The short answer

CDBG-DR carries Davis-Bacon. Your payroll goes to the owner or subrecipient named in your contract, and grantees differ: Texas and Nebraska use labor standards officers, Kentucky a developer, Puerto Rico a subrecipient contact. A March 21, 2025 DOL waiver removes it for work finished before HUD signed the grant agreement, on public facilities and improvements under 2020 to 2023 grants. Confirm scope with your grantee.

  • DOL granted HUD a waiver on March 21, 2025, and Policy Bulletin 2025-02 says that, within the waiver's scope (2020 to 2023 grants under Public Laws 117-43, 117-180, 117-328), Davis-Bacon does not apply where all construction was completed before HUD signed the CDBG-DR grant agreement and funds only reimburse it; private housing is outside the waiver.
  • Under the same bulletin, construction ongoing on the agreement date is covered prospectively from that date, with no retroactive payroll for earlier work.
  • The bulletin's FAQ says the 2025 waiver does not apply to private housing construction.
  • A separate DOL letter dated June 25, 2020 gives the same prospective treatment to earlier CDBG-DR grants, and the bulletin says it covers 2015 to 2019 CDBG-DR grants and all CDBG-MIT grants.
  • Nebraska's chapter 14 says contractors typically submit payrolls within 10 business days after the payroll period ends, which is that grantee's timeframe and not a federal rule.

What is different about disaster recovery money

CDBG-DR grants are Community Development Block Grant disaster recovery funds, awarded under public laws after specific disasters. They carry the same Davis-Bacon duty as regular CDBG, because 24 CFR 570.603 applies Section 110 of the Housing and Community Development Act to labor financed with CDBG assistance. For the base rule, the $2,000 line and the clauses in your contract, read our CDBG page and the HUD-4010 guide.

Who you submit to: the grantee chain

HUD awards the grant to a grantee (bulletin). The grantee may hire contractors itself or pass money to a subrecipient. The Department of Labor's 2020 letter says the prevailing wage duty is the same either way: a contractor's workers are doing work financed by the program whether the state or a sub-grantee signed your contract.

Your payroll goes to the owner or subrecipient named in your contract, not to HUD, and grantees differ on who reviews it. The Texas General Land Office manual (version 17, March 2025) has each subrecipient designate a Labor Standards Officer who reviews certified payrolls. The Nebraska Department of Economic Development chapter also uses subrecipient labor standards officers and has payrolls go on to DOL through the state. Kentucky's developer training says contractors should submit payrolls to the developer weekly. Puerto Rico's handbook has the prime mail originals to the designated subrecipient point of contact.

The 2025 waiver: work finished before the grant agreement

Normally, if federal funding is approved after construction starts, the wage determination goes into the contract retroactively to the date of award or start of construction.

On March 21, 2025, DOL granted HUD a waiver of retroactive Davis-Bacon applicability for certain CDBG-DR projects. HUD's Policy Bulletin 2025-02 explains the result, measured against the date HUD signed the CDBG-DR grant agreement:

Your constructionDavis-Bacon under the waiver
All work finished before HUD signed, and CDBG-DR only reimburses itDoes not apply
Started before HUD signed and still ongoing on that dateApplies from that date forward, not to earlier work
Started after HUD signedApplies from the start, no change

Which jobs and which grants the waiver reaches

The bulletin says the waiver applies only to three things: public facilities and improvements, including infrastructure projects; projects where CDBG-DR funds are used as non-federal match for other federal grant programs, such as FEMA-funded projects; and CDBG-DR grants for 2020, 2021, 2022 and 2023 disasters under Public Laws 117-43, 117-180 and 117-328. Its FAQ says the waiver applies only to public facilities and improvements, including infrastructure, and not to private housing construction. Confirm with your grantee in writing that your contract is in scope.

Disaster yearPublic laws named in the bulletin
2020117-43
2021117-43, 117-180
2022117-180, 117-328
2023117-328

The 2020 waiver for older grants

The bulletin's footnote says HUD received a separate waiver in 2020 for 2015 through 2019 CDBG-DR grants and all CDBG-MIT grants, with the same prospective treatment for all construction contracts under them. DOL's June 25, 2020 letter adds one instruction for ongoing work: the contract specifications must include the Davis-Bacon clause and the wage determination in effect on the date the grant agreement was executed. HUD's August 2020 training slides define that date as the signing of the agreement for the specific year's disaster allocation.

What the waivers do not do

DOL's March 21, 2025 letter itself was not available to read; the rules above come from HUD's bulletin. The second limit comes from DOL's 2020 letter and the third from HUD's 2020 slides.

