Davis-Bacon Certified Payroll on an FAA AIP Airport Project
Built from FAA's Contract Provision Guidelines for Obligated Sponsors and AIP Projects (issued March 17, 2026), the FAA contract provisions page, and 29 CFR 5.5.
Last reviewed against the sources it cites
The short answer
On an airport job funded by the FAA's Airport Improvement Program, the contractor sends weekly payrolls to the airport sponsor, and the sponsor transmits them to FAA, unless FAA is itself a party to the contract. The sponsor puts the Davis-Bacon clause in the contract, and FAA or the sponsor can withhold accrued payments for unpaid wages, and the federal agency can suspend further payment or funds if required records are not submitted.
- FAA's Contract Provision Guidelines issued March 17, 2026 (section A9) require the Davis-Bacon clause in AIP construction contracts and subcontracts over $2,000.
- Under that clause the contractor submits payrolls weekly to the sponsor for transmission to FAA, and the prime contractor is responsible for its subcontractors' submissions (FAA guidelines, A9.3).
- Weekly transmittals carry an identifying number such as the last four Social Security digits. The FAA clause (A9.3, paragraph 3(ii)(A)) bars full SSNs and home addresses, while current 29 CFR 5.5(a)(3)(ii)(B) also bars telephone numbers and email addresses.
- The clause lets FAA suspend further payment, advance or guarantee of funds if records are not submitted, after written notice (A9.3, paragraph 3(iii)).
- The 2025 OMB Compliance Supplement tells auditors to check, for each week of work, that the required certified payrolls were submitted.
Who collects the payroll on an AIP airport job?
The airport sponsor does, unless FAA is a party to the contract. FAA's guidelines say an airport Owner becomes an obligated Sponsor upon acceptance of the AIP grant assurances, and that a Sponsor is a "recipient" of federal assistance when receiving AIP or other FAA grant funds (FAA guidelines, terminology). FAA's mandatory Davis-Bacon clause says the contractor submits a copy of all payrolls weekly, for each week in which any contract work is performed, to FAA if FAA is a party to the contract. If FAA is not a party, the contractor submits them to the sponsor, "for transmission to the Federal Aviation Administration" (FAA guidelines, A9.3, paragraph 3(ii)(A)).
So you do not send payroll to FAA yourself. You send it to whoever the contract names, and the sponsor then transmits it to FAA. The prime is responsible for every subcontractor's payroll.
The wage and payroll rules inside the clause track 29 CFR 5.5, but FAA's mandatory clause text (March 17, 2026) differs from current 29 CFR 5.5(a)(3)(ii)(B) in what it bars from weekly transmittals: the regulation also bars telephone numbers and email addresses, which the FAA text does not mention. That difference is covered below. For the form, see the WH-347 guide.
Which airport contracts carry the clause?
FAA's guidelines list 49 U.S.C. 47112(b) and 40 U.S.C. 3141 to 3144, 3146 and 3147 as the sources (A9.1). They say the clause goes into all construction contracts and subcontracts that exceed $2,000 and include AIP funding (A9.2). The same section extends it past ordinary paving jobs:
| Contract type | What FAA's A9.2 says |
|---|---|
| Equipment installation | Applies to installation projects over $2,000, such as electrical vault improvements. |
| Equipment bought from a vendor's plant | Does not apply. FAA's examples are SRE and ARFF vehicles. |
| Professional services | Applies if the agreement includes tasks that count as construction, alteration or repair under 29 CFR Part 5 and exceed $2,000. |
| Land acquisition | Ordinarily not. It applies if the project employs laborers or mechanics, for example for boundary fencing or demolition of structures, and the contract exceeds $2,000. |
| Fencing | Fencing projects over $2,000 must include it. |
One point surprises engineers and design firms. FAA says an architect or engineering firm that employs laborers and mechanics on construction tasks is acting as a contractor, and the sponsor may not swap the word "Contractor" for "Consultant" in the clause. If your firm does field work under a professional services agreement, expect to submit payroll for those workers.
What does the sponsor have to do?
FAA's guidelines tell sponsors to use the clause text without change. They must also require the contractor to insert it in every lower-tier contract and hold the prime responsible for subcontractor compliance (Sponsor Actions and A9.2). The same document warns that a sponsor that fails to incorporate the required clauses risks audit findings or denial of federal funding.
Beyond the clause, the sponsor's job is set by its grant and its state. Tennessee DOT's Aeronautics flyer (undated) lists the sponsor's duties as putting a current wage determination and the required clause in the bid solicitation, not awarding to a debarred contractor, reviewing weekly payroll records and conducting labor standards interviews (TDOT flyer). Interview frequency is not fixed, but the flyer notes that 29 CFR 5.6 calls for interviews as often as needed to assure compliance.
What can be held back if payroll is missing?
There are two separate levers in the clause.
- Withholding for unpaid wages. FAA or the sponsor, on its own action or at the written request of the Department of Labor, can withhold accrued payments or advances to cover wages owed to workers. The withholding can come from this contract, from any other Federal contract with the same prime contractor, or from any other federally assisted contract subject to Davis-Bacon requirements that the same prime holds. If workers are underpaid, FAA can, after written notice, suspend further payment, advance or guarantee of funds until the violations stop (A9.3, paragraph 2).
