WYDOT certified payroll in iCX: what to upload, and when payments stop
This page covers payroll on Wyoming Department of Transportation highway and bridge contracts. It relies on WYDOT's iCX payroll instructions (WYDOT's iCX page lists these instructions as 9-26), the iCX Construction Management System page, and Subsection 110.4 of the 2021 Standard Specifications.
Last reviewed against the sources it cites
The short answer
On a WYDOT contract the prime contractor uploads weekly payrolls for itself and every approved subcontractor in the iCX Construction Management System. Section 110.4 of the 2021 Standard Specifications says WYDOT may suspend monthly progress payments if payroll submissions are more than 14 calendar days late. Federal-aid contracts need weekly payrolls with a Statement of Compliance. State-funded contracts need them only for a wage grievance or force account costs.
- Subsection 110.4 of the 2021 Standard Specifications says WYDOT may suspend monthly progress payments if payroll submissions are more than 14 calendar days late.
- Under the same subsection, federal-aid contracts require payrolls and a Statement of Compliance for the contractor and subcontractors, while state-funded contracts require payrolls when a wage grievance or force account costs call for them.
- WYDOT's iCX payroll instructions say all payrolls go through the prime contractor, which monitors, checks and uploads them for every subcontractor.
- In iCX a saved payroll shows Reviewed if WYDOT checked it for accuracy and Received if no accuracy check was done, per the iCX payroll instructions.
- A subcontractor has no access to the project in iCX until WYDOT approves the subcontract, according to WYDOT's subcontracts page.
Payroll is late: what WYDOT can do
Subsection 110.4 of the 2021 Standard Specifications for Road and Bridge Construction tells you to submit weekly payrolls in WYDOT's Construction Management System. It adds that the department "may suspend monthly progress payments if payroll submissions are more than 14 calendar days late." The word is "may," so suspension is WYDOT's choice, not automatic. The subsection does not say what date starts the 14 days, so ask your resident engineer how WYDOT counts it before you rely on any grace.
The prime contractor handles payroll for the whole job. The payroll instructions say the prime is responsible for monitoring, checking for accuracy and uploading payrolls for all subcontractors. Subsection 110.4, quoted above, lets WYDOT suspend monthly progress payments when submissions are over 14 calendar days late.
The specification text above is the 2021 edition. Your own contract may carry supplemental specifications that change it, so read the one in your bid documents.
Which contracts need payrolls
| Contract funding | What 110.4 requires |
|---|---|
| Federal-aid | Payrolls and a Statement of Compliance for the contractor and subcontractors, in line with the FHWA-1273 required contract provisions. |
| State-funded | Payrolls for the contractor and subcontractors when a wage grievance or the need to document force account costs calls for them. |
So on a state-funded job, weekly uploads are not the default. On a federal-aid job they are. The weekly duty survived the 2026 change that made attaching Form FHWA-1273 optional, as our page on the FHWA-1273 changes explains. For the federal side in general, see WH-347 explained.
Which form is the Statement of Compliance?
Subsection 110.4 requires the "Statement of Compliance" on "Form WH-348" for federal-aid contracts. The 2026 FHWA-1273 requires a signed Statement of Compliance with each payroll in paragraph 3.b.(3) and treats the WH-347 as an optional form, without using the WH-348 number. Confirm the form with the resident engineer, and see which WH-347 version to use.
How the iCX payroll module works
- Get in the project. A subcontractor has no iCX access to the project until WYDOT approves the subcontract, per WYDOT's subcontracts page. The upload form's contractor list shows only subcontractors with approved subcontracts.
- Open Payroll. Use the Construction Dashboard for recent projects or the top menu, then search for the project. The contract wage decision is uploaded in the project for reference.
- Choose Upload Payroll. Pick the contractor and enter the period start and end dates.
- Use the Payroll # field. The instructions suggest noting the county there, such as "#1 - Laramie County," if you use more than one certified wage scale by location.
- Upload the payroll document and click Save. A payroll can be deleted only before you click Save. Until then its status is Awaiting Submission.
No work that week
If the contractor did not work, toggle No Work on the record. The instructions say this matters for the accuracy of the Payroll to Labor report, described below.
What Reviewed and Received mean
| Status | Meaning in the instructions |
|---|---|
| Awaiting Submission | The record is not saved yet. |
| Received | No accuracy check was performed. |
| Reviewed | WYDOT checked the payroll, it was satisfactory, and no further action is needed. |
WYDOT reviews beginning and periodic payrolls for accuracy. Comments from its review appear on the record, if there are any. Received means WYDOT did not perform an accuracy check.
A supplemental payroll request
If WYDOT needs more, iCX generates an email to the payroll contact listed in your company's directory. The instructions put the burden on you: the contractor must keep that contact name up to date. A stale contact is the easy way to miss a request.
- Select the grey line that needs updating.
- Click Upload Supplemental Payroll. This ties the records together.
- Complete the fields as for a new payroll. The Supplemental # Required fills in from WYDOT's entry, with the payroll week and a letter, such as "1A."
The original line then shows Supplemental Submitted.
The Payroll to Labor report
The Reports menu creates a Payroll to Labor comparison. It compares the payrolls you entered for a date range with the labor the engineer's office recorded for the same period. You must enter at least a full week for it to produce data.
The instructions give the failure case: the engineer's log shows your crew working, and you uploaded no payroll. The resolution they give is to contact the engineer to check the labor entries, or to upload the payroll if one is needed.
Wage rates on WYDOT jobs
WYDOT's prevailing wage page posts the state heavy and highway wage decision and the state building and special trades decision, each marked 2026. For the federal determination it points you to SAM.gov. The iCX payroll instructions say the contract wage decision is uploaded into the project. The state statute behind the state decisions is covered on our state requirements table.
Related WYDOT items in iCX
The same iCX page also links a how-to video for the annual FHWA-1391 EEO report, which is a separate report from payroll. See the FHWA-1391 guide. Owner/operator truckers who haul under a lease instead of a subcontract must be listed on the prime's or leasing contractor's weekly certified payrolls, per the subcontracts page.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Can WYDOT hold my payment for late payroll?
Does my subcontractor upload its own payroll?
My payroll says Received, not Reviewed. Is something wrong?
Why can't my subcontractor see the project in iCX?
Do state-funded WYDOT contracts need weekly payrolls?
What if I have no workers on the job one week?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- iCX payroll instructions dot.state.wy.us
- iCX Construction Management System page dot.state.wy.us
- 2021 Standard Specifications dot.state.wy.us
- subcontracts page dot.state.wy.us
- FHWA-1273 required contract provisions fhwa.dot.gov
- prevailing wage page dot.state.wy.us