CMHA certified payroll: what Cleveland's housing authority requires and what holds a payment
This page reads the Labor Compliance text on the Cuyahoga Metropolitan Housing Authority business opportunities page, read November 13, 2026, and the federal clauses at 29 CFR 5.5 and 29 CFR 5.9.
Last reviewed against the sources it cites
The short answer
On a CMHA project covered by Davis-Bacon, every contractor and subcontractor submits a weekly certified payroll from the first week your company works on the project until its work is complete, using CMHA's software, which coincides with the WH-347. CMHA's Compliance Department enforces the labor standards. CMHA's page names no late-payroll penalty or payment hold, so read your contract.
- CMHA's Labor Compliance text says Davis-Bacon covers some, but not all, of its construction projects, and covered ones carry a General Decision Number.
- CMHA says every contractor, subcontractors included, submits a weekly certified payroll starting the first week the company works on the project and for every week afterward until its work is done.
- CMHA says its payroll software coincides with the DOL's WH-347 and points to lcptracker.net for training, but the page does not name the product it uses.
- CMHA says every contractor must make employees available for an interview at the job site with Compliance Department staff.
- CMHA says each contractor keeps its payrolls for at least three years after the project is completed, and the prime keeps a full set for every contractor.
- Federal rule 29 CFR 5.5(a)(3)(iv)(B) lets the Federal agency suspend further payment when records are not submitted or worker interviews are refused, even though CMHA's page states no consequence.
If CMHA has stopped paying you
CMHA's page does not say it will hold payment for a late or rejected payroll. It states no penalty, no hold and no closeout condition. Read your own contract or bid package for any withholding clause. CMHA's page says only that you must log in or register to view and download solicitations.
The federal clauses address payment in two separate ways. First, 29 CFR 5.5(a)(3)(iv)(B) says that if a contractor fails to submit required records or refuses worker interviews during working hours on the job, the Federal agency may, after written notice, "take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds." That is a step the Federal agency can take against the funds flowing to the recipient, not a CMHA withholding clause. The same paragraph says the failure may also be grounds for debarment. 29 CFR 5.9(a) separately says that where a contractor fails to comply with the labor standards clauses, the Federal agency "(and any other agency)" may on its own action, or must on written request of an authorized representative of the Department of Labor, cause suspension of payment until the violations are discontinued and/or until sufficient funds are withheld to compensate workers and to cover any liquidated damages and interest.
Second, the recipient's own right to withhold comes from 29 CFR 5.5(a)(2)(i) as written into your contract. The clause says the agency or recipient of Federal assistance "may, upon its own action, or must, upon written request of an authorized representative of the Department of Labor, withhold" accrued payments or advances needed to satisfy wage liabilities.
So the practical steps are these:
- Ask your prime, or CMHA's Compliance Department through the CMHA business page, what is missing: a week, a signature, a classification, or an interview.
- Count your weeks. CMHA says the weekly payroll starts with your first week on the project and covers "every week afterward until the firm has completed its work."
- Ask for the withholding or payment clause in your contract in writing, including how 5.5(a)(2)(i) withholding is handled.
Does Davis-Bacon apply to your CMHA job?
Not always. CMHA's text says some, but not all, of its construction projects are covered by the Davis-Bacon Act, and it tells bidders to review each bid or RFP document. A covered project includes a General Decision Number, which lists classifications and minimum hourly rates, base wage plus fringe. CMHA says that in most cases the wage decision is locked in when the contract is awarded or construction begins. It also says its Compliance staff will help you work out whether prevailing wage applies.
The rules on when HUD money triggers Davis-Bacon, and the forms HUD attaches, are on our housing authority certified payroll guide. We do not repeat them here. HUD-funded work falls under the clauses at 29 CFR 5.5.
Ohio has its own prevailing wage law, Chapter 4115 of the Ohio Revised Code, covered on our Ohio certified payroll page. CMHA's page does not mention it.
What CMHA says you must do
| Item | What CMHA's page says |
|---|---|
| Who submits | All contractors, including subcontractors. The prime is responsible for full compliance by all subcontractors. |
| How often | A weekly certified payroll report, starting the first week each company works on the project and every week after, until its work is complete. |
| System | CMHA says it uses a software package that coincides with the DOL's WH-347. Training is at lcptracker.net or from any Compliance Department staff member. |
| Pay frequency | Mechanics and laborers must be paid at least once a week. |
| Job-site posting | The prime posts the wage decision and the DOL poster "Employee Rights under the Davis-Bacon Act" (Form WH1321) in a prominent, accessible place. |
| Interviews | Every contractor must make its employees available for an interview at the job site with Compliance Department staff. |
| Records | Each contractor keeps its own payrolls and basic records at least three years after project completion. The prime keeps every contractor's payrolls for the same period. |
| Enforcement | The Compliance Department administers and enforces the federal labor standards on covered contracts. No penalty is stated. |
Each item is a CMHA statement. The federal baseline behind them is in 29 CFR 5.5, including three-year retention in (a)(3)(i)(A). Weekly submission is in paragraph (a)(3)(ii)(A), which words it differently: payrolls are due "for each week in which any DBA- or Related Acts-covered work is performed." CMHA says "every week afterward until the firm has completed its work," which does not mention weeks with no work. Ask CMHA or your prime in writing how it wants a no-work week handled, and see our no-work-performed payroll guide.
Which system does CMHA use?
CMHA's text says "a software package" and points to lcptracker.net for training. It does not name the product or publish a login address. The federal clause allows an agency to permit or require an electronic system, so CMHA's choice is its own. Confirm the product, and who creates your login, with Compliance or your prime before the first payroll.
Do not mix this up with the City of Cleveland. The City runs its own compliance office and forms, covered in our City of Cleveland LCPtracker guide.
If you build your payroll from your own export, our WH-347 guide explains the form that CMHA says its software matches.
Worker interviews
CMHA says every contractor must make employees available for an interview at the job site with Compliance staff, and that it will try to limit disruption to the work. The federal clause behind this, 29 CFR 5.5(a)(3)(iv), lets agency representatives interview workers during working hours on the job and ties refusal to the payment suspension described above. The HUD interview form is covered in our HUD-11 guide.
Where the text sits on CMHA's site
The Labor Compliance text is on the business opportunities page. It ends with an "I have read the above Labor Compliance information" line, and the solicitation details follow it. The same page says you must log in or register to view and download solicitations.
False certifications
29 CFR 5.5(a)(3)(ii)(F) says falsifying the certifications may subject the contractor to prosecution under 18 U.S.C. 1001 and 31 U.S.C. 3729.
For other states and agencies, see certified payroll requirements by state. We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Does CMHA make me submit certified payroll every week?
Is the CMHA software LCPtracker?
What happens if my payroll is late?
Do all CMHA construction jobs need certified payroll?
How long do I keep my payroll records?
Is this the same as City of Cleveland payroll?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Cuyahoga Metropolitan Housing Authority business opportunities page apps.cmha.net
- 29 CFR 5.5 ecfr.gov
- 29 CFR 5.9 ecfr.gov
- Chapter 4115 of the Ohio Revised Code com.ohio.gov