New York PW 30: when you need a dispensation to work overtime on public work

This page reads Labor Law section 220, the Department of Labor's PW 30 form (12/25) and its 2026 guide for employers. The statute text was read on an unofficial legal-text site because nysenate.gov could not be read by script.

Last reviewed against the sources it cites

The short answer

On New York public work, nobody may work more than 8 hours a day or 5 days a week unless there is an extraordinary emergency. The statute counts a worker shortage as one, and the Commissioner of Labor grants a dispensation for it. You request one on the PW 30. The contracting agency must sign a certification, and the form says no extra hours may be worked until you receive a notice of determination.

  • Labor Law 220(2) bars work of more than eight hours in a calendar day or five days in a week except in an extraordinary emergency, which the statute defines to include a worker shortage that a dispensation addresses.
  • The PW 30 (12/25) says the application cannot be processed without the signed certification of an officer of the contracting agency.
  • The same form says no worker, laborer or mechanic may be employed past 8 hours a day or 5 days a week until you receive a notice of determination.
  • Once a dispensation is granted, work beyond eight hours a day and five days a week is overtime paid at a premium wage commensurate with the premium wages prevailing in the area (Labor Law 220(2)).
  • Labor Law 220(2-a) makes it a misdemeanor for a contracting party to require more than eight hours for a day's labor unless otherwise permitted by law (statute text).
  • DOL's employer guide lists a Dispensation of Hours poster among the postings required on public work projects when applicable.

The 8-hour, 5-day rule

New York writes a hours limit into public contracts. Labor Law 220(2) says each contract to which the state, a public benefit corporation, a municipal corporation or a commission appointed pursuant to law is a party must contain a stipulation. So must any public work contract entered into by a third party acting in place of, on behalf of and for the benefit of such a public entity under a lease, permit or other agreement. No laborer, worker or mechanic may be permitted or required to work more than eight hours in a calendar day or more than five days in a week. The statute allows an exception for cases of extraordinary emergency including fire, flood or danger to life or property. Section 220(2) also defines extraordinary emergency to include a shortage of workers, which is the situation the dispensation addresses.

DOL's guide for employers puts the same rule in plain terms. Employees may not work more than eight hours a day or five days a week unless an extraordinary circumstance requires overtime. The employer and the contracting agency may then apply for permission through a Dispensation of Hours, the PW 30.

This is a limit on the schedule, separate from the wage rate. A crew that is paid the correct prevailing rate can still break the rule by working a ninth hour or a sixth day.

What the dispensation is

A dispensation is the Commissioner of Labor's permission for laborers, workers and mechanics, or for named classifications, to work extra hours or days on a project or in an area. Section 220(2) lets any interested person apply. The Commissioner then decides whether enough workers can be employed to carry on the work expeditiously under the 8-and-5 limit.

The statute ties a grant to two findings. There are not enough workers in the classifications involved, and immediate commencement, prosecution or completion of the work without undue delay is necessary in the Commissioner's judgment for the preservation of the contract site and for the protection of the life and limb of the persons using it. The form asks for your reason in writing.

Extraordinary emergency, in the statute's wording, is also deemed to include the worker-shortage situation just described.

Who signs the PW 30, and why it stalls

The PW 30 has two signatures, and the contractor controls only one.

  1. The applicant completes both pages and signs the dispensation statement. This must be signed by the contractor or an authorized representative.
  2. A representative of the department of jurisdiction, which the form calls the contracting agency, signs the certification at the bottom of page 1. It reads that the project "is of an important nature" and that a delay in completing it "would result in serious disadvantage to the public."
  3. The form says to have an officer of the contracting agency complete the certification and return it to the Bureau of Public Work office listed on the form.

The form states that your application cannot be processed without the certification. The statute goes further: section 220(2) says no dispensation is effective for any public work unless and until the department of jurisdiction certifies that the work is of an important nature and a delay would be a serious disadvantage to the public. If the agency will not sign, plan the schedule without the extra hours.

The form and the statute do not give a lead time or a processing time, so ask the agency and the Bureau of Public Work before you promise the owner a start date for Saturday work.

