is a 2019 disaster, so Chapter 14 section 14.1.1 is the rule DED applies; DED's page ties that guidance to the Infrastructure Match Program.

DED's CDBG-DR page, read November 6, 2026, still lists "End of FY26 Payment Request (Drawdown) Submission Deadline: June 5, 2026" and does not say what applies after it. If you are finishing work, ask the LSO or DED whether requests are still being processed.

Who sends what to whom

ItemFrom, toTiming
Weekly payroll and signed Statement of CompliancePrime to the subrecipient, then to the Department of Labor through DED (14.6.1)Typically no more than 10 business days after the pay period ends
Subcontractor payrollsSubcontractor to the prime, who reviews first (14.11.4)Weekly, from the subcontractor's first week to the end of its work
Correction payrollPrime to the subrecipient (14.8)The prime has 30 days from written notice to correct
Semi-annual enforcement reportContractors to the Department of Labor through DED (14.11.6); DED's page says to the subrecipientOctober 1 to March 31 and April 1 to September 30
Quarterly reportsSubrecipient to DED in AmpliFund (DED's page); DED to HUD through DRGR (14.3.1)Quarterly

Chapter 14 names no contractor payroll portal, so ask the LSO how to deliver it. DED's pages differ in two places. One line says the prime submits the Statement of Compliance to DED, while the Reporting list and section 14.6.1 send it to the subrecipient; send it there and ask whether DED wants a copy. The page also says payrolls are due "no more than 10 business days" after the period, where 14.6.1 says typically that long. Plan on 10. Ask the LSO what the semi-annual report needs.

DED's Labor Standards Compliance Officer spot-checks payrolls against interview data, can ask for more or reject a payroll, and enforces corrections (14.3.1). Keep your own copies available to DED, HUD or the Department of Labor (14.11.4), and keep the reports three years from grant closeout (14.1).

Before you start work

  • DED must clear you. The subrecipient submits you and needs DED's approval before you start (section 14.3.2). Chapter 14 does not say what clearance involves, so ask the LSO.
  • Accept the wage decision and sign a certification to pay wages on that basis (14.1). Rates come from Department of Labor decisions on SAM.gov, or a project decision DED orders (14.4.2 to 14.4.4).
  • Record new employees on DED's New Employee Information Form and run E-Verify (14.3.3).
  • Name the signer. An officer or authorized individual with signatory authority signs (14.5.1); an unauthorized signature is an error DED enforces (14.3.1). See our signature guide.

Payroll errors the manual flags

Chapter 14 calls the WH-347 optional. Any format must be signed and certify that the information is true and correct (section 14.11.4).

ErrorWhat the manual says
One Statement of Compliance for several weeksAn error DED enforces (14.3.1). Send one signed statement per weekly payroll.
Unsigned statementResubmit with a signed one (14.11.5).
Missing or vague classification, such as "operator"A typical finding (14.11.3). You are asked to reclassify, and any underpayment becomes restitution (14.11.5).
Apprentice or trainee without papersIf the registration, ratio and wage schedule are not with the first payroll the person appears on, you must resubmit the registration (14.11.5).

A week with no work

Section 14.3.1 lists failing to submit weekly payrolls, "including for weeks of no work," as an error DED enforces. Section 14.11.4 says a subcontractor with a temporary break may submit a "no work" payroll, tell the prime in advance, or number each payroll consecutively. Chapter 14 does not reconcile the two, and 14.11.4 addresses subcontractors. Get the LSO's answer in writing before the first gap.

If an underpayment is found

The subrecipient notifies the prime in writing and says how to compute and document restitution. Section 14.8 gives the prime 30 days to correct it, and the prime answers for subcontractors' restitution (14.6.1). Report it on a corrected certified payroll listing each employee and classification, total hours, the adjustment rate (required rate minus rate paid), gross restitution, deductions and net pay, with a signed Statement of Compliance attached. Workers who receive restitution should sign it. If more is owed, extra payments go on a supplemental correction payroll within 30 days. If a worker cannot be found, the prime places the unpaid amount in a deposit or escrow account at project end (14.8).

On contracts of about $100,000 or more, unpaid overtime also brings liquidated damages. Chapter 14 words the threshold two ways, "in excess of $100,000" in section 14.2 and "$100,000 or greater" in section 14.5.1, so ask the LSO if your contract is at exactly $100,000 (sections 14.2 and 14.5.1). DED's page shows $29 per worker per day. 29 CFR 5.8(a), read November 6, 2026, shows $33, and Chapter 14 says to check 5.8. Under 14.9.3, DED's compliance officer handles amounts below $100 and HUD staff handle larger ones.

No state prevailing wage schedule applies here

The rates on this work are federal, and the sources read for this page show no state wage schedule. Nebraska statute 73-102 asks public works bidders for a fair labor standards statement, unless the authority writes its own hours, pay and conditions into the contract. 73-104 defines the standard as the scale paid by at least 50 percent of contractors in the field. Neither publishes a wage schedule or asks for a payroll, and Chapter 14's records list mentions state wage decisions (14.11.1) but names no state rate source. Our state table counts Nebraska as having no state prevailing wage law and explains the judgment call, including that the Department of Labor's older state table lists Nebraska as having a law with no threshold.

A different DED program: Shovel-Ready

A separate program, the Shovel-Ready Capital Recovery and Investment Act, has its own DED Memorandum 22-01 (September 19, 2022): beneficiaries collect a WH-347 weekly and upload them with quarterly reports to DED.

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

How long do I have to send weekly payroll on a CDBG-DR job?
Section 14.6.1: a reasonable time, typically no more than 10 business days after the payroll period ends.
Do I send payroll to DED or to the organization that hired me?
To the subrecipient, which passes it to the Department of Labor through DED.
Do I need a payroll for a week with no work?
Section 14.3.1 flags a missing no-work week payroll, while 14.11.4 gives subcontractors other options. Chapter 14 does not reconcile them, so ask the LSO in writing.
How long do I have to fix an underpayment?
The prime has 30 days after the subrecipient's written notice (section 14.8).

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Chapter 14: Davis-Bacon of its CDBG-DR manual opportunity.nebraska.gov
  2. Davis-Bacon and Labor Standards page opportunity.nebraska.gov
  3. CDBG-DR page opportunity.nebraska.gov
  4. April 2025 bulletin 2025-02 hud.gov
  5. DED opportunity.nebraska.gov
  6. 29 CFR 5.8(a) ecfr.gov
  7. 73-102 nebraskalegislature.gov
  8. 73-104 nebraskalegislature.gov
  9. DED Memorandum 22-01 opportunity.nebraska.gov

Questions about your CDBG-DR project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us