Miami-Dade PHCD certified payroll: the CDBG and HOME rules and what holds a payment
This page reads the county's Policies and Procedures Manual page and its Chapter 5, Labor Standards, a document marked "Revised December 2010".
Last reviewed against the sources it cites
The short answer
On Miami-Dade CDBG and HOME construction, the county's labor standards chapter says payrolls go weekly to "the locality", the first marked "#I initial" and the last "Final", no later than seven calendar days after the work week ends. The manual is revised December 2010.
- The county's Chapter 5 says payrolls must be submitted weekly, the first titled "#I initial" and the last labeled "Final", within seven calendar days of the end of the work week (Chapter 5, revised December 2010).
- The chapter says at least five percent to twenty percent of each position classification must be interviewed, and the Project Manager compares weekly payrolls with those interviews (Chapter 5).
- The chapter lists weekly payroll and the Statement of Compliance among its labor documentation items, then draws, then retainage release (Chapter 5).
- The chapter states $10 per day per violation in liquidated damages for insufficient overtime pay, while the current federal contract clause in 29 CFR 5.5(b)(2) says $33 for each calendar day.
- The chapter says payroll deductions other than those required by law must be submitted to the program administrator on the payroll deduction authorization form (Chapter 5).
What the county publishes, and what it does not
Miami-Dade's housing department posts a manual for recipients of federal money. The county's page says it helps recipients manage federally funded projects. Chapter 5 is written for sub-recipients that engage or procure construction, and it mentions CDBG and HOME funds. It does not mention public housing.
The chapter is dated December 2010, its page footers call the agency DHCD, and parts of it still say "the State" and "locality". The county's policies page still links it. For delivery instructions, ask your Project Manager or use the county's contact page; the chapter does not say how to deliver payrolls.
Federal Davis-Bacon terms apply to this work under 29 CFR 5.5. The federal mechanics are on our housing authority page. This page covers only what Miami-Dade adds.
When does the chapter apply?
The chapter's applicability test lists four items: a government entity is involved, there is construction or alteration, laborers or mechanics are employed, and CDBG or HOME funds are used in full or in part. It adds that housing rehabilitation with fewer than eight units for CDBG, and fewer than 12 units for HOME, does not trigger Davis-Bacon, the Contract Work Hours and Safety Standards Act or the Copeland Act. That is the 2010 wording.
How often, to whom, and with what label
Chapter 5 gives these payroll rules.
- Submit payrolls weekly. The first is titled "#I initial" and the last is labeled "Final".
- Mark the "week ending" period clearly. Enter all data on each employee on the first payroll.
- Submit any supplemental or corrected payroll "in like manner".
- Get each payroll in no later than seven calendar days after the end of the work week. The chapter says payrolls go "to the locality" and leaves that term undefined, so ask your Project Manager who receives them.
The chapter's labor documentation list names the "Subcontractor's Certification Weekly Payroll (WH 347)" and a "Statement of Compliance". For how to fill the form and sign it, see our WH-347 guide and the HUD signature page.
The chapter also lists the payroll deductions it treats as permissible: those required by law, interest-free loans to the worker, the purchase price of U.S. notes, stamps or bonds, contributions to governmental, quasi-governmental or charitable organizations, and union fees. It adds that payroll deductions other than those required by law must be submitted to the program administrator using the payroll deduction authorization form.
Who reads your payroll, and how
The chapter makes the Project Manager responsible for monitoring. Weekly payrolls are reviewed and compared with employee interviews and wage rates to check minimum wages, overtime and ineligible deductions. The sub-recipient's contract file is to hold the payrolls "with evidence of their review", along with the interviews and any violations and the steps taken to resolve them.
Interviews
The chapter says on-site interviews must be done and that "at least five percent to twenty percent of each position classification must be interviewed". Interviews should cover a broad sampling of the work classifications on the project and are recorded on a Record of Employee Interviews form. Expect a monitor on site, and make sure the classifications on your payroll match the work people actually do. The federal side of interviews is on the HUD-11 page.
What can hold your payment
The chapter does not say that a late payroll stops a draw. It says these two things.
- Sequence. In its construction stage list, labor documentation comes first, then "Project Manager reviews contractor's draws", then "Contract close-out-release of retainage". The chapter does not state a payment condition for that list.
- Licensing. The chapter says the County Attorney's position is that the county is "not legally obligated to pay any invoices for construction if the correct licenses are not in place". It says the party doing the work needs at least an occupational license plus a certificate of competency or a general contractor's license.
Separately, chapter 5 section F says federally awarded funds cannot be used to engage a contractor during a period of debarment, suspension or ineligibility, and the Project Manager reviews the successful bidder and subcontractors against the debarment list. That is a check before award, not a payment hold.
The federal contract clause adds its own remedies. Under 29 CFR 5.5(a)(2)(i), the agency may withhold accrued payments or advances to cover unpaid wages and, after written notice, suspend further payment, advance or guarantee of funds until the violations have ceased. Under 29 CFR 5.5(a)(3)(iv)(B), if a contractor fails to submit the required records or refuses to permit worker interviews during working hours on the job, the Federal agency may, after written notice, cause the suspension of any further payment, advance or guarantee of funds. The same subparagraph says it can also be grounds for debarment under 29 CFR 5.12. A Miami-Dade manual that is silent on lateness does not remove that clause from your contract.
Liquidated damages: $10 or $33?
The chapter says failure to pay sufficient overtime "will result in the assessment of liquidated damages in the amount of $10 per day per violation", that only HUD and the Department of Labor may reduce or waive them, and that the contractor must be notified and may then request a waiver. The current federal clause in 29 CFR 5.5(b)(2) states $33 for each calendar day an individual worked over 40 hours without the required overtime pay, per laborer or mechanic. The $10 figure is the 2010 manual's. Use the figure written in your contract's clause. The $10 and $33 figures apply to overtime, not to a late payroll.
Where this is not the county's LCPtracker rule
Miami-Dade also runs a separate Responsible Wages program with LCPtracker and monthly due dates on county contracts. It is a different program with different rules. See our Miami-Dade Responsible Wages page.
If the job is federal-aid highway work in Florida, the rules come from FDOT instead. See the FDOT page.
We prepare certified payroll for public works contractors. Tell us about your project.
Questions
How soon is a Miami-Dade CDBG or HOME payroll due?
Does Chapter 5 cover public housing contractors?
What do I do if I miss the 7 day window?
How do I correct a payroll I already sent?
Will workers be interviewed?
Sources
Every figure on this page links to its source where it first appears. The full list, in order: