Wyandotte County and Kansas City, Kansas certified payroll: what section 54 requires

This page covers the weekly payroll reports on construction contracts of the Unified Government of Wyandotte County/Kansas City, Kansas. The rules are from General Conditions section 54 in two of its bid manuals: Klamm Park Walking Trail, bid B32960 (bids due August 21, 2024) and Kensington Park Improvements, bid B41516 (bids due May 21, 2025).

Last reviewed against the sources it cites

The short answer

In the two Unified Government of Wyandotte County/Kansas City, Kansas bid manuals read for this page, General Conditions section 54.1 requires weekly reports on a form the Unified Government approves, due no more than 7 days after each pay date, and pay at the rates in the U.S. Department of Labor wage decision for Wyandotte County. No payment is made unless the reports are current and approved by the Construction Compliance Officer.

  • Section 54.1 applies to all construction projects over $15,000, and its text is identical in the Klamm Park manual (bids due August 21, 2024) and the Kensington Park manual (bids due May 21, 2025).
  • Under section 54.1(c) of the Kensington Park manual, each weekly report is due no more than 7 days after the pay date it documents, on a form approved by the Unified Government.
  • The same paragraph says no payments are made unless the weekly reports are current and approved by the Unified Government Construction Compliance Officer (section 54.1(c)).
  • Apprentices and trainees in Department of Labor approved programs may be paid not less than 70 percent of the applicable rate, and their training certificate must accompany the weekly payroll reports (section 54.1(b)).
  • Section 54.1(d) says the Compliance Officer will contact and interview all employees on the job site (Kensington Park manual).
  • Kansas repealed its old state article on public work, K.S.A. 44-201 to 44-205, and the Revisor of Statutes page for 44-201 cites L. 1987, ch. 186, section 1, so section 54 is a contract term and not a state statute.

If your pay application is on hold

The cause is one sentence in section 54.1(c): the Unified Government makes no payment unless the weekly reports are current and approved by its Construction Compliance Officer. Both manuals carry the same text. The same paragraph sets a 7 day deadline for each report, so an overdue week or an unapproved week is the first thing to look for.

  1. List every pay date since the job started. The 7 days run from the pay date, not the end of the work week.
  2. Send any missing week now, on the form the Unified Government approves. Attach the training certificate for every apprentice on those payrolls.
  3. Ask the Construction Compliance Officer named in section 54.1, in writing, for the status of each report, (the manual lists no section 54 contact, so the Procurement & Contract Compliance Department in the Instructions to Bidders is a reasonable place to start, which is our suggestion and not a route the manual provides). Ask which weeks are unapproved and why.
  4. Ask the Engineer/Architect for the reason in writing. Under section 25.1, the Engineer/Architect has 10 days after receiving a partial payment estimate to approve it or return it with written reasons, and you may correct and resubmit.

What section 54 says

ItemWhat the clause saysSection
Projects coveredAll construction projects in excess of $15,00054.1
WagesNot less than the current prevailing per diem rate for each job classification listed in the U.S. Department of Labor General Wage Decision for Wyandotte County, Kansas54.1(a)
Apprentices and traineesIn Department of Labor approved programs: not less than 70 percent of the applicable rate, with the training certificate attached to the weekly payroll reports54.1(b)
Weekly reportsSubmitted no more than 7 days after the pay date they document, on a form the Unified Government approves54.1(c)
PaymentNone unless the reports are current and approved by the Construction Compliance Officer54.1(c)
InterviewsThe Officer will contact and interview all employees on the job site54.1(d)
OvertimeOne and one-half times the basic rate over 40 hours in a workweek; a violation is a violation of the Code of Ordinances section on the 40 hour work week50.1

Section 54 does not use the words certified payroll. It says weekly reports and, in 54.1(b), weekly payroll reports. It does not mention a Statement of Compliance or a signature, and the manuals do not say whether the approved form carries a certification.

Which contracts it covers

Kansas repealed its old state article on public work, K.S.A. 44-201 to 44-205. The Revisor of Statutes chapter 44 index lists all five sections as repealed, and the page for 44-201 cites L. 1987, ch. 186, section 1, with case notes on its per diem wage requirement. Our state table lists no current Kansas prevailing wage law. Section 54 is a contract term, not a state statute.

The scope wording in the manuals does not agree with itself. Section 54.1 covers all construction projects over $15,000. Section 54.2 describes the wage decision as the required wages on federal and federally assisted projects. The Kensington notice says the wage rate applies due to state and/or federal requirements. Paragraph 8 of the Agreement in the Kensington manual and the Klamm Park manual says the work is paid from a Community Development Block Grant, while the Klamm Park Instructions to Bidders also say the requirements of 2 CFR Part 200 apply to all "CPF" awards. For a CDBG contract, our HUD-4010 page covers the federal clauses.

Section 54.1 is written to reach every project over $15,000, and the Agreement defines the Contract Documents to include the General Conditions. Plan to meet it as written, and ask the compliance office how it reads its scope on your job.

Both manuals are park projects from the County Engineer's office, and another department's contract may differ. Section 4.2 says Special Conditions govern over the General Conditions, and section 57.1 says changes are made in the Supplemental Conditions, so read both and every addendum. Kansas City, Missouri is a different government; see our Missouri guide.

Which wage decision

Section 54.2 names the General Wage Decision for Wyandotte County that is current and effective ten days before the bid date, and says bidders may rely on the decision handed out at the pre-bid conference. The Kensington notice adds that the contract uses the Heavy & Highway general decision. The Klamm Park notice has no wage paragraph, yet section 54 is in its General Conditions.

The weekly report

The 7 day clock

The limit runs from the pay date. For example, a crew paid on Friday, November 13, 2026 has until Friday, November 20, 2026 to get the report for that pay date to the Unified Government.

The form

Neither manual names the approved form. On a contract that also carries the federal clause, 29 CFR 5.5(a)(3)(ii)(B) lets the weekly information go on Optional Form WH-347 or in any other format, which does not tell you what the Unified Government has approved. Ask whether WH-347 with its signed certification is accepted. Our WH-347 guide covers filling it in, and this page covers the current version.

Apprentices

The 70 percent floor in 54.1(b) does not spell out how the 70 percent applies to the fringe portion of the rate or how it fits a program's own wage schedule. Section 54.2 describes the prevailing per diem wage rate as the required wages and fringe benefits.

Subcontractors

Sections 54.1(a) and (b) bind the Contractor and Subcontractors, but 54.1(c) puts the reporting duty on the Contractor. Section 32.6 makes the prime responsible for its subcontractors' acts and omissions, and section 32.8 says the contract creates no relationship between a subcontractor and the Unified Government. Ask your prime what internal deadline it sets for your payrolls.

The Compliance Officer's interviews

Section 54.1(d) says the Officer will contact and interview all employees on the job site to assure compliance. The manuals do not say when or how. Check that each classification and rate on your report matches the work and pay the worker would describe.

When reports are late, rejected or wrong

  • Late or unapproved: the payment bar in 54.1(c). Section 54 sets no daily charge or fine for a late report.
  • Rejected: the manuals do not describe how a report is rejected or cured. Ask for the reason in writing.
  • Wrong wages or overtime: section 50.1 makes a violation of the 40 hour rule a violation of the Unified Government's ordinance on the 40 hour work week, to be dealt with as that ordinance provides. The Code of Ordinances could not be read when this page was written.
  • Breach: section 18.1 lets the Procurement Officer declare the Contractor in breach for a substantial breach of the Contract Documents if the Contractor fails, within 14 days after written notice, to start and continue correction. Section 19.1(g) lists disregarding the ordinances, rules, regulations or orders of a public body with jurisdiction. Neither mentions payroll reports.

What the manuals do not say

They do not name the approved form. They do not say whether reports go on paper, by email or into LCPtracker or another system, or what the Officer checks. The Unified Government's own website refused automated access when this page was prepared, so its compliance pages could not be read. Put four questions in writing to the Construction Compliance Officer named in section 54.1 before your first payroll: which form is approved, where and how to send it, who the Officer is on your project, and whether section 54.1 applies as written. The Instructions to Bidders name the Procurement & Contract Compliance Department for equal opportunity and the Contract Compliance Division for tax clearance, and neither is listed for section 54 reports. Our suggestion is to start with one of them and ask who handles section 54.

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

Does Wyandotte County require prevailing wage and weekly payroll reports?
In the two Unified Government manuals read for this page, yes. Section 54.1 covers all construction projects over $15,000 and requires weekly reports and pay at the Department of Labor wage decision rates. Kansas repealed its old state article on eight-hour days on public work (K.S.A. 44-201 to 44-205); the chapter 44 index lists no current replacement.
When is the weekly report due?
No more than 7 days after the pay date it documents (section 54.1(c)). A Friday pay date of November 13, 2026 means a deadline of Friday, November 20, 2026.
Why is the Unified Government holding my payment?
Section 54.1(c) bars payment unless weekly reports are current and approved by the Construction Compliance Officer. Check for an overdue or unapproved week, and ask the Engineer/Architect for the reason in writing, which section 25.1 requires when a payment estimate is returned.
Can I pay apprentices less?
Apprentices and trainees in Department of Labor approved programs may be paid not less than 70 percent of the applicable rate, and the training certificate must accompany the weekly payroll reports (section 54.1(b)).

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Klamm Park Walking Trail, bid B32960 purchasing.wycokck.org
  2. Kensington Park Improvements, bid B41516 purchasing.wycokck.org
  3. Revisor of Statutes page for 44-201 ksrevisor.gov
  4. Revisor of Statutes chapter 44 index ksrevisor.gov
  5. 29 CFR 5.5(a)(3)(ii)(B) ecfr.gov

Questions about your Wyandotte County project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us