Miami-Dade Responsible Wages: certified payroll in LCPtracker and the 20, 40 and 60 percent penalties

This page reads the county's 2026 Heavy, Building and Highway Responsible Wages and Benefits schedules, the county's Responsible Wages and Benefits page, and Florida Statutes 255.0992 and 218.077. It is a plain-language reading, not county or LCPtracker guidance.

Last reviewed against the sources it cites

The short answer

On Miami-Dade County contracts that still carry Responsible Wages and Benefits, every contractor and low-tier subcontractor submits certified payrolls in LCPtracker by the 10th of the month for the previous month. The county may fine an underpayment at 20, 40 and then 60 percent on top of back wages. The county says state law now limits the program to contracts awarded before July 1, 2024, plus surtax-funded projects and leases.

  • The county's 2026 schedules say LCPtracker is mandatory under Ordinance No. 18-33 and that each contractor and every low-tier subcontractor submits certified payrolls and labor compliance documentation by the 10th of every month for the previous month (Heavy schedule, section 3.B).
  • Section 2.B of the schedules lets the county fine 20 percent of the first underpayment, 40 percent of the second and 60 percent of the third and later ones, in addition to the back wages (Building schedule).
  • A fourth underpayment within three years subjects the contractor to debarment under the county's procedures and is a default of the contract (Highway schedule, section 2.B).
  • An underpayment notice gives a due date to pay or request a compliance meeting, and missing that date is a waiver of the meeting that the schedule treats as an admission (Heavy schedule, section 5.A).
  • LCPtracker will not let a contractor enter an apprentice on a certified payroll until the county approves the Apprenticeship Certification, which is valid for 90 days after issuance (Heavy schedule, section 6.A).
  • The county's page says state law limits Responsible Wages and Benefits to county contracts awarded before July 1, 2024, surtax-funded county projects and leases, with section 218.077 blocking new contracts and leases from Sept. 30 (county page).

You have an underpayment notice or a payment hold

After a complaint or a finding, the county investigates and sends the contractor or subcontractor a notice. Under section 5.A of the schedules, it states the back wages and fines in dollars, names the corrective action, and gives a due date to pay or to request a compliance meeting. Missing that date waives the meeting, and the schedule treats the waiver as an admission. The county can also hold your money: section 2.C lets it stop payment of the wages and penalties owed.

  1. Note two dates. The due date in the notice, and the date 30 days after the notice, which is the hearing deadline.
  2. Answer in writing before the due date. Pay the back wages and fines, or ask for the compliance meeting.
  3. To dispute the finding, request a hearing. Section 5.B calls for a written request to the County Mayor or designee within 30 days of the notice, with a $250 non-refundable filing fee.

A worker can sue instead of using the county process, but not in addition. The schedule gives a two year limit and says a court can award back pay, benefits, fees and costs, plus damages of up to $500 for each week of violation.

The penalty ladder

The county may fine at these rates (section 2.B), in addition to back wages.

StepWhat the schedule says
First underpaymentPenalty of 20 percent of the underpayment
Second underpaymentPenalty of 40 percent
Third and each later underpaymentPenalty of 60 percent
Fourth within three yearsDebarment to be initiated under the county's procedures. Also a default of the contract and cause for suspension or termination
Required payments not made in the specified timeThe firm and its principal owners are barred from county contracts for a period not to exceed three years
Violation other than underpaymentDamages of $500 for each week it remains outstanding. Failing to post the wage schedule at the site is a violation (section 1.F)

Contractors must also pay all back wages and penalties on previous contracts before being awarded or taking part in a new one (section 2.A), and the prime answers to a subcontractor's underpaid employees (section 4).

Is your job still covered?

The county's page says the program applies to county construction contracts over $100,000 and to privately funded construction on county-owned land valued at more than $5 million.

Section 255.0992 bars a political subdivision from requiring set wage rates or benefits on a public works project, with an exception for what federal or state law requires. It does not apply to contracts under chapter 337 or to a use authorized by s. 212.055(1) that voters approved. Section 218.077 separately bars using contracting to control contractors' wages or benefits. It leaves a county free to set wages for its own employees and for employers receiving a direct tax abatement or subsidy as a condition of it, and subsection (4) steps aside where compliance would cost federal funds.

Your jobWhat the county's page says
County construction contract awarded before July 1, 2024Still covered. The county lists contracts awarded before July 1, 2024 among those not affected by s. 218.077
Surtax-funded county project, or lease for privately funded construction on county land, awarded before Sept. 30, 2026Still covered
Surtax-funded project or lease awarded on or after Sept. 30, 2026Not among the groups the county says the s. 218.077 change did not impact. The county says that section further prevents it from requiring these wages and benefits on new contracts or leases
County construction contract awarded on or after July 1, 2024, not surtax-fundedNot among the categories the county says remain covered
Federal-aid or other federally required wage rulesBoth statutes make room for federal requirements. Our FDOT page covers payroll on federal-aid FDOT contracts

One window needs a written answer from the county. A note to s. 218.077 says its 2024 amendments do not impair any contract entered into before September 30, 2026, while the county ties its July 1, 2024 cutoff to s. 255.0992, whose 2026 text carries no such date. If your non-surtax county contract was awarded between those dates, ask whether Responsible Wages and LCPtracker apply. The county's page cites Code Sec. 2-11.16 as the source of the $100,000 and $5 million thresholds; the county code site refused our request, so this page relies on the county's page and schedules, which cite Ordinance No. 18-33 for LCPtracker. A separate Living Wage ordinance, Code Sec. 2-8.9, covers county service contracts (per the county's Contract Requirements page) and is not covered here.