What the form asks for

Section of the PW 30What you enter
ApplicantCompany name, address, email, telephone and Federal Employer Identification Number
Project identificationPrevailing Rate Case (PRC) number and county, both found on the wage schedule
Project descriptionLocation (city, town, intersection, street or route) and one nature-of-project box: new building, addition, heavy and highway construction, new sewer or waterline, other new construction, other reconstruction, maintenance, repair or alteration, or demolition
ReasonFree-text reason for requesting the dispensation
Dispensation requiredBeginning and ending dates, hours per day and days per week to be permitted, signed by the contractor
Agency certificationAgency name, address, authorized signature, printed name and title, date and telephone
Page 2Each job classification for which the dispensation is requested and the number of employees in each

Ask for the dates, daily hours and weekly days you actually need. The form's own wording is that application is made to permit operations a stated number of hours per day and days per week for the period you give.

Do not start the extra hours early

Page 2 of the form says no worker, laborer or mechanic may be employed in excess of 8 hours in any one day nor 5 days in any one calendar week until you receive a notice of determination. Sending the application is not permission. The permission is the determination.

The criminal provision is section 220(2-a). It says any person contracting with the state, a public benefit corporation, a municipal corporation or a commission appointed pursuant to law who requires more than eight hours of work for a day's labor, unless otherwise permitted by law, is guilty of a misdemeanor and is punished in accordance with the penal law. The sentence addresses the party who requires the work.

Overtime pay once a dispensation is granted

Under section 220(2), whenever a dispensation is granted, all work beyond eight hours a day and five days a week is overtime work. Workers who do it are paid a premium wage commensurate with the premium wages prevailing in the area where the work is performed. The statute does not state a multiplier. Read the premium terms of the wage schedule for your project and classification, and see our guide on overtime, shift and holiday pay.

Postings

DOL's employer guide says employers must display a Dispensation of Hours poster on public work projects when it applies, alongside the wage schedule and the other required notices. The two DOL sources differ here: the guide lists the poster, but DOL's required postings page does not list a Dispensation of Hours poster. Our suggestion, not a DOL instruction, is to ask the Bureau of Public Work or the contracting agency for a copy. The guide says employers are subject to fines for failure to display postings in a prominent place.

How the hours show on payroll

The guide says certified payroll submissions must show the hours and days worked by each worker and the classification each worked in. A worker who passes eight hours or five days under a dispensation should appear with those actual hours. The portal steps are on our New York certified payroll page. The PW 30 itself does not say how to enter overtime on a payroll.

Highway weather make-up time

Section 220(2) has a separate rule for highways. Time lost in any week because of inclement weather by employees engaged in the construction, reconstruction and maintenance of highways outside the limits of cities and villages may be made up during that week and the succeeding three weeks. The statute attaches no application to this rule, so the PW 30 is not what covers it. If your work is on a city street or village road, this sentence does not apply to it. See also roadway excavation prevailing wage.

Where this fits with your other New York paperwork

The PW 30 is one of the forms DOL lists on its public work forms page, described there as the form to request a determination for overtime work. This page relies on the form, the statute and the employer guide. A subcontractor who never received the wage schedule has a different form, covered in our PW 51 guide. For a national comparison, see certified payroll requirements by state.

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

Can I work a Saturday on New York public work without a PW 30?
Not if it makes a sixth day in the calendar week. Section 220(2) bars more than five days in a week except in an extraordinary emergency, and the PW 30 says to wait for a notice of determination.
Who has to sign the PW 30?
Two people. The contractor or an authorized representative signs the dispensation statement, and an officer of the contracting agency signs the certification. The form says it cannot be processed without the second signature.
Is the PW 30 the same as a prevailing wage overtime rate?
No. The PW 30 asks DOL for permission to exceed the hours limit. The pay for those hours is a premium wage commensurate with the premium wages prevailing in the area, per section 220(2).
How long does DOL take to decide?
Neither the form nor the statute gives a processing time. The form only says you may not work the extra hours until you receive a notice of determination.
Does the highway weather make-up rule need a dispensation?
The statute's make-up sentence in section 220(2) does not mention an application. It covers highways outside cities and villages and allows make-up in the same week and the next three.
Where do I send the completed PW 30?
The form carries the Bureau of Public Work address in Albany and says to return it to that office once the agency officer has completed the certification. See DOL's forms page for the current form link.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Labor Law section 220 newyork.public.law
  2. PW 30 form (12/25) forms.labor.ny.gov
  3. 2026 guide for employers dol.ny.gov
  4. required postings page dol.ny.gov
  5. public work forms page dol.ny.gov

Questions about your project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us