Prevailing wage for architects, engineers and design-build teams in California
The rule is in Labor Code 1720 and 8 CCR 16001. DIR's Director addressed design services in Public Works Case No. 2019-015.
Last reviewed against the sources it cites
The short answer
Design-phase work on a publicly funded project counts as construction under Labor Code 1720(a)(1), whether or not anything is built. The statute names inspection and land surveying. No DIR rule on office-only design work was found; the Caltrans Labor Compliance Manual says lab work or calculations at a consultant's commercial facility, lab, or a surveyor's office would not be covered.
- Labor Code 1720(a)(1) says "construction" includes work performed during the design, site assessment, feasibility study, and other preconstruction phases, including inspection and land surveying, regardless of whether any further construction work is conducted.
- In Public Works Case No. 2019-015 (decision on appeal, February 3, 2022), the Director, deciding whether county funds paid for public work, reasoned that architectural and engineering services were paid for public work to the extent they include covered preconstruction work.
- 8 CCR 16001(c) subjects field survey work traditionally covered by collective bargaining agreements to prevailing wage when it is integral to the project in the design, preconstruction, or construction phase.
- Under Public Contract Code 22161, a local agency design-build entity is able to provide contracting, architectural, and engineering services under one design-build contract.
- Labor Code 1775(b) says a prime contractor is not liable for a subcontractor's section 1775(a) wage penalties unless the prime had knowledge of the underpayment or "fails to comply with all of the following requirements": listed code sections in the subcontract, monitoring of certified payroll, corrective action upon becoming aware of the failure, and a final-payment affidavit.
The short answer
Design-phase work on a publicly funded project is "construction" under Labor Code 1720(a)(1), so it is not outside prevailing wage just because it comes before the build. The statute names inspection and land surveying. It does not say that a licensed architect's or engineer's office work is covered or exempt, and the DIR sources read for this page do not either. The only source read that addresses office work is the Caltrans Labor Compliance Manual, quoted below. Pay prevailing wage to anyone doing field trade work, and get a written answer on the office roles.
What the statute says about design
Public works under Labor Code 1720(a)(1) are "construction, alteration, demolition, installation, or repair work done under contract and paid for in whole or in part out of public funds, except work done directly by a public utility company pursuant to order of the Public Utilities Commission or other public authority." The same paragraph says "construction" includes work performed "during the design, site assessment, feasibility study, and other preconstruction phases of construction, including, but not limited to, inspection and land surveying work, regardless of whether any further construction work is conducted."
Paragraph (a)(1) turns on three things, and all three must be present. Other paragraphs of section 1720(a) cover other kinds of work and do not use these tests.
- Under contract. Labor Code 1771 does not apply to work a public agency carries out with its own forces.
- Public funds. The contract must be paid for at least in part with public money. See whether your project is public works.
- The $1,000 floor. Section 1771 sets a floor: projects of $1,000 or less are outside the prevailing wage requirement.
What DIR has said about architects and engineers
The Director has not issued a rule that sorts design professionals into covered and exempt. The closest statement in the sources read is in Public Works Case No. 2019-015, a decision on appeal dated February 3, 2022, about tenant improvements Los Angeles County helped pay for. The Director wrote that design and preconstruction services of that kind "often include work such as testing, inspection, soil sampling, and surveying, all work that is covered under the prevailing wage law," and reasoned that county funds paid for public work "to the extent that" the architectural and engineering services include covered preconstruction work.
That reasoning cuts both ways. It does not make every hour of an architect's time covered, and it does not exempt the survey or testing crew that an engineering firm sends to the site. The Director quoted former section 1720 and noted that Assembly Bill 1768 (Stats. 2019, ch. 719) expanded the definition of preconstruction work while the request was pending, which the Director said did not affect the decision. The statement was made in deciding whether county funds paid for public work. The line is drawn by the work performed, not by the job title on the contract.
Field work versus office work
| Role | What the sources say |
|---|---|
| Field survey crew | 8 CCR 16001(c): field survey work traditionally covered by collective bargaining agreements is covered when integral to the specific project in the design, preconstruction, or construction phase. See our land surveying guide. |
| Inspection, soil sampling, materials testing at the site | Section 1720(a)(1) names inspection and land surveying. Soil sampling and testing are not named in the statute; Case 2019-015 describes "testing, inspection, soil sampling, and surveying" as covered work, and the Caltrans Labor Compliance Manual, section 9-2-4 (a Caltrans document) says engineering firms furnishing construction inspection, materials testing, and land surveying at the job site are subject to prevailing wage. See our inspectors and testing guide. |
| Lab work or calculations at a consultant's commercial facility, lab, or a surveyor's office | Not addressed in Labor Code 1720 or 8 CCR 16001. The Caltrans Labor Compliance Manual, section 9-2-4(b) says: "Employees performing lab work or doing calculations at a consultant’s commercial facility, lab, or a surveyor’s office would not be covered." It is a Caltrans document, though chapter 9 describes itself as covering state law and DIR precedential decisions. No DIR rule on this was found in the sources read. |
| Licensed architect or engineer drafting, sealing, or designing | No DIR rule found in the sources read. Ask the awarding body how it classified the work, or request a ruling. |
An "interested party enumerated in Section 16000" can ask the Director for a ruling on a specific project or type of work under 8 CCR 16001(a)(1), and 8 CCR 16000 lists a contractor or subcontractor "likely to bid on or to perform" the work. Our coverage determination guide walks through it.
