LAWA prevailing wage and certified payroll: what the airport's own documents say

This page reads LAWA's published construction standards and its living wage page, then points to DIR's public works FAQ for the California payroll rules.

Last reviewed against the sources it cites

The short answer

LAWA's July 2016 construction standards say work on LAWA property may require prevailing wage under federal or state law, and the tenant must decide whether it does. They name no payroll form, portal, or deadline. If it is public works, DIR's prevailing wage and payroll rules apply, with listed exemptions from eCPR filing (small projects, projects monitored by a legacy labor compliance program, and qualifying project labor agreements).

  • LAWA's construction standards, dated July 2016, say construction, demolition, installation, repair or maintenance work on LAWA property may require prevailing wages.
  • The same document says the tenant must determine whether prevailing wage laws apply, and must comply with the California Labor Code and other labor laws.
  • The tenant must indemnify LAWA for damages, penalties, fines, attorney's fees and litigation costs LAWA incurs from noncompliance with applicable prevailing wage laws on that work (LAWA standards, section 00 73 43).
  • DIR's public works FAQ says contractors performing work on projects exceeding $1,000 must pay prevailing wages and maintain payroll records (it cites Labor Code 1771 and 1776).
  • If you are unsure whether a project is public works, you can ask DIR's Office of the Director for a coverage determination, as the public works FAQ explains; published determinations are online.

What LAWA's documents say about prevailing wage

LAWA is Los Angeles World Airports, which its homepage calls the governing body for LAX and Van Nuys Airports. Its construction standards guide specification is dated July 2016. Section 00 73 43, "Wage Rate Requirements," is the part that matters here. It says three things.

  1. Construction, alteration, demolition, installation, repair or maintenance work on LAWA's property "may require" payment of prevailing wages under federal or state prevailing wage and apprenticeship laws.
  2. The tenant is obligated to decide whether prevailing wage laws apply. The tenant must comply with the California Labor Code and with federal, state and local labor laws.
  3. The tenant must indemnify LAWA, and pay or reimburse it, for damages, penalties or fines LAWA incurs or pays because of noncompliance with applicable prevailing wage laws on that work. The section says this includes attorney's fees and litigation costs.

Sections 00 73 10 and 00 73 43 address the tenant and the tenant's general contractor. Section 00 73 10 calls the general contractor's bond a Labor and Material Payment Bond "for private work," with the tenant, not the City, as obligee. The standards do not say whether any particular tenant project is public works, so that question stays with you.

What LAWA's documents do not say

The construction standards and the LAWA administrative pages we read do not name a certified payroll form, a payroll portal, a reporting deadline, a labor compliance officer, or a wage determination for tenant work. Nothing in them tells a subcontractor where to send payroll. If your contract with the tenant or a LAWA contract names a system or a schedule, that contract controls the mechanics.

QuestionWhat LAWA's published documents say
Does prevailing wage apply?It "may" apply. The tenant decides (section 00 73 43).
Does the tenant indemnify LAWA?Yes, for LAWA's own damages, penalties or fines from noncompliance (section 00 73 43). Who is liable for Labor Code penalties on a contractor is outside what the LAWA document addresses.
Which payroll form?Not stated.
Which system or portal?Not stated.
How often is payroll due?Not stated.

If the work is covered, DIR's rules apply

LAWA's section 00 73 43 also mentions federal prevailing wage law. If the work is California public works under Labor Code 1720, DIR's prevailing wage and payroll rules apply, not LAWA's page. DIR's FAQ says contractors performing work on projects exceeding $1,000 must pay prevailing wages and maintain payroll records (it cites Labor Code 1771 and 1776). As of the November 2026 fetch, it says each contractor and subcontractor must submit certified payroll records directly to the Labor Commissioner through the DIR Public Works Portal, except on the projects the Labor Commissioner has exempted. As of the FAQ's November 2026 fetch, it says records must be submitted at least monthly (within a month after the end of the payroll period) or more frequently if the contract with the awarding body requires it. DIR calls weekly submission the best practice.

The FAQ lists three exemptions from eCPR filing. The first is projects monitored by one of four legacy labor compliance programs: Caltrans, the City of Los Angeles, Los Angeles Unified School District, and the County of Sacramento. Projects monitored by one of those programs are exempt from eCPR filing. The LAWA documents do not say that any LAWA tenant project is monitored by a legacy program, so ask the tenant or your prime contractor whether one is, and read your contract for where payroll is sent. The second is projects covered by a qualifying project labor agreement under Labor Code 1771.4(b)(2). The third is the small project exemption below.

