Davis-Bacon on DOE weatherization work: who is covered and what you submit
This page follows DOE's Weatherization Program Notice IIJA-6, DOE's WAP Davis-Bacon page and its LCPtracker page, plus 29 CFR 5.5.
Last reviewed against the sources it cites
The short answer
Usually no. DOE says WAP annual formula awards are not subject to Davis-Bacon. It applies to work on multifamily buildings with 5 or more units that is funded in whole or in part by IIJA money. If your job is covered, you submit weekly certified payroll through DOE's LCPtracker.
- DOE's WPN IIJA-6 (revised April 14, 2025) applies Davis-Bacon to IIJA-funded WAP work on multifamily buildings with not fewer than 5 units.
- Coverage is counted building by building: a 16-unit project made of four 4-unit buildings is not covered, per FAQ 1 of the notice.
- The notice says there is no "Weatherization Worker" classification under IIJA, so you use the trade classification for the work performed (FAQ 4).
- DOE's LCPtracker page says recipients must submit weekly certified payrolls through LCPtracker unless a waiver is granted, and the software is free to IIJA recipients.
- DOE's WAP Davis-Bacon page says weatherization work cannot begin until LCPtracker attaches the wage determination, with processing time of 30 to 45 days as of DOE's March 31, 2025 update.
Does Davis-Bacon apply to weatherization work?
For a narrow slice of it. DOE's WAP page says that WAP annual formula awards are not subject to DBA requirements. The trigger is the Infrastructure Investment and Jobs Act (IIJA, which DOE's pages also call the Bipartisan Infrastructure Law, or BIL).
Section 40551(b) of that law, quoted in WPN IIJA-6, says that on a WAP project assisted in whole or in part by IIJA funds, the Davis-Bacon requirements apply to work on multifamily buildings with not fewer than 5 units, and no other WAP work under that funding. The notice also covers IIJA work run through the SERC and E&I programs. FAQ 4 of the notice adds that, unlike under the American Recovery and Reinvestment Act, there is no Weatherization Worker classification.
A job is covered when all three are true:
- IIJA money pays for some or all of the work.
- The building has 5 or more units.
- The worker is a laborer or mechanic doing physical work at the site.
How units are counted
Each building stands on its own. FAQ 1 of the notice says a 16-unit project made of four 4-unit buildings is not covered. FAQ 2 says that in a complex with some small and some larger buildings, the buildings with 5 or more units follow Davis-Bacon and the smaller ones do not.
Territories are included. FAQ 3 of the notice says the IIJA requirement applies in United States Territories too.
Who is the subgrantee, and what do they collect?
On a covered job, the notice says a grantee or subgrantee that contracts out IIJA-funded weatherization work on a building with not fewer than 5 units must ensure the Davis-Bacon requirements flow down to the entities that employ the laborers and mechanics doing the work.
The notice's task chart puts the contractor and subcontractor on the hook to certify that prevailing wages were paid. The subgrantee certifies if its own crew does the work, and the chart notes that some requirements may not apply to a subgrantee that is a unit of local government. The notice also excludes direct employees of a local, Tribal or state government from the wage requirement.
In LCPtracker, DOE's WAP page says the subgrantee should select the Prime Approver or Limited Admin role on the Admin Intake form. Prime Approver reviews and approves certified payrolls. Prime contractors submit their own payrolls and make sure their subcontractors submit theirs. Subcontractors submit payroll too.
What a crew submits
The notice says agencies and companies on covered projects must maintain and submit accurate and complete weekly certified payrolls from the start of construction. The general rule in 29 CFR 5.5(a)(3)(ii) is the same: weekly, for each week in which covered work is performed, with a signed Statement of Compliance under (a)(3)(ii)(C). Under (a)(3)(ii)(A), the prime contractor is "responsible for the submission of all certified payrolls by all subcontractors." Our WH-347 guide covers the form itself.
What is specific to WAP is where it goes. DOE calls LCPtracker the DOE authorized certified payroll compliance reporting system, and the LCPtracker page says:
- The software is free to IIJA recipients and subrecipients.
- A company that already has its own Davis-Bacon software, or its own LCPtracker account, must still use DOE's LCPtracker database for IIJA work.
- You can upload from a payroll system, or from a free spreadsheet template found in the Payroll Records section of your dashboard.
- Paper requires a waiver, for a recipient unable or limited in its ability to use the software. Each weekly statement is then due within seven days after the regular payment date of the payroll period.