- Missing records. If a contractor or subcontractor fails to submit the required records or make them available, the federal agency may, after written notice to the contractor and sponsor, suspend further payment. Failure to submit records on request can also be grounds for debarment under 29 CFR 5.12 (A9.3, paragraph 3(iii)).
In practice the sponsor is the one standing between you and FAA. The Tennessee flyer says the state aeronautics office should receive and review all certified payrolls for the dates of service before it approves a reimbursement request. That is the flyer's instruction to its own staff, not a federal rule, so check what your state aeronautics office or sponsor requires. For payrolls that are never submitted, the clause's route is the suspension of further payment, advance or guarantee of funds after written notice (A9.3, paragraph 3(iii)).
What can you leave off a weekly transmittal?
The FAA clause says weekly payrolls must contain the information 29 CFR 5.5(a)(3)(i) requires, "except that full social security numbers and home addresses shall not be included." Each employee gets an individually identifying number instead, such as the last four digits of the Social Security number. You must still keep the full number and current address, and provide them on request for an investigation or audit (A9.3, paragraph 3(ii)(A)). The current regulation's list is longer than the FAA text: it adds telephone numbers and email addresses (29 CFR 5.5(a)(3)(ii)(B)). A prime may require its subs to give it those details for its own records.
The two sources conflict. FAA says the sponsor "may not make any modification to the standard language" (A9.2), and that language bars only full Social Security numbers and home addresses. The current regulation bars telephone numbers and email addresses too. To resolve it, leave all of those items off your weekly transmittal, and ask the sponsor in writing which version of the clause its contract requires.
Each payroll must come with a signed Statement of Compliance (A9.3, paragraph 3(ii)(B)). The weekly payroll may be submitted in any form desired (A9.3, paragraph 3(ii)(A)), and a properly executed certification on the reverse of the Wage and Hour Division's optional WH-347 satisfies the statement requirement (A9.3, paragraph 3(ii)(C)). The statement is signed by the contractor or subcontractor, or the agent who pays or supervises the payment of the workers. WellStanding does not sign or certify.
How do states and sponsors route the payrolls?
The FAA clause sends payrolls to the sponsor, and sponsors and state offices add their own channels. These are the three sources read for this page.
| Source | What it says about airport payroll |
|---|---|
| Tennessee DOT Aeronautics flyer (undated) | Contractor submits copies of payroll to the sponsor weekly, with a Statement of Compliance. State staff should review certified payrolls before approving reimbursement. It says the Highway wage determination type suits most airfield projects and the Building type suits non-residential enclosures. |
| MaineDOT form for LAP and airport projects (undated) | The form says contractors and subcontractors on a federal-aid project must submit certified payrolls electronically using the Elation system. After award, the local agency should email project details to MaineDOT's Contracts Section so the project can be set up, including the wage decision number and any modification numbers. |
| Manchester Airport project manual (February 2025) | An example of a sponsor bid manual. It reproduces the Davis-Bacon clause under its required contract provisions and attaches a Highway-type general decision for the county. It sets out the same payroll submission language as FAA's clause. |
If you work on an airport in Maine, the form is the place to start. It does not say whether Elation entry replaces submission to the sponsor on a contract with the FAA clause, and the clause still routes payrolls to the sponsor, so confirm with the sponsor whether Elation entry satisfies the transmittal. See Maine certified payroll and Elation Systems for contractors. The New Hampshire DOT's grant assurance document refused the request when fetched, so this page makes no statement about it. For other states, see certified payroll requirements by state, and ask your sponsor for its instructions in writing.
How do auditors check that payroll arrived?
A sponsor that spends federal money is audited against the OMB Compliance Supplement. For the Airport Improvement Program, the 2025 supplement points to its wage rate cross-cutting section. Its suggested procedure is to sample construction contracts and subcontracts over $2,000, verify the required clauses were included, and for each week in which work was performed verify that the contractor or subcontractor submitted the certified payrolls. It adds that auditors are not expected to determine whether the correct wage rates were paid.
For weeks with no work, see our guide to no-work weeks on a Davis-Bacon job.
Where do overtime and wage rates come in?
FAA treats overtime under the Contract Work Hours and Safety Standards Act as its own clause, A7, separate from A9 (FAA guidelines, section A7). Our guide to CWHSSA overtime and liquidated damages covers it. To confirm the wage determination in your contract, see finding your wage determination on SAM.gov.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
Do I send my certified payroll to FAA?
Does the clause apply to a job under $2,000?
Do I put my full Social Security numbers on the weekly payroll?
Can the sponsor hold my payment if a subcontractor's payroll is late?
Does Davis-Bacon apply when we only install equipment?
Can WH-347 be used on an airport job?
Sources
Every figure on this page links to its source where it first appears. The full list, in order:
- Contract Provision Guidelines for Obligated Sponsors and AIP Projects faa.gov
- FAA contract provisions page faa.gov
- 29 CFR 5.5 ecfr.gov
- OMB Compliance Supplement whitehouse.gov
- TDOT flyer tn.gov
- MaineDOT form for LAP and airport projects maine.gov
- Manchester Airport project manual flymanchester.com