Small projects have a lower bar. The FAQ says contractors who work only on small public works projects need not register or file electronic certified payroll reports, but must still keep payroll records and give them to the Labor Commissioner on request. The exemption looks at the whole contract between the awarding body and the prime contractor, not just your subcontract. The FAQ puts the small-project limits at $25,000 for new construction, alteration, installation, demolition or repair and $15,000 for maintenance. Our project thresholds guide has more, and how to submit certified payroll to DIR walks through the portal.

For deadlines in detail, see certified payroll deadlines in California.

What if the project is not registered with DIR?

You still need a DIR project ID to file in the portal. DIR's FAQ says to contact the awarding body first and ask it to register the project. If it does not, contact the DIR Public Works Office through DIR's contact page. A subcontractor that is not listed on a registered project can request to be added in the portal, then submit its payroll once it has the project ID.

On a tenant improvement it may be unclear who the awarding body is. Ask the tenant and your prime contractor in writing who registered the project, or whether anyone did. Their answer is worth having before the first payroll period closes.

How to settle whether your project is public works

DIR's FAQ says "Public Works" is defined in Labor Code 1720. It says that if you need help deciding whether a project is public works, you can request a coverage determination from the DIR Office of the Director, Legal Unit, at the email address given in the FAQ. It says awarding bodies and other interested parties can ask the Director for a formal determination, and that determinations issued since 2002 are published online. Read earlier ones for facts close to yours. Our coverage determination guide covers the request.

The FAQ lists categories such as professional services, material suppliers, and trucking companies as questions about whether an awarding body must use registered contractors. It then says prevailing wage requirements extend broadly to workers employed "in the execution of the public works contract" and are not necessarily limited to work at the construction site by traditional trades. It also says ready-mixed concrete suppliers have the status of subcontractors under the public works chapter and, effective September 1, 2020, must submit eCPRs to DIR. For any vendor you are unsure about, request a coverage determination.

LAWA's living wage rates are a different rule

LAWA's living wage page describes the City's Living Wage Ordinance under Los Angeles Administrative Code section 10.37. It applies to service contractors, public lessees and licensees, City financial assistance recipients, and their subcontractors. It sets its own rates. LAWA's page says they will increase on July 1, 2026 to $18.42 an hour plus $1.25 for health benefits, and $25.00 an hour plus $7.65 for health benefits for "Airport Employees." The page says covered contractors must let City representatives review operations, payroll and related documents.

That is not the prevailing wage rate on a craft determination, and it does not replace certified payroll on a public works job. A construction project on airport property can raise one question, the other, or both. Compare the two against your scope of work.

If you have a federal airport grant

For federally funded airport projects, see our FAA airport project guide. When both federal and California rules apply, the federal versus California payroll guide explains how they fit together.

Handing the payroll over

If you decide the work is covered and you do not want to build the filings yourself, WellStanding prepares the WH-347 and the eCPR from the payroll export you already run, and a person reviews every filing. You review the finished filing and sign the certification in one step, and nothing is filed until you have signed; we never sign for you.

Questions

Does LAWA require prevailing wage on every tenant project?
LAWA's July 2016 standards say the work "may" require prevailing wage and that the tenant must decide whether it does. They do not say it applies to every project.
Where do I send certified payroll for LAWA work?
The LAWA documents we read name no payroll system. If the project is public works, DIR's FAQ says each contractor and subcontractor submits certified payroll to the Labor Commissioner through the DIR Public Works Portal, except on exempted projects: those monitored by a legacy labor compliance program (Caltrans, the City of Los Angeles, Los Angeles Unified School District, or the County of Sacramento), those under a qualifying project labor agreement, and small projects. Ask the tenant or prime whether a legacy program monitors the project, and check your contract for where payroll is sent.
Does the tenant indemnify LAWA if prevailing wage was missed?
Under section 00 73 43 the tenant must indemnify LAWA for damages, penalties, fines, attorney's fees and costs LAWA incurs from noncompliance. The section does not address who is liable for Labor Code penalties against a contractor, or what your contract with the tenant or prime says about passing that cost to you. If you face a claim, talk to an attorney.
How do I find out if my airport project is public works?
Ask the awarding body or tenant who registered it with DIR. For a formal answer, request a coverage determination from DIR's Office of the Director, as described in DIR's FAQ.
Is the LAWA living wage the same as prevailing wage?
No. The living wage page describes a City ordinance with its own rates for service contractors, lessees and similar parties. Prevailing wage rates come from DIR's determination for the craft and county.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. published construction standards lawa.org
  2. living wage page lawa.org
  3. public works FAQ dir.ca.gov
  4. published determinations dir.ca.gov
  5. its homepage lawa.org
  6. contact page dir.ca.gov

Working on LAWA property? First filing free

Send the payroll export you already run. We turn it into the WH-347 and the DIR eCPR filing, checked by software and verified by a person. First filing free, before you pay us anything. $995 one time setup, then $249 per month flat for crews up to 25 workers.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallFirst filing free