  • They do not change future work. The bulletin says construction that begins after the agreement date follows standard rules.
  • For 2015 to 2019 grants and CDBG-MIT, the 2020 waiver does not cover work funded by another Davis-Bacon statute. DOL's 2020 letter says that if other statutes apply, the Wage and Hour Division would need to rule on a separate waiver request, and without one those labor standards do not apply only prospectively.
  • As 2020 guidance for 2015 to 2019 grants and CDBG-MIT, for FEMA-funded work HUD's 2020 slides say Categories A and B emergency work, such as debris removal, generally is not covered and Categories C through G permanent work generally is.

If a grantee asks you to rebuild payroll

  1. Ask the labor standards officer for the date HUD signed the grant agreement and which grant, by disaster year, funds your contract.
  2. Write down your first and last day on site. Compare them with that date.
  3. Row 1 of the table above applies when three things are true: your grantee confirms in writing that the project is within the waiver, all your work finished before HUD signed the grant agreement, and CDBG-DR only reimburses that work.
  4. If you were working on that date, the bulletin says Davis-Bacon applies prospectively from it, but it does not say which wage determination governs ongoing work. Ask the grantee which one applies and prepare payroll for the weeks from that date. Only DOL's 2020 letter, for 2015 to 2019 grants and CDBG-MIT, says to use the wage determination in effect on the grant agreement date. The wage determination lookup guide shows how to read one.
  5. Get the grantee's answer in writing before you change payroll records.

Grantee rules differ: payroll timing and payment holds

The federal rule gives weekly payrolls. Deadlines, forms and holds come from each grantee's manual, so what follows is grantee-specific and not a federal rule. Read the manual your subrecipient cites.

Grantee and sourceWhat it says
Nebraska DED (chapter 14, 2022 upload)Prime submits payrolls to the subrecipient, typically no more than 10 business days after the payroll period ends. Payment requests wait for payrolls to be received and reviewed with discrepancies resolved. Section 14.11.4 sets a break-in-work rule for subcontractors.
Texas GLO (chapter 9, March 2025)Weekly payroll goes to the subrecipient promptly after each week, on WH-347 or a similar form, with the Statement of Compliance signed in ink by the owner or an authorized designee. For periods with covered construction, the Labor Standards Officer sends a payroll certification form with each payment request, unless GLO reviews all payrolls before payment. Payments to the prime may be withheld, for example when underpayments are not corrected within 30 days of notice.
Kentucky DLG (developer training, October 2025)Contractors send payrolls to the developer weekly. A payroll report goes to DLG when a new contractor or subcontractor starts. Final payment, less 10 percent retainage, waits until all payrolls and Statements of Compliance are in and reviewed.
Puerto Rico PRDOH (subrecipient handbook, September 2, 2021)WH-347 or equivalent with a wet-signed Statement of Compliance. The prime mails originals at least weekly. A Statement of Non-Performance replaces a payroll for each week with no work.

The no-work rules differ in that table, so check yours. See our no-work payroll guide. The form most of these grantees accept is the WH-347, explained in our WH-347 guide. Other states and agencies are compared on the state requirements page.

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

Does Davis-Bacon apply to every CDBG-DR job?
No. 24 CFR 570.603(a) applies the labor standards to nonvolunteer labor and limits residential rehabilitation coverage by unit count, and 570.603(b) says 24 CFR part 70 governs volunteers. HUD's 2020 guidance for 2015 to 2019 grants and CDBG-MIT adds that soft costs generally do not trigger it. Ask the subrecipient which clauses are in your contract.
My work finished before the grant was signed. Do I owe payrolls?
Under the March 21, 2025 waiver, no, if CDBG-DR only reimburses the finished work and your project is within the waiver's scope. The bulletin says the date to compare is when HUD signed the grant agreement.
I started before the grant agreement and am still working. What is owed?
Davis-Bacon applies from the date HUD signed the agreement, not to earlier work, per the bulletin.
Is the 10 business day payroll deadline a federal rule?
No. It is Nebraska DED's typical timeframe in its chapter 14. Other grantees use other wording, so follow the one your subrecipient names.
Does the waiver apply if FEMA also funds the job?
The bulletin covers CDBG-DR used as non-federal match for programs such as FEMA. The bulletin is silent on other Davis-Bacon statutes for 2020 to 2023 grants. For 2015 to 2019 grants and CDBG-MIT, DOL's 2020 letter says another Davis-Bacon statute needs its own waiver. Ask the grantee which funding source governs.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. HUD CDBG-DR Policy Bulletin 2025-02 hud.gov
  2. Department of Labor letter of June 25, 2020 hud.gov
  3. chapter 14 opportunity.nebraska.gov
  4. 24 CFR 570.603 govinfo.gov
  5. Texas General Land Office manual glo.texas.gov
  6. developer training dlg.ky.gov
  7. handbook cdn.recuperacion.pr.gov
  8. retroactively to the date of award or start of construction ecfr.gov
  9. August 2020 training slides hud.gov

Questions about your project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

CallContact us