NYCHA certified payroll in eComply: why your invoice is on hold

This page reads NYCHA's eComply deck on CPRs and CHRs (undated), its eComply FAQ (updated March 2025), its CHR deck (undated) and its Accounts Payable and Prevailing Wage pages, read in November 2026. It is not NYCHA support.

Last reviewed against the sources it cites

The short answer

At NYCHA the invoice waits on eComply. On A&CM contracts that invoice through eBuilder, the invoice sits in an eComply hold until a CPR package is submitted, and the package needs every weekly CPR in the invoice period approved. On operations contracts you email the invoice or use Transcepta, and type the exact same invoice number into eComply so your payroll and documents link to it.

  • On A&CM contracts that invoice through eBuilder, the invoice stays in an eComply hold until a CPR package is submitted, and you are notified that the invoice is pending package submittal (NYCHA's CPR and CHR deck, undated).
  • The deck says every weekly CPR in the invoice period must be in Approved status before the package can be submitted, and NYCHA's FAQ (updated March 2025) calls the same requirement Accepted status.
  • On operations contracts the invoice number typed into eComply must match the emailed invoice number exactly, and the deck says to avoid special characters (NYCHA deck).
  • Prevailing wage hours go on the weekly CPR and non-prevailing wage hours on the weekly CHR, and a worker who does both kinds of work appears on both (deck).
  • A non-performance report cannot be the first submission on a project (FAQ, answer 50), and one report can cover several weeks only after those weeks have passed (deck).
  • The general (prime) contractor who subcontracts must use the Manage Subcontractors module to assign subcontractors and upload each subcontractor's NYCHA Procurement Approval document, and every subcontractor, at any tier, enters its own payroll (FAQ, answer 16).

Why a NYCHA invoice sits on hold

At NYCHA the invoice waits on eComply, and how it waits depends on the contract. The deck describes one route for Asset and Capital Management (A&CM) contracts that invoice through eBuilder and another for operations contracts.

A&CM contracts that invoice through eBuilderOperations contracts
InvoiceSubmitted in eBuilder, which creates the invoice number and dates in eComply. You do not type the number.Emailed to NYCHA Accounts Payable (see its page), or sent through Transcepta e-invoicing. You type its number into eComply, and it must match exactly.
The holdThe eBuilder invoice stays in an "eComply hold" until you submit a CPR package.An Oracle prevailing wage hold, released when eComply shows the payroll as approved.
What clears itEvery weekly CPR in the invoice period approved, then the package submitted.The invoice number you type links your supplemental documents and payroll to the emailed invoice.

A&CM contracts: the eComply hold and the CPR package

The deck says you are notified when the invoice is pending package submittal, and that the eBuilder payment process moves to NYCHA approval only after the package is submitted. The package cannot be submitted until every weekly CPR in the invoice period is submitted and approved. The deck's word is Approved. NYCHA's FAQ says Accepted, and adds (answer 53) that if there are subcontractors on the project, their CPRs must be in Accepted status before being added to the package. The FAQ names "CPD Primes" as the submitters, a term it does not define, and the deck says "Contractor". Ask your prime or your A&CM project manager who submits the package and where your payroll stands.

  1. Check Action Items on the eComply home page. The deck says it lists CPRs awaiting your review if you are a prime, projects with overdue CPRs, and rejected CPRs.
  2. Check every week in the invoice period has a CPR, and each CPR shows approved status. The sources do not say how a non-performance week is treated in the package.
  3. Send the CHR package first if you also have CHRs in the period.
  4. Create the CPR package. Under Activities choose CPR Package Management, pick the borough, contract and project, and select Create New. Pick the eBuilder invoice number, select the CPRs in that period, then Preview and Submit.

The two decks differ on a missing CHR package. The CPR deck says eBuilder moves forward but flags it and slows approval. The CHR deck says the invoice stays in eComply hold until both packages are submitted. Both say to submit the CHR package first, so do that, and ask your A&CM project manager if the invoice is still held.

Operations contracts: the invoice number has to match

The deck says the invoice number in eComply must match the emailed invoice exactly so your documents link to it, and to avoid special characters. Its Step 2 has you type the invoice number, then enter payroll and certification and upload supplemental documents, while its appendix flow shows weekly payrolls submitted and approved before invoicing. Type the number as it appears in Oracle. Upload the Statement of Services, sign-in sheet, Section 3 Hiring Summary and Affidavits of General Contract under Project Documents. The Accounts Payable page (undated) adds that an invoice number must never have been used on any current or past NYCHA contract.

The deck says NYCHA no longer accepts paper invoices and CPRs, and that contracts or purchase orders from 2020 or earlier keep the previous process. The Accounts Payable page lists a postal address and says it pays from original invoices. The two differ, so ask NYCHA through the contacts on its Accounts Payable page.

The deck names Transcepta, NYCHA's electronic invoicing service, as the second route, and the Accounts Payable page says NYCHA has partnered with Transcepta. The deck's payment slides list the invoice first, while its appendix flow has you wait for eComply approval before invoicing. The sources differ on the order, so ask Accounts Payable which applies to your contract. Our eComply guide covers sign-in and rejections.

