Certified payroll requirements for Long Beach City College Community District projects

What California public works subcontractors owe on projects where the awarding body is Long Beach City College Community District. Project counts on this page come from WellStanding's collection of DIR project registration data.

Data updated 2026-11-06

The short answer

On Long Beach City College Community District public works projects, you file electronic certified payroll records (eCPR) directly with DIR at least monthly, or more often when the contract says so, unless a DIR exemption covers the project. An upload to an awarding body or prime contractor portal does not replace that filing.

  • DIR eCPR: filed directly with DIR at least monthly, or more often when the contract says so, unless a DIR exemption applies (Labor Code 1771.4).
  • Portal: we have not verified one for Long Beach City College Community District. If your contract names a system, an upload there is the awarding body's copy and does not replace the DIR filing (DIR eCPR FAQ).
  • Federal payroll: every week, each submission with a signed Statement of Compliance, on contracts subject to the Davis-Bacon and Related Acts (U.S. Department of Labor).
  • Records on request: produce certified records within 10 days of a written request, or forfeit $100 per worker per calendar day (Labor Code 1776); $140 from January 1, 2027 (SB 909).
10 projects in WellStanding's collection of DIR project registration data, as of November 6, 2026
Required direct DIR eCPR filing on this body's projects, unless a DIR exemption applies

Counts cover registrations from June 26, 2026 to November 6, 2026. Collection paused from July 7 to September 3, 2026, so counts are a floor, not a total. Filing tile sources: DIR certified payroll FAQ, DIR eCPR exemptions page.

Recent Long Beach City College Community District project registrations

PWC-100 project registrations naming Long Beach City College Community District as the awarding body, from WellStanding's collection of DIR project registration data, as of November 6, 2026. Collection paused from July 7 to September 3, 2026, so counts are a floor, not a total. The list can miss projects registered in that window.

ProjectRegistered
Bid 27-003 Bldg D310/D311 Chemical Stock2026-11-06
Bid 27-002 Buildings EE and LL Refresh2026-11-06
Interior Painting 1st Floor, Bldg. LL2026-11-04
Floor replacement, Bldg. M, LAC2026-10-30
Mold Remediation, Bldg. T - Rm T13262026-10-30
AV System and installation, Bldg. T, LAC2026-10-14
Bid 27-001 Building EE Barbering Program2026-10-01
RFP 26-B006 North LB Student Housing2026-10-01

The portal situation

We have not verified a dedicated compliance portal for Long Beach City College Community District. Your contract documents are the source of truth: if a system like LCPtracker, Elation, or PRISM is named, uploads there are the awarding body's monitoring copy. Either way the direct DIR eCPR filing under your own registration is a separate, standing obligation on non-exempt projects (DIR eCPR FAQ).

Your filing duties on Long Beach City College Community District projects

  • Direct DIR eCPR filing. On a registered public works project you submit electronic certified payroll records directly to DIR at least monthly, or more often when the contract says so (Labor Code 1771.4). DIR is explicit that submitting certified payroll records to other agencies "does not put you in compliance with the state unless you submit eCPRs directly to DIR" (DIR eCPR FAQ).
  • Federal weekly payroll. Contracts subject to the Davis-Bacon and Related Acts require payroll information every week, each submission with a signed Statement of Compliance (U.S. Department of Labor).
  • Records on demand. You keep certified records and produce them within 10 days of receiving a written request. Miss it and you forfeit $100 for each calendar day, or part of a day, for each worker, and the Division of Labor Standards Enforcement can request that the penalty be withheld from progress payments then due (Labor Code 1776). From January 1, 2027, SB 909 (Chapter 660, Statutes of 2026) raises that penalty to $140 per worker per calendar day; what SB 909 changes.

Working for a city

Read the contract documents for the system or office that takes certified payroll on this city's projects, and confirm whether the project is one DIR exempts from the direct eCPR filing.

Trades recently listed on Long Beach City College Community District work

Contractor license classes listed on Long Beach City College Community District projects in WellStanding's collection of DIR project registration data, as of November 6, 2026. Collection paused from July 7 to September 3, 2026, so counts are a floor, not a total.

  • General building (B): 4 contractors
  • Painting and decorating (C-33): 1 contractor
  • Plumbing (C-36): 1 contractor
  • Electrical (C-10): 1 contractor
  • General engineering (A): 1 contractor

Sources

Every figure on this page links to its source where it first appears. The full list, in order:

  1. Labor Code 1771.4 leginfo.legislature.ca.gov
  2. DIR eCPR FAQ dir.ca.gov
  3. U.S. Department of Labor dol.gov
  4. Labor Code 1776 leginfo.legislature.ca.gov
  5. SB 909 leginfo.legislature.ca.gov
  6. DIR certified payroll FAQ dir.ca.gov
  7. DIR eCPR exemptions page dir.ca.gov

Filing on a Long Beach City College Community District project? First filing free

Send the payroll export you already run. We turn it into the WH-347 and the DIR eCPR filing, checked by software and verified by a person. First filing free, before you pay us anything. $995 one time setup, then $249 per month flat for crews up to 25 workers.

Got it. If your filing is due sooner, call us at 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.

Prefer the phone? Call 1-858-834-8430, Monday to Friday, 7:00 to 5:00 Pacific.