How certified payroll works in LCPtracker

The Building, Highway and Heavy schedules carry identical general conditions, so this page applies to each.

Each contractor and every low-tier subcontractor must submit all certified payrolls and labor compliance documentation electronically by the 10th of every month for the previous month (section 3.B). The schedule calls LCPtracker mandatory under Ordinance No. 18-33 and names the Internal Compliance Department as its manager. The prime is responsible for the submissions, the records and county access to them, subcontractors included (section 3.C). The schedule does not define labor compliance documentation; ask the county what it expects. The county's Contract Requirements page also requires prime contractors and subcontractors to include the 10 Hour Safety Training Affidavit (RFTE 3) with each payroll and contractors to submit the Responsible Contractor Affidavit (RFTE 1); the schedules do not mention either.

LCPtracker's contractor guide says the agency or the prime creates every contractor account and the service is free to contractors. Fields marked with a red asterisk are required by the agency, and the system will not save without them. Cleveland uses the same system, as our Cleveland page explains.

  1. Get a login. Ask the prime or the county to add you to the project.
  2. Set up each worker. Records must show name, social security number, address, classification, hourly rates including fringes, and daily and weekly hours, signed under oath (section 3.A).
  3. Enter each week. The guide lists five routes: copy a prior week, upload a payroll export or Excel template, use a direct interface, or key it in. A worker in two classifications may be paid each rate for the time worked, and the payroll must show the time in each classification (section 1.C).
  4. Clear every notice. LCPtracker will not certify a payroll until they are cleared.
  5. Certify. Choose the project, payroll type and week-ending date, enter your own name and title, mark how fringes were paid (4a plan, 4b cash, 4c exceptions) and e-sign. The guide also lets you certify a week with no work.
  6. Correct by recertifying. The guide makes remarks mandatory when you recertify.

Apprentices and late payrolls

All apprentices must be approved in LCPtracker by the county. It will not let you enter an apprentice on a payroll until the county approves the Apprenticeship Certification, which the program sponsor sends and which is valid for 90 days after issuance (section 6.A). An unregistered apprentice, or one over the schedule's ratio, must be paid the schedule rate (sections 6.A and 6.B).

If a contractor fails to submit reports or make records available, section 3.C lets the county stop payments after written notice, and failing to submit reports on request may be a reason for debarment. The schedule names no fee for a late submission.

Where the county's own documents disagree

Which office. The schedules linked from the county's page, dated September 23, 2026 in their file names, name the Internal Compliance Department for complaints, classification questions and apprentice approval. Other copies, such as the Heavy schedule at an older address, name the Strategic Procurement Department, with otherwise the same general conditions. Take contacts from the county's page, which lists a Contracts Compliance and Monitoring Team under Internal Compliance.

Which payroll format. The schedules require LCPtracker. The county's Contract Requirements page tells Responsible Wages and Living Wage contractors to submit payroll on the WH-347 form (see our WH-347 guide) and still names Small Business Development. The two are not reconciled. Section 5.C says a breach of the schedule's clauses is a breach of the contract, so follow the schedule in your contract and get the county's answer in writing if your contract says otherwise. For other states, see our state requirements table.

We prepare certified payroll for public works contractors. Tell us about your project.

Questions

What happens if I miss the date in an underpayment notice?
Section 5.A waives the compliance meeting and treats the waiver as an admission. Section 5.B separately allows a hearing request within 30 days of the notice. The schedule does not link the two.
Does a county contract awarded after July 1, 2024 need LCPtracker?
The county's page says state law limits the program to contracts awarded before that date, surtax-funded projects and leases. If yours falls outside them, ask the county in writing whether the schedule applies.
Can I pay an apprentice rate right away?
No. LCPtracker will not accept the apprentice on a payroll until the county approves the Apprenticeship Certification.
Is the prime liable if a subcontractor underpays?
Yes. Section 4 says the prime is liable to the subcontractor's underpaid employees for each underpayment.

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Heavy documents.miamidade.gov
  2. Building documents.miamidade.gov
  3. Highway documents.miamidade.gov
  4. Responsible Wages and Benefits page miamidade.gov
  5. 255.0992 flsenate.gov
  6. 218.077 flsenate.gov
  7. Contract Requirements page miamidade.gov
  8. contractor guide kb.lcptracker.com
  9. Heavy schedule at an older address miamidade.gov

Questions about your county project

We prepare certified payroll for public works contractors in any state: the weekly federal WH-347 from the payroll export you already run, and state or agency payroll forms by arrangement. You review, sign and submit. Tell us the state, the agency and the system your job uses, and we reply the same business day.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.