CPR or CHR: which hours go where

ReportHours it carriesWhat you enter
CPR, Certified Payroll ReportHours subject to prevailing wage under Davis-Bacon or HUD's Maintenance Wage Rate DecisionHours, wages, fringes, deductions, then the Statement of Compliance
CHR, Certified Hourly ReportHours in non-prevailing wage titlesHours by employee and title; no wage or fringe data

CPRs are weekly; CHRs are weekly, or less frequently in some cases. A worker who does both kinds of work appears on both, prevailing wage hours on the CPR and the rest on the CHR, with matching week-ending dates. The CHR deck says that on certain A&CM professional services only projects the cadence may be quarterly, so consult your A&CM project manager. Subcontractors submit their own CHRs, and the FAQ says to type NON in the Crafts and Classifications search to find non-prevailing titles.

Non-performance weeks

The deck says a week with no hours on the project still needs a Non-Performance report (NP), and one NP can cover several weeks, but only after they have passed. The FAQ says your first submission must be a CPR, because eComply will not accept an NP before it. After that, submit an NP for every week you are not working until you return. A CPR NP and a CHR NP are separate reports in separate menus, and an NP CHR likewise waits for a first CHR. In the NP wizard you sign to certify that the employees worked no hours that week.

Titles are set up per project, and fringe packages need current rates

The deck says craft and classification titles do not carry over between projects. Add a title again for each new project, because a title not added to the project will not appear in your CPR and causes errors. Seeing a craft on the Crafts and Classifications page does not mean it is linked to your project, so find the project by purchase order or contract number and select Add Craft. If a craft is missing, the FAQ says to select Other or ask NYCHA for a similar or new title.

The FAQ says you cannot select a fringe package when the current date is outside its effective range. For a rate that changes mid-week, add a package with Save As and enter 2 in No. of Classifications, which gives one employee two lines on one CPR. eComply takes hours and full dollar amounts, not percentages. For a spreadsheet upload, the deck says to have your template preapproved by eComply support.

Subcontractors: the prime contractor assigns, and every tier enters its own payroll

The FAQ says a subcontractor without access to a project asks the general (prime) contractor to assign it (answer 15). It also says the general (prime) contractor who subcontracts must use Manage Subcontractors to assign subcontractors and upload the subcontractor's NYCHA Procurement Approval document for every project (answer 16). Every subcontractor, at any tier, enters its own CPRs, and the general contractor enters payrolls for its own employees. The deck's slide on subcontractor requests says contractors assign their own subcontractors and subcontractors assign theirs, if applicable. The deck and FAQ differ on lower tiers, so if you are a lower-tier subcontractor without access, ask whoever holds your contract.

The deck says primes and subcontractors must upload their documents before they get access to a project site. It splits the approval document by contract type:

  • A&CM projects: the Procurement Approval Letter.
  • Operations and other department projects: the Subcontractor Request Email and Reporting Form 036.013.

The deck describes the prime contractor's package as one combined PDF that also holds Debarment Certification Form 022.015, licenses, proof of PASSPort and New York Department of State registration, and the NY DOL 220-i certificate.

A different hold: money withheld after an underpayment

NYCHA's Prevailing Wage page (undated) says its monitors interview workers and review payrolls, inspection reports and development logs. An investigation that finds underpayment results in money withheld from the contractor, for the worker and for the investigation's cost. NYCHA's Inspector General Anti-Corruption Guide (undated) says submitting falsified certified payrolls is against the law. For the federal process, see back wages withheld from contract payments.

Which wage law applies

The Prevailing Wage page says contractors must comply with "federal, state and city" employment and labor laws on prevailing wages, including Davis-Bacon and Related Acts, the U.S. Housing Act of 1937 and HUD's Maintenance Wage Rate Decision, and the deck says to email NYCHA for contract-specific wage schedules. The state labor department's Article 8 FAQ (undated) says prevailing wages are generally required on HUD-assisted projects, but that Article 8 does not apply on projects assisted by HUD under the U.S. Housing Act of 1937 when the New York State prevailing wage is greater than the prevailing wage established by HUD. The deck points you to NYCHA's prevailing wage team for contract-specific wage schedules. Our New York guide covers the state system. See also the state comparison.

What we do

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

Why is my NYCHA invoice stuck in eComply hold?
On an A&CM contract that invoices through eBuilder, the invoice waits for a CPR package, which needs every weekly CPR in the invoice period approved. Check Action Items for overdue or rejected CPRs.
Why does eComply not link my operations invoice?
The invoice number in eComply must match the emailed invoice exactly, and to avoid special characters. Type it as it appears in Oracle, and do not reuse an earlier NYCHA invoice number.
Do I need a CHR if my workers are all prevailing wage?
The FAQ says a CHR is required if any of your employees work non-prevailing wage titles, and that every hour on the project goes on a CPR or a CHR.
Can I submit a non-performance report for my first week?
No. The FAQ says you cannot submit one until your first certified payroll is submitted.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. eComply deck on CPRs and CHRs nyc.gov
  2. eComply FAQ nyc.gov
  3. CHR deck nyc.gov
  4. Accounts Payable nyc.gov
  5. Prevailing Wage nyc.gov
  6. Anti-Corruption Guide nyc.gov
  7. Article 8 FAQ dol.ny.gov

Questions about your NYCHA project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.