The notice adds that payrolls and basic payroll records are kept for three years, or as the grant document says. For upload and rejection problems, see our upload template errors and rejected payroll pages. Those describe a Caltrans setup, and DOE runs its own instance with its own intake forms and roles.
Setup comes before the first day of work
DOE's WAP page (last updated March 31, 2025) lays out the order. The wage determination must be in LCPtracker before work begins. DOE's LCPtracker page describes the intake sequence differently: its setup steps (updated July 19, 2024) have the DOE Technical Project Officer submit the Admin Intake and Wage Intake forms, and DOE create only the initial Prime Recipient account. Follow your subgrantee or DOE project officer on who submits which form.
- The grantee tells its DOE project officer about the potential multifamily building.
- The grantee and subgrantee submit the LCPtracker Admin Intake form. Once contractors are identified, each contractor submits the Contractor Intake form.
- When the scope of work is identifiable, the Project Intake and Wage Intake forms go in. Project names follow the pattern DOE-S3-WAP-[state]-[subgrantee]-[building name].
- Weatherization work cannot begin until LCPtracker attaches the wage determination to the project. As of DOE's March 31, 2025 update, the processing time is 30 to 45 days.
- All users complete the required training. DOE's page lists live LCPtracker training for administrators, Prime Approvers and contractors.
If a subgrantee is slow to tell you this, ask early. The notice says certified payroll records submitted prior to the inclusion of the proper wage determination must be reviewed, and any employees paid less than the determined wage rates must be compensated for the difference in all hours worked on the project.
Classifications: there is no Weatherization Worker
FAQ 4 of the notice says there is no "Weatherization Worker" classification under IIJA. You use the classification for the work being performed. FAQ 6 says not to request a Weatherization Worker as a new classification.
FAQ 7 covers crews whose workers cross trades. You may pay a different rate for each classification in a week, if you track actual hours in each classification and pay by that record. Do not estimate hours or use an average. Even when a worker's rate meets or exceeds every classification, the worker still reports hours in each one.
| Type of work (DOE example) | Example classification |
|---|---|
| Batt and blown insulation, caulking, drywall, air sealing, pipe and duct insulation, door repair | Carpenter or Drywall Hanger |
| Furnace, heating and cooling repair, ventilation, duct sealing | HVAC Mechanic or Sheetmetal Worker |
| Window repair | Glazier, Carpenter |
| Plumbing, electrical | Plumber, Electrician |
DOE labels this chart as an example and says it is not legal advice. The notice says the scope of work covered by a classification may differ based on local practice, and tells you to direct questions about the scope of a classification to the Wage and Hour Division. If the wage determination has no classification for a task, FAQ 6 describes a conformance request, which DOE's project officer submits for the grantee using form SF-1444.
Which wage determination: stories decide, not units
The notice says WAP projects fall under a Residential wage determination for buildings of no more than four stories, or a Building determination for buildings with 5 or more stories. Coverage turns on units. The wage determination type turns on stories. Look up the rates on SAM.gov, and see our SAM.gov lookup guide.
DOE's WAP page says to pull the determination near the funding agreement, and to recalculate it if more than 6 months pass before the construction contract or start of work. Under the notice's contracting requirements, whoever solicits bids (a grantee, subgrantee, contractor or subcontractor) must provide or post the wage determination at least 10 calendar days before bid opening. If a competitively bid contract is not awarded within 90 days of bid opening, updated wage determinations go into the final contract unless the contracting agency has obtained an extension from DOL WHD.
Who does not go on the payroll
FAQ 12 of the notice says Davis-Bacon does not apply to energy auditors, inspectors and other personnel who do no physical or manual work at the site. The term laborer or mechanic includes at least workers whose duties are manual or physical, including those who use tools or perform the work of a trade. For owners and working foremen, see our foremen and owners page.
A week with no covered work
The rule in 29 CFR 5.5(a)(3)(ii)(A) is that the contractor or subcontractor "must submit weekly, for each week in which any DBA- or Related Acts-covered work is performed, certified payrolls." See our no work week page for the detail.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Does Davis-Bacon apply to every weatherization job?
Is "more than five units" the test?
Do I have to use LCPtracker?
What if my wage determination was wrong?
Are energy auditors covered?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Weatherization Program Notice IIJA-6 energy.gov
- WAP Davis-Bacon page energy.gov
- LCPtracker page energy.gov
- 29 CFR 5.5 ecfr.gov
- SAM.gov
- 29 CFR 1.6(f)(3)(i) ecfr.gov