What contractors on a design-build job have to do
Design-build puts design and construction under one contract. For local agencies, Public Contract Code 22161 defines design-build as "a project delivery process in which both the design and construction of a project are procured from a single entity," and a design-build entity as one able to provide appropriately licensed contracting, architectural, and engineering services. The authority is for local agencies and, per section 22160(b)(1), excludes projects on the state highway system.
Sections 1771, 1775, 1776 and 1725.5 speak of "contractor and subcontractor." None of the sources read says how they apply to a design-build entity, so confirm with the awarding body which party holds each duty below.
- Pay prevailing wage to covered workers. Section 1771 requires it for "all workers employed on public works," and that includes the design-phase work described above.
- Register. Labor Code 1725.5 requires a contractor to register with DIR to bid on, be listed in a bid, or perform public work, and "contractor" includes a subcontractor. Registration does not apply to a public works project of $25,000 or less for construction, alteration, demolition, installation, or repair work, or $15,000 or less for maintenance work (subdivision (f)). Our registration guide covers the process.
- Flow the rules down. Under section 1775(b), a prime is not liable for a subcontractor's section 1775(a) penalties "unless the prime contractor had knowledge" of the failure "or unless the prime contractor fails to comply with all of the following requirements." The requirements are to put sections 1775, 1771, 1776, 1777.5, 1813 and 1815 in the subcontract, monitor the subcontractor's certified payroll, take corrective action upon becoming aware of the failure to pay, and get a signed affidavit before final payment. See the flow-down clause guide.
- Keep payroll records. Labor Code 1776 requires each contractor and subcontractor to keep accurate payroll records for every worker employed in connection with the public work.
Design-build procurement under section 22164(c) also asks the entity for an enforceable commitment that it and its subcontractors at every tier will use a skilled and trained workforce on apprenticeable trade work, unless a listed exception applies, such as a project labor agreement. That is a procurement condition separate from the wage rules on this page.
Worked example
A city hires a design-build entity to design and build a fire station. The entity subcontracts the geotechnical work to an engineering firm, which sends a two-person crew to take soil samples and also has a project engineer prepare the foundation calculations in its own office.
- The city's contract is paid with public funds, so section 1720(a)(1) applies to the design phase. The sampling is preconstruction work of a kind the Director has called covered, even if the station is never built.
- The sampling crew is paid prevailing wage and reported on certified payroll. Section 1725.5 requires a subcontractor to register above the $25,000 threshold for construction work, so the firm confirms its registration with the awarding body before the subcontract is signed.
- The office calculations are the open question. The entity asks the city in writing how it classified them before the subcontract is signed.
- The entity puts the section 1775(b) provisions in the subcontract and reviews the firm's certified payroll while the sampling is under way.
What to do next
- List every person who will touch the project and sort them into site work and office work.
- Treat site survey and inspection as covered, as section 1720(a)(1) names them, and treat soil sampling and testing as covered too, since Case 2019-015 describes them as covered work. Put them on certified payroll.
- For office-only roles, get the awarding body's classification in writing, or file for a coverage ruling.
- Check each firm's DIR registration before it starts, and put the required sections in every subcontract.
WellStanding prepares the WH-347 and the eCPR from the payroll export you already run, and a person reviews every filing. You review the finished filing and sign the certification in one step, and nothing is filed until you have signed; we never sign for you.
Questions
Do architects and engineers get prevailing wage in California?
Is design-build exempt from prevailing wage?
Does a design-build prime have to register with DIR?
Is the prime liable if a subcontractor underpays?
Does the work count if the project is cancelled?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Labor Code 1720 leginfo.legislature.ca.gov
- 8 CCR 16001 dir.ca.gov
- Public Works Case No. 2019-015 dir.ca.gov
- Public Contract Code 22161 california.public.law
- Labor Code 1775 leginfo.legislature.ca.gov
- Labor Code 1771 leginfo.legislature.ca.gov
- Caltrans Labor Compliance Manual, section 9-2-4 dot.ca.gov
- 8 CCR 16000 dir.ca.gov
- section 22160 california.public.law
- Labor Code 1725.5 leginfo.legislature.ca.gov
- Labor Code 1776 leginfo.legislature.ca.gov
- section 22164